1 LNGS Scanning Station Nicola D’Ambrosio (LNGS group) Maiori, 4-6 June 2007

2 CS Scanning Station: presently activities CSd measurement and analysis On-Line and off-line ESS improvements (New Filters, brick X-ray measurement, …) CS Scanning improvements (soft../Hard…) CS X-Ray system development and management Automatic emulsion changer (oil option) development Bricks / CS handling and shipment organization … General maintenance ( lab environment, network, processing PCs) PENAUT analysis

3 Scanning station: April 2007 run 2 shifts/day - 1 Physicist /shift (LNGS people available and on-call) 4 microscopes dedicated : used only 3 (1 microscope had a camera problem, now solved) - 1 microscope used for PENAUT analysis - - 1 microscope at TecnoCut for automatic changer tuning -

4 Week 20 14-20 May Week 21 21-27 May Week 22 28-1 May-June MarilisaAlessandraFrancesco LucaAndrea Scanning station shifts List (April 2007 Run) A new call is under way for 1÷2 weeks in June CSd measurement started on 17/5

5 Scanning station CSd analysis (April 2007 Run) 18 CSd measured from first extraction 19 CSd measured from second extraction 37 CSd in 11 Days (36÷15 cm 2 around prediction) Detailed results of this analysis will be presented by Luillo

6 On-Line scanning parameters tuning needed on “real” CSd emulsion No information on efficiencies for “large angle” ( > 400 mrad) We need a new set of emulsion for efficiencies check using “presently” CSd-like emulsion + large angle set New test beam ? Comments

7 Scanning station : 2007 September Run 24 hours/day 6 microscopes operative 3 shifts/day ( 8 hours ) - 2 person/shift (1 Physicist from the collaboration, 1 ext. man power ) ~ 1 CSd / system / day ( considering also NC ) In total 6÷8 CSd/day can be analyzed at LNGS

8 Scanning station : near future plan Setting Up of the CS Analysis parameters (On-Line and Off-Line) Re-Measurement of the CSd (April 2007 run) A soon as they are available -> tuning of the other 3 microscopes Tuning of the data flow into the computer infrastructure (Data access via Central DB !!!)

9 Emulsion Scotch Tape Vacuum channel CSD full surface analysis: Emulsion on scotch tape

10 CSD full surface analysis Preliminary quality test DONE : CSD prediction from August Run measured and confirmed Event found 98 times on 100 measurements Future tests: new scotch, un-gluing emulsion effects, precise measurement near the border. Presently we manually glue the emulsion on scotch with a “simple tool”: not so easy to get good result Professional gluing machine will be soon available (Bologna) New prototype of glass with large perimeter channel is under construction (Bologna)


Download ppt "LNGS Scanning Station Nicola D’Ambrosio (LNGS group) Maiori, 4-6 June 2007."