PORTFOLIO COMMITTEE ON CORRECTIONAL SERVICE PRESENTED BY SITA 27 February 2013.

Similar presentations


Presentation on theme: "PORTFOLIO COMMITTEE ON CORRECTIONAL SERVICE PRESENTED BY SITA 27 February 2013."— Presentation transcript:

1 PORTFOLIO COMMITTEE ON CORRECTIONAL SERVICE PRESENTED BY SITA 27 February 2013

2 BACKGROUND  The following matters were raised at previous Department of Correctional Services (DCS) Portfolio Committee held on 12 September 2012 and SITA is to report on the findings.  Signing of Business Agreement  Outstanding SITA payments  RDOMS -Remand Detainee  Progress on VPN Migration 2

3 SITA’s intervention to DCS Challenges ISSUEPROPOSED SOLUTIONSTATUS Signing of the current Business Agreement A new BA workshopped and submitted to DCS for signature Engaging with GITO for further negotiation Delays in payments to SITA DCS to effect payments for outstanding debt to avoid accumulating interest on overdue account 2012-13 Payments are paid regularly. Balance at R44mil of which R10mil is current financial year. R34 mil disputesDCS requested supporting documents on outstanding invoices SITA has retrieved supporting documents to the value of R18mil and will complete the process in 3months 3

4 SITA’s intervention to DCS Challenges ISSUEPROPOSED SOLUTIONSTATUS RDOMS-Remand Detainee and Offender Management System SITA, DCS and Dimension Data to find a solution towards completing the project. Meeting held between the 3 parties to outline the way forward. SITA recommends further engagements with the SITA CEO, DCS Commissioner and Dimension Data Chairperson to resolve the matter amicably. 4

5 STATUS OF DCS DEBT TO SITA Current 1-30 Days 4,749,207.41 31-60 Days 405,720.00 61-90 Days 889,433.67 91-180 Days 3,646,212.32 181-360 Days 612,986.37 361+ Days 33,797,399.14 TOTAL 44,100,386.91 R34 million 5

6 STRATEGIC PROJECTS PROJECTBENEFITSTATUS Virtual Private Network (VPN) -Migration of +/- 400 sites to the SITA NGN Secure connections to or from foreign networks through Common Access Point (CAP) with high Quality of Service (QoS) Migration to SITA VPN is scheduled 1-3 March 2013 6

7 Thank you


Download ppt "PORTFOLIO COMMITTEE ON CORRECTIONAL SERVICE PRESENTED BY SITA 27 February 2013."