Presentation is loading. Please wait.

Presentation is loading. Please wait.

Texas Pollutant Discharge Elimination System Stormwater Construction General Permit (CGP) 2013 TCEQ Environmental Trade Fair April 30 – May 1, 2013 Lindsay.

Similar presentations


Presentation on theme: "Texas Pollutant Discharge Elimination System Stormwater Construction General Permit (CGP) 2013 TCEQ Environmental Trade Fair April 30 – May 1, 2013 Lindsay."— Presentation transcript:

1 Texas Pollutant Discharge Elimination System Stormwater Construction General Permit (CGP) 2013 TCEQ Environmental Trade Fair April 30 – May 1, 2013 Lindsay Garza & Hal Bailey Stormwater & Pretreatment Team (512) 239-4671 (512) 239-4671

2 TPDES CGP, TXR150000  Construction General Permit (CGP), TPDES Permit No. TXR150000 Effective March 5, 2013 Expires March 5, 2018  Authorizations NOIs: > 19,000

3 What Does the Permit Cover?  Discharges of stormwater from soil disturbances due to construction activity Small Construction = 1 acre to less than 5 acres Large Construction = 5 acres or more Includes sites less than 1 acre that are part of a larger common plan of development or sale Sites less than 1 acre that are not part of a larger common plan of development or sale are exempt

4 Soil Disturbance Due to Construction Activity  clearing  grading  excavating  demolition, or  similar activities that disturb or expose soil Examples

5 Activities not considered to be construction for the purposes of this permit  routine grading of existing roads  routine maintenance of stormwater conveyances  land disturbance from agricultural activities

6 Larger Common Plan of Development or Sale  A construction activity completed in separate stages, phases, or in combination with other construction activities  Identified by documentation showing the scope of the construction project  Documentation may include plats, blue prints, marketing plans, contracts, building permits, zoning requests, etc.

7 A construction project is not part of a larger common plan of development if:  The project is considered to be discrete or stand alone and not part of any other construction project or larger common plan of development or sale OR OR  It is a discrete project within a common plan of development that is ¼ mile or more from the nearest site, and: all land disturbance between projects is completed (will not be further built out), andall land disturbance between projects is completed (will not be further built out), and not connected by roads, pipelines, or utility construction projects that are included in the area to be disturbednot connected by roads, pipelines, or utility construction projects that are included in the area to be disturbed

8 A construction project is no longer a part of a larger common plan of development if:  there is less than 1 acre left to be built out in the larger common plan AND AND  there has been a clearly definable amount of time since the last construction activity

9 TXR150000 also covers…  Stormwater discharges from concrete batch plants located at construction sites  Concrete truck washout water from trucks associated with an on-site and off-site batch plants permitted under TXG110000 washout water must be discharged to areas where structural controls have been established as described in the general permitwashout water must be discharged to areas where structural controls have been established as described in the general permit

10 Who Needs a Permit? Primary Operator erson(s) with on-site operational control over construction plans and specifications, including the ability to make changes to those plans and specifications  Person(s) with on-site operational control over construction plans and specifications, including the ability to make changes to those plans and specifications OR OR erson(s) with day-to-day operational control of those activities at a site that are necessary to ensure compliance with a stormwater pollution prevention plan (SWP3)  Person(s) with day-to-day operational control of those activities at a site that are necessary to ensure compliance with a stormwater pollution prevention plan (SWP3)

11 Who Needs a Permit? Secondary Operator  A person whose operational control is limited only to all or part of the following: Employment of other operatorsEmployment of other operators OR OR Ability to approve or disapprove changes to the plans and specificationsAbility to approve or disapprove changes to the plans and specifications

12 Requirements of Primary Operators for Large Construction Activities  Develop and implement an SWP3 and maintain a copy on-site (update as necessary)  Submit a completed Notice of Intent (NOI) and application fee  Send a copy of NOI to the MS4 operator 7 days prior to starting construction activity  Post a copy of the primary operator site notice on-site  Meet final stabilization requirements  Submit a Notice of Termination (NOT) to the TCEQ and a copy to the MS4

13 Requirements of Secondary Operators for Large Construction Activities  Participate in the development of the SWP3 (according to the permit requirements) and sign the SWP3  Complete and post a copy of the secondary operator site notice at the site  Submit a copy of the completed site notice or alternative notification to the local MS4 (no NOT required)

14 Stormwater Pollution Prevention Plan Basics  The SWP3 must be: developed before submitting the NOIdeveloped before submitting the NOI implemented before commencing construction activityimplemented before commencing construction activity retained on siteretained on site consistent with other regulationsconsistent with other regulations continuously updated to reflect changes at the construction sitecontinuously updated to reflect changes at the construction site

15 Effective Date of Authorization  Authorization for coverage of large construction is: provisional and begins 7 days after a paper NOI is postmarkedprovisional and begins 7 days after a paper NOI is postmarkedOR immediate upon submitting a NOI using the e-Permits systemimmediate upon submitting a NOI using the e-Permits system  Authorization for coverage of small construction is: automatic on condition of complying with applicable permit requirementsautomatic on condition of complying with applicable permit requirements

16 Electronic e-NOI vs. Paper NOI  e-NOI has a lower application fee $225 for e-NOI vs. $325 for paper NOI$225 for e-NOI vs. $325 for paper NOI  e-NOI allows for immediate authorization of coverage  Immediate retrieval of approval letter and certificate upon submittal of e-NOI

17 Correcting or Updating Information in the NOI  Fill out and submit a Notice of Change (NOC) form to make: changes to incorrect information on the NOI (typographical errors, incorrect site address or acreage, etc.) changes to incorrect information on the NOI (typographical errors, incorrect site address or acreage, etc.) changes due to expansion of the project (additional acreage, starting a new phase) changes due to expansion of the project (additional acreage, starting a new phase)  The SWP3 may need to be updated with changes submitted in an NOC

18 Inspection Frequencies  For most sites: once every 14 days and within 24 hours after a storm event of 0.5 inches or greateronce every 14 days and within 24 hours after a storm event of 0.5 inches or greater OR OR at least once every 7 calendar daysat least once every 7 calendar days  For sites in an arid or semi-arid or drought stricken area: inspect at least once per month; andinspect at least once per month; and within 24 hours after a storm event of 0.5 inches or greaterwithin 24 hours after a storm event of 0.5 inches or greater

19 Construction Site Inspections  If snow or ice covers the site: inspect at least once per month; andinspect at least once per month; and return to previous inspection frequency once snow and ice start melting, causing stormwater runoff from the sitereturn to previous inspection frequency once snow and ice start melting, causing stormwater runoff from the site  If flooding prevents access to the site: inspect as soon as access is practicableinspect as soon as access is practicable

20 Termination Requirements for Large Construction Activities  Primary Operators must: meet final stabilization requirements remove temporary best management practices (BMPs) remove primary operator site notice submit NOT to TCEQ Submit copy of NOT to MS4 operator (if applicable)  Secondary Operators must: remove secondary operator site notice Send completed copy of the site notice to the MS4 (if applicable)

21 Termination Requirements for Small Construction Activities  Both primary and secondary operators must: meet final stabilization requirementsmeet final stabilization requirements remove temporary BMPsremove temporary BMPs remove their site noticeremove their site notice each operator must:each operator must: send a copy of their completed Small Construction Site Notice to the MS4 operator (if applicable) orsend a copy of their completed Small Construction Site Notice to the MS4 operator (if applicable) or provide alternative notification as allowed by the MS4 operatorprovide alternative notification as allowed by the MS4 operator

22 Final Stabilization Requirements  All soil disturbing activities completed  Even distribution of perennial cover to a density of 70% of native background  Excludes areas that are: paved, paved, covered by permanent structures, or covered by permanent structures, or covered with equivalent permanent stabilization measures covered with equivalent permanent stabilization measures

23 TXR150000 Renewal  Renewal process began - September 2011  Stakeholder meeting – February 21, 2012  EPA 90-day review: May – August 2012  Notice published in the October 12, 2012 issue of the Texas Register and in nine (9) newspapers throughout the state  Permit expires – March 5, 2018  A public meeting was held on November 12, 2012 and the public comment period ended at the close of the meeting

24 TXR150000 Renewal  Response to Comments – November 2012  Agenda for adoption – February 12, 2013  Permit issuance – February 19, 2013  Permit effective – March 5, 2013  Permit expires – March 5, 2018  Renewed CGP, fact sheet, and RTC are available on the TCEQ construction stormwater web page

25 TXR150000 Renewal  Revised NOI and Waiver forms available  Updated site notices available  New instructions on how to register with STEERS and set up a user account  90 day renewal period – ends June 3, 2013

26 Changes from the Previous Permit  Added narrative BMPs for regulated construction sites based on the federal ELGs at 40 CFR Part 450 based on the federal ELGs at 40 CFR Part 450  Impaired Receiving Waters and Total Maximum Daily Load (TMDL) Requirements Construction sites that discharge to impaired waters with an approved TMDL must have an SWP3 that is consistent with the:Construction sites that discharge to impaired waters with an approved TMDL must have an SWP3 that is consistent with the: applicable TMDL orapplicable TMDL or Implementation Plan (I-Plan)Implementation Plan (I-Plan)

27 Changes from Previous Permit  Clarified the definition of secondary operator  Removed the requirement for the primary operator to post a copy of the signed NOI  Extended the allowance for the on-site disposal of concrete truck wash out water to include trucks from on-site batch plants  Added definitions  Clarified existing permit requirements  Removed site notices from permit

28 40 CFR Part 450 – Construction ELGs  December 1, 2009 – EPA published effluent limitations guidelines (ELGs) and new source performance standards (NSPS) to control the discharge of pollutants from construction sites. Also known as the “C&D rule.”  The new ELGs were effective on February 1, 2010  January 4, 2011 - Numeric turbidity limitation was stayed  C&D rule requires BMPs for all sites

29 40 CFR Part 450 – Construction ELGs  Rule applies to large and small sites  Applies to all disturbed areas of a site  No numeric effluent limits (narrative requirements only)  February 16, 2012 – EPA issued their NPDES CGP  ELGs incorporated into TCEQ’s 2013 CGP renewal

30 Web Links for Resources TCEQ Stormwater Home Page: http://www.tceq.texas.gov/permitting/stormwater/sw_permits.html TCEQ Construction Stormwater Web page www.tceq.texas.gov/permitting/stormwater/wq_construction.html Small Business and Local Government Assistance: www.tceq.texas.gov/assistance Status of Stormwater NOIs: http://www2.tceq.texas.gov/wq_dpa/index.cfm Link to “Water Quality General Permits Search” data base

31 Web Links for Resources EPA SWP3 Guidance: http://cfpub.epa.gov/npdes/stormwater/swppp.cfm EPA National Menu of BMPs: http://cfpub.epa.gov/npdes/stormwater/menuofbmps/index.cfm Link to “Construction” and “Post-Construction”

32 TCEQ Stormwater Program Contacts Rebecca L. Villalba, Team LeaderRebecca L. Villalba, Team Leader Hanne Lehman NielsenHanne Lehman Nielsen Dan SiebeneicherDan Siebeneicher Hal BaileyHal Bailey Lindsay GarzaLindsay Garza Austin Office (512) 239-4671Austin Office (512) 239-4671 SWGP@tceq.texas.govSWGP@tceq.texas.gov

33 TCEQ Stormwater Program Contacts Questions regarding your STEERS account:Questions regarding your STEERS account: –(512) 239-6925 Questions about the application process, contact the Stormwater Processing CenterQuestions about the application process, contact the Stormwater Processing Center – (512) 239-3700 Other questions including Technical, contact the Small Business and Local Government (SBLGA) HotlineOther questions including Technical, contact the Small Business and Local Government (SBLGA) Hotline –1-800-447-2827


Download ppt "Texas Pollutant Discharge Elimination System Stormwater Construction General Permit (CGP) 2013 TCEQ Environmental Trade Fair April 30 – May 1, 2013 Lindsay."

Similar presentations


Ads by Google