Master Patient Index (MPI) Project Update Presentation to NADB Nick Elcock 14 th January 2009.

Similar presentations


Presentation on theme: "Master Patient Index (MPI) Project Update Presentation to NADB Nick Elcock 14 th January 2009."— Presentation transcript:

1 Master Patient Index (MPI) Project Update Presentation to NADB Nick Elcock 14 th January 2009

2 The Business Need Patient Safety –To reduce duplicate records (resulting in partial clinical records) –To improve demographic data quality and reduce clerical errors. To support Trust Merger –To ensure that each patient has only one identity in the newly formed Trusts –To allow new information systems to be implemented across the whole Trust To support the implementation of the Welsh Clinical Portal –A single source of patient identity –Pointers to the location of clinical information

3 Data Quality Business Processes

4 WCP and the MPI

5 Why Not Use the WDS? WDS only holds demographic data and not the references to link to episodes of care. WDS is only populated with patients registered at Welsh GPs WDS is only updated by GPs

6 A National MPI As services start to be delivered as a national level: National MPI to supplement or supersede local MPIs National systems will link into the national MPI. (LIMS, PACS integration ? Future versions of WCP)

7 Approach Three stages but a detailed plan is only required for stage 1 1.Specification of Scope and Requirements 2.Procurement / Development 3.Implementation & post implementation review Stage 1 - Specification of Scope and Requirements 3 streams of work:- –Process Definition –Requirements Data Definition Functional Catalogue Technical requirements –Procurement/Development Planning Market evaluation In-house development proposal(s) Options appraisal and Business Justification Followed by a decision – AW procurement or In-house development

8 Resource & Governance Proposed Structure

9 Progress to date Project team in place with good representation across the Trusts Business Processes largely documented Functional and Technical requirements agreed Information requirements agreed Option appraisal has been developed.

10 Next steps MPI project board on 9 th January agreed: To work with NHS Trusts to develop a more detailed design To develop more detailed procurement plan To widen the project team to include WAST, HSW/ Velindre and Swansea University. To link into All Wales Medical Records Manager Group To ensure links into the single Record Project board and Patient Safety Group(s)

11 Budget No budget is in place currently for the MPI project. Initial estimates are for an average sized Trust: –Contract costs (if procured) : £250,000 –Local implementation costs : £200,000

12 Approval Sought To agree to this approach