2 1 Draft License Application DLA comment period ended December 27, 2010 Received 17 comment letters  FERC – 2  Resource Agencies – 5  NGOs – 5  Members of the Public – 5

3 2 Final License Application  To be filed with FERC no later than February 28, 2011  Includes response to comments table and modifications to Draft License Application  All participants will receive electronic version consistent with CEII, Confidential, and Privileged requirements

4 3 Final License Application Distribution  Relicensing participants that received paper copies of the DLA will be issued revised copies : VolumeContentsDistribution Vol 1Initial Statement, Exhibits A, B, C, D, G, and H (Public Information) Revised volume Vol 2Exhibit F (Critical Energy Infrastructure Information [CEII]) Only provided to FERC Vol 3 Books 1– 4 Exhibit E SD A – Proposed Environmental Measures (Public Information) Revised volume Vol 3 Books 5–11 Exhibit E SD B – Final Technical Study Reports (Public Information) Replacement pages Vol 3 Book 12 Exhibit E SD C – BA/BE (Public Information) Revised volume Vol 4Exhibit E and Supporting Documents (SD A and SD B) (Confidential Information) Select distribution of replacement pages Vol 5Exhibit E Supporting Documents SD D – Final Cultural Technical Study Reports SD E – Draft HPMP (Privileged Information) Select distribution of replacement pages

5 4 FERC Relicensing Timeline (Following Submittal of the Final License Application) Does not assume continued negotiation

6 5 Proposed Negotiation Process  Submit a request to FERC for additional time and a delay of issuance of the Notice of Ready for Environmental Analysis to complete negotiations on Proposed PM&E Measures  Continue collaboration with the stakeholders post-filing of the FLA (March through June 2011)  Develop Supplemental Information including rationale supporting consensus of PCWA and Relicensing Participants on resolved issues (if applicable)  Submit Supplemental Information to FERC on November 1, 2011

7 6 Proposed Negotiation Major Topic Areas  Flow and Reservoir Monitoring Plan  Instream Flow and Reservoir Minimum Pool Measure  Recreation Plan  Vegetation and Integrated Pest Management Plan  Others?

8 7 Develop Collaboration Schedule

9 8 Relicensing Participant Letter to FERC (handout)   Discuss and edit letter to FERC