1 Virtis-Opis Beta Testing Todd S. Thompson, PE South Dakota DOT Office of Bridge Design August 3, 2011

2 How does this work? So you want to be a Beta Tester? Or maybe you are a Beta Tester? How do I fit in the development process? What is Beta testing? What is Alpha testing? Am I in the wrong presentation?

3

4 AASHTOWARE Standards and Guidelines http://www.aashtoware.org/Documents/07012010 %20SnG%20Notebook.pdf Policies, Guidelines and Procedures http://www.aashtoware.org/Documents/PGP- October2009final.pdf

5 Lifecycle

6

7 Testing & More Testing Contractor Testing –Unit –Build –System –Alpha Task Force Testing (Beta TAG) –Beta

8 Contractor Testing Unit testing –Is performed on each class/object or program module to reduce the complexity of testing the entire system. Build testing –Is the means used for testing a component that is made up of lesser components (units or other builds).

9 Contractor Testing System testing –Is used to test the system as a whole and to ensure that the integration is completed and that the system performs as required. –Ensures that all user and system requirements are met –Allows the contractor to prepare for alpha testing and ensures that the product is complete and ready for formal alpha testing and the subsequent acceptance.

10 Contractor Testing Alpha testing –Covers the same system and system components as System Testing. –The emphasis is, however, on breaking the system, checking the user and system requirements, and reviewing all documentation for completeness by using the application as if it were in production.

11 Contractor Testing Alpha testing complete –Contractor documents everything is complete, tested and meets all the requirements –Task Force accepts and approves the start of Beta Testing

12 Beta Testing Beta TAG role –Confirm operational and functionality requirements are satisfied –Operates in users’ environment –Review of documentation –Confirm ready to implement

13 Beta Testing Beta TAG Chair/Contractor –Confirm all the various user environments are covered Operating Systems Databases Design vs Rating

14 Beta Testing Cycle Installation problems are reported Contractor resolves installation issues and re-distributes material, as necessary Testers perform their work and report problems Contractor validates and fixes problems

15

16 Beta Testing Process Test using YOUR bridges Report Bugs to Support Center Confirm bugs were fixed in subsequent release(s) Recommend (or not) Acceptance Release is ready for production

17 What to test? Test variety of your typical bridges Migrate your database –Copy of your production DB? –And/Or copy of your “testing DB”? Test just like you were going to migrate to the next version in production

18 What to test? Confirm bridges with valid results are still valid Review new enhancements and confirm they work

19 Test or Check? Is there a difference? What is the difference of testing software or checking software?

20 Checking Software Is confirming existing beliefs Is a validation or verification Is often done by programmers as they work – making sure they don’t break something Is focusing on making sure the program doesn’t fail

21 Testing Software Something done with motivation to learn something new Process of exploratory, discovery, investigation and learning Trying to find limits Trying to find everything about the program that works and does NOT work

22 Checking vs Testing Checking provides a yes or no Checking answers the question “Does this assertion pass or fail?” Testing is open ended Testing is “Is there a problem here?”

23 Checking vs Testing Checking doesn’t let us know if the program works – it only lets us know it’s working within the scope of our expectation(s) Testing is, in part, finding out if our checks are good enough

24 Checking vs Testing Testing involves some checking, but if it only involves checking, it will be poor testing Testing involves curiosity and exploration and can’t be automated – it involves human intervention

25 Checking vs Testing If we find a problem in testing, the checks need to be revised so that the problem doesn’t happen again Automated testing is really automated checking Any “testing” that is looking for a yes/no or an expected result is actually checking

26 Find a bug? Document any and all errors or bugs you find

27

28 Documenting Confirm your problem/issue –Provide the bridge XML –Explain how it happens –Screenshots of error or problem –Explain what it should be –Engine, DB, OS, etc

29

30 Test New Features Review new Enhancements –Plan out what you can test –E.g. if you don’t have floor trusses – don’t plan on testing that portion.

31 Global Testing Check Final results of various bridges –I have various groups of bridges that have “accepted” results –Compare those RF’s with new release(s) –Use of spreadsheet(s) to quickly compare results Look at the “final” result and compare

32 Global Testing Quick and fairly easy way to feel comfortable with new release –Your bridges –Your results –Good comparison –Identify potential problems

33 Global Testing Compare Final LF Rating Results with previous version Brass LF 6.2 vs AAHSTO LF 6.3 HS 20 –INV RF = 1.108 (Version 6.2) –INV RF = 1.087 (Version 6.3) –Only 2% difference – say ok

34 Global Testing Life is easy when everything matches But what to do when you get differences? –Confirm same bridge data (same input) –Confirm bridge properties –Confirm same load effects (DL and LL) –Confirm capacities –Confirm rating factors (if load rating)

35 Global Testing When you get differences – you need your detective hat Think about what input affects the results and where the difference could be found –Spec Change? –Corrected previous error/bug?

36 Global Testing The more data you can confirm The better you can isolate the difference Greatly reduces the time the developer needs to try to figure out what and where the problem is and get a successful fix.

37 “Local” Testing Looking into the deep and dirty details of the analysis –Comparing Moments, Shears, Deflections –Comparing M, V, & Service Capacities –Reviewing Specifications and their details –Reviewing other details as necessary –Very time consuming effort at times

38 Enhancement Testing Testing out new features in the application FY 2011 Work Plan –FP1 User Enhancements Truss LL Distribution Factor

39 Truss LL DF

40

41

42

43

44

45

46 Compare LL DF’s Hand Calcs vs Virtis Calcs –Single Lane M LL DF 0.865 vs 0.87 –Multi Lane M LL DF 1.7725 vs 1.77

47 Truss LL DF Hand Calcs vs Virtis Calcs –Both used AASHTO 3.12.1 for multi lane reduction factors –Both used AASHTO 3.6.2 for 12 ft lanes –Both used 2 ft from curb line to first Wheel –Everything agrees with hand calcs –Accept this Enhancement as correct

48 Other testing areas Reports –Data Correct –Labels match data –Missing data Import/Export Bridge and Library XML files –Conversion works ok, if necessary –Bridge rates ok after migration – same results

49 Other testing areas Administration –Adding/Removing users –Revising their permissions (groups) Other Configuration revisions –Libraries

50

51 Still Want to Test?

52 Other Beta Test TAG duties Review upcoming enhancements Review GUI changes during design Review enhancement list and short list them for UG meeting Other duties as assigned by TAG Chair and/or Task Force

53 Why? Why do I test? –I’m going to do the same testing before I’d implement a new version anyway, so might as well have a jump start from ground level. –I learn the product and the new enhancements. –Get to help in direction of the product. –Like to help

54 Why do you want to test?

55 Questions?