Presentation is loading. Please wait.

Presentation is loading. Please wait.

WEC Library & Teaching Rooms Refurbishement Project

Similar presentations


Presentation on theme: "WEC Library & Teaching Rooms Refurbishement Project"— Presentation transcript:

1 WEC Library & Teaching Rooms Refurbishement Project

2 Project Communication Presentation
Purpose of today; For WEC building users to undertand the scope, programme and impact of the summer works. The team Scope/areas of work Key dates Logistics Noisy works Contacts and meetings

3 The team Estates Project Manager – Raghbir Nagra
External Project manager – (Mace) Mark Jaloszynski Design & Build Contractor – (ISG) Andy Thorogood Client Design Team Wilson Mason Elementa Ross & Partners

4 Scope of works - Library
Presentation title footer

5 Scope of works - Library
Presentation title footer

6 Scope of works - Library
Presentation title footer

7 Scope of works - Library
Presentation title footer

8 Scope of works – Teaching Rooms
Presentation title footer

9 Scope of works – Teaching Rooms
Presentation title footer

10 Key dates Teaching room construction 25th June to 17th September
Library closes to staff and students 25th June Construction works commence 9th July Library open th October ISG operate a double shift 08:00 – 18:00 and 18:00 to 01:00. Noisy works, deliveries and corridor refurb will be undertaken during the 2nd shift to minimise building disruption.

11 Logistics Compound Plan Temporary toilets Level 2 Gantry
Access / egress staircase Storage container 1000kg beam hoist Hoarding Sp Security checkpoint Opening cut into brick wall – gates formed in hoarding Sp

12 Noisy works Low impact/noise activities during the day (still will be activities continuing) Heavy demolition, drilling, cutting to be completed during 2nd shift, post 18:00 and/or weekends Deliveries and bulk material movements post 18:00 can be via main entrance.…during the day, via scaffold gantry Lift only used post 18:00 Corridor refurbishment out of hours Corridor accessible during the day; always safe and clear

13 Reporting/communications
Raghbir Nagra (KCL Estates) Mark Jaloszynski (Mace) Andy Thorogood (ISG) Sub contractors Sub Contractors Questions & complaints

14 Reporting/communications
External liaison sessions every Tuesday 15:30-16:00 from 3rd July in the WEC Refectory. Mark Jaloszynski Ext 5785 or (or Jonathan Kirby ) 2nd floor office opposite boardroom Raghbir Nagra Ext 6926 or

15 WEC Library & Teaching Rooms Refurbishement Project
Questions…..


Download ppt "WEC Library & Teaching Rooms Refurbishement Project"

Similar presentations


Ads by Google