ELC 347 project management
Day 24
2
Agenda Integrative Project Assignment 7 Corrected Quiz 3 is Corrected
Part 5 Feedback posted in File Exchange Any of the first five sections can be resubmitted for rescoring prior to finals week. The recorded score will the average of the original score and the score on the resubmitted section. Assignment 7 Corrected 8 A’s Quiz 3 is Corrected 1 A, 1 B, 4 C’s, 1 D and 1 no-take Everyone missed question on Critical Chain and buffers A project is represented by the activity durations (estimated at 90% likelihood of completion) and precedence requirements shown in the table. What is the length of the project buffer if this project is managed using critical chain methodology?
3
Schedule for rest of semester
Today Project ‘s 5 & 6 Dec 4 Group Work Dec 8 Chap 12 IP Part 6 due Dec 11 Chap 13 & 14 Assignment 8 due Dec 10 AM Quiz 4 Chap 12, 13 & 14 IP Project’s due © 2007 Prentice-Hall, Inc
4
Essentials Microsoft Project 2003 Dawn Parrish Wood Mary E. Pascarella
Modifying Task Information
5
Objectives Edit and replace task information and check spelling
Save a baseline Enter percent complete View percent complete Enter actuals Specify lead and lag time Resolve constraint conflicts and set a task deadline
6
Copyright © 2004 Prentice-Hall. All rights reserved.
Why would I Do This? To track project progress Task level Assignment level Requires assigned resources Time period Using different viewing options Copyright © 2004 Prentice-Hall. All rights reserved.
7
Copyright © 2004 Prentice-Hall. All rights reserved.
Visual Summary Baseline – original information to track progress Copyright © 2004 Prentice-Hall. All rights reserved.
8
Editing and Replacing Task Information and Checking Spelling
Effort-driven scheduling Default setting Resource adjustments Reflected in overall project completion dates Copyright © 2004 Prentice-Hall. All rights reserved.
9
Copyright © 2004 Prentice-Hall. All rights reserved.
Task Usage View View the specific task Double-click to open task information Copyright © 2004 Prentice-Hall. All rights reserved.
10
Task Information Dialog Box
Copyright © 2004 Prentice-Hall. All rights reserved.
11
Task Modification Results
Copyright © 2004 Prentice-Hall. All rights reserved.
12
Copyright © 2004 Prentice-Hall. All rights reserved.
Find And Replace Copyright © 2004 Prentice-Hall. All rights reserved.
13
Copyright © 2004 Prentice-Hall. All rights reserved.
Spell Check Copyright © 2004 Prentice-Hall. All rights reserved.
14
Copyright © 2004 Prentice-Hall. All rights reserved.
Saving A Baseline Copyright © 2004 Prentice-Hall. All rights reserved.
15
Copyright © 2004 Prentice-Hall. All rights reserved.
Print Baseline Data Hide Gantt Chart portion of the Tracking Gantt View Ready for print Copyright © 2004 Prentice-Hall. All rights reserved.
16
Entering Percent Complete
Task Information dialog box Tracking toolbar Copyright © 2004 Prentice-Hall. All rights reserved.
17
Tracking Toolbar Up Close
Copyright © 2004 Prentice-Hall. All rights reserved.
18
Viewing Percent Complete
Easiest methods Gantt Chart Percent complete column Background calculations Actual duration Remaining duration Copyright © 2004 Prentice-Hall. All rights reserved.
19
Copyright © 2004 Prentice-Hall. All rights reserved.
Gantt Chart View Copyright © 2004 Prentice-Hall. All rights reserved.
20
Adding Percent Complete Column
Copyright © 2004 Prentice-Hall. All rights reserved.
21
Copyright © 2004 Prentice-Hall. All rights reserved.
Entering Actuals Alternate work progress tracking Actual work Finish dates Work durations Related fields automatically updated Copyright © 2004 Prentice-Hall. All rights reserved.
22
Modifying Task Information
Using the Tracking Table Copyright © 2004 Prentice-Hall. All rights reserved.
23
Specifying Lead and Lag Time
Lead time Task overlap Negative number Lag time Time needed between tasks Positive number Copyright © 2004 Prentice-Hall. All rights reserved.
24
Copyright © 2004 Prentice-Hall. All rights reserved.
Create Lead/Lag Time Copyright © 2004 Prentice-Hall. All rights reserved.
25
Resolving Constraint Conflicts And Setting A Task Deadline
Copyright © 2004 Prentice-Hall. All rights reserved.
26
Copyright © 2004 Prentice-Hall. All rights reserved.
Constraint Date Table Results of removing a constraint Copyright © 2004 Prentice-Hall. All rights reserved.
27
Copyright © 2004 Prentice-Hall. All rights reserved.
Deadlines Target dates Task Information dialog box Technically not constraints Indicator icon appears if deadline passes Copyright © 2004 Prentice-Hall. All rights reserved.
28
Summary Edit and replace task information and check spelling
Save a baseline Enter percent complete View percent complete Enter actuals Specify lead and lag time Resolve constraint conflicts and set a task deadline
29
Review Options Key terms Checking concepts and terms Discussion
Skill drill Challenge
30
What are your questions?
Copyright © 2004 Prentice-Hall. All rights reserved.
31
Essentials Microsoft Project 2003 Dawn Parrish Wood Mary E. Pascarella
Modifying Tasks Using The Gantt Chart
32
Objectives Add a progress line to a Gantt chart
Remove task dependencies Reschedule uncompleted work Modify and remove a split Use Tracking Gantt view to analyze the critical path Check overall project progress
33
Why would I Do This? Budget Time constraints Scope
To monitor progress in the three main project areas Budget Time constraints Scope Copyright © 2004 Prentice-Hall. All rights reserved.
34
Copyright © 2004 Prentice-Hall. All rights reserved.
Visual Summary Advertising campaign Copyright © 2004 Prentice-Hall. All rights reserved.
35
Progress Line In A Gantt Chart
Quick visual reference Copyright © 2004 Prentice-Hall. All rights reserved.
36
To Add Progress Lines to a Gantt Chart
Project information Copyright © 2004 Prentice-Hall. All rights reserved.
37
Progress Line Dialog Box
Copyright © 2004 Prentice-Hall. All rights reserved.
38
Copyright © 2004 Prentice-Hall. All rights reserved.
Actual Progress Line Right spike = ahead Left spike = behind Copyright © 2004 Prentice-Hall. All rights reserved.
39
Modifying A Specific Task
Double-click task to get Task Information dialog box Copyright © 2004 Prentice-Hall. All rights reserved.
40
Copyright © 2004 Prentice-Hall. All rights reserved.
Results Of Change Copyright © 2004 Prentice-Hall. All rights reserved.
41
Removing Task Dependencies
No longer needed View task Screen Tip Copyright © 2004 Prentice-Hall. All rights reserved.
42
Copyright © 2004 Prentice-Hall. All rights reserved.
Unlink Tasks Copyright © 2004 Prentice-Hall. All rights reserved.
43
Rescheduling Uncompleted Work
Splitting a task … Copyright © 2004 Prentice-Hall. All rights reserved.
44
Split Task Screen Feedback
… Copyright © 2004 Prentice-Hall. All rights reserved.
45
Modifying And Removing A Split
Adjust for changes in the project Change the unit of time Default is one unit Remove the split … Copyright © 2004 Prentice-Hall. All rights reserved.
46
To Modify And Remove The Split
Copyright © 2004 Prentice-Hall. All rights reserved.
47
Using Tracking Gantt View To Analyze The Critical Path
Predecessors Critical tasks Tracking Gantt view Baseline bar Comparison to actual Variance task table Copyright © 2004 Prentice-Hall. All rights reserved.
48
Tracking Gantt Chart Display
Copyright © 2004 Prentice-Hall. All rights reserved.
49
Critical Task And ScreenTip
Copyright © 2004 Prentice-Hall. All rights reserved.
50
Changing Date Of Critical Task
Changes project completion date Copyright © 2004 Prentice-Hall. All rights reserved.
51
Checking Overall Project Progress
Project statistics Up-to-the-minute statistics View only Project summary report outlines actual and baseline data Tracking Gantt view Copyright © 2004 Prentice-Hall. All rights reserved.
52
Copyright © 2004 Prentice-Hall. All rights reserved.
Project Statistics Copyright © 2004 Prentice-Hall. All rights reserved.
53
Project Summary Report
Copyright © 2004 Prentice-Hall. All rights reserved.
54
Copyright © 2004 Prentice-Hall. All rights reserved.
Tracking Gantt View Copyright © 2004 Prentice-Hall. All rights reserved.
55
Summary Add a progress line to a Gantt chart Remove task dependencies
Reschedule uncompleted work Modify and remove a split Use Tracking Gantt view to analyze the critical path Check overall project progress
56
Review Options Key terms Checking concepts and terms Discussion
Skill drill Challenge
57
What are your questions?
Copyright © 2004 Prentice-Hall. All rights reserved.