BAJA STATUS UPDATE November 9, 2011 FRAME & SUSPENSION Design Phase completed Analysis Phase 35% completed – Frame Design uploaded to PATRAN – Material.

Similar presentations


Presentation on theme: "BAJA STATUS UPDATE November 9, 2011 FRAME & SUSPENSION Design Phase completed Analysis Phase 35% completed – Frame Design uploaded to PATRAN – Material."— Presentation transcript:

1 BAJA STATUS UPDATE November 9, 2011 FRAME & SUSPENSION Design Phase completed Analysis Phase 35% completed – Frame Design uploaded to PATRAN – Material Properties selected – Tubing Dimensions selected – Boundary Conditions established Upcoming Tasks – PATRAN FEA under multiple load cases

2 BAJA STATUS UPDATE November 9, 2011 GEARBOX Calculation Phase completed – Gears – Shafts – Bearings Design Phase 60% completed – Gear train design completed Upcoming Tasks – Packaging design in SolidWorks – SolidWorks FEA

3 GANTT CHART – 11/9/2011


Download ppt "BAJA STATUS UPDATE November 9, 2011 FRAME & SUSPENSION Design Phase completed Analysis Phase 35% completed – Frame Design uploaded to PATRAN – Material."