1
MRP
2
Learning Objectives Describe the conditions under which MRP is most appropriate. Describe the inputs, outputs, and nature of MRP processing. Explain how requirements in a master production schedule are translated into material requirements for lower-level items. Discuss the benefits and requirements of MRP.
3
Learning Objectives Explain how an MRP system is useful in capacity requirements planning. Outline the potential benefits and some of the difficulties users have encountered with MRP. Describe MRP II and its benefits. Describe ERP, what it provides, and its hidden costs.
4
MRP Material requirements planning (MRP): Computer-based information system that translates master schedule requirements for end items into time-phased requirements for subassemblies, components, and raw materials. End products Time-phase based Subassemblies Components Raw materials MRP
5
Independent and Dependent Demand
Independent Demand A B(4) C(2) D(2) E(1) D(3) F(2) Dependent Demand Independent demand is uncertain. Dependent demand is certain.
6
Dependant Demand Dependent demand: Demand for items that are subassemblies or component parts to be used in production of finished goods. Once the independent demand is known, the dependent demand can be determined.
7
Demand “Lumpy” demand Demand Stable demand Amount on hand Safety stock
Time Demand Stable demand “Lumpy” demand Amount on hand Safety stock
8
Overview of MRP MRP Inputs MRP Processing MRP Outputs Master schedule
Bill of materials Inventory records MRP computer programs Changes Order releases Planned-order schedules Exception reports Planning reports Performance- control reports transaction Primary Secondary
9
MPR Inputs Master Production Schedule
Time-phased plan specifying timing and quantity of production for each end item. Material Requirement Planning Process Product Structure Tree Inventory Lead Times
10
Master Schedule Master schedule: One of three primary inputs in MRP; states which end items are to be produced, when these are needed, and in what quantities. Cumulative lead time: The sum of the lead times that sequential phases of a process require, from ordering of parts or raw materials to completion of final assembly.
11
Planning Horizon 1 2 3 4 5 6 7 8 9 10 Fabrication Assembly
Procurement Fabrication Subassembly Assembly Time Period (weeks)
12
Bill-of-Materials Bill of materials (BOM): One of the three primary inputs of MRP; a listing of all of the raw materials, parts, subassemblies, and assemblies needed to produce one unit of a product. Product structure tree: Visual depiction of the requirements in a bill of materials, where all components are listed by levels. Low-level coding: Restructuring the bill of materials so that multiple occurrences of a component all coincide with the lowest level the component occurs
13
Product Structure Tree
Chair Seat Legs (2) Cross bar Side Rails (2) Back Supports (3) Leg Assembly Level 1 2 Level 1 2 3 E (4) E (4) E E (2)
14
Inventory Records One of the three primary inputs in MRP
Includes information on the status of each item by time period Gross requirements Scheduled receipts Amount on hand Lead times Lot sizes And more …
15
Inventory Requirements
Net requirements: Available Inventory: Net Requirements = Gross Requirements – Available Inventory Available Inventory = Projected on hand – Safety stock – Inventory allocated to other items
16
Assembly Time Chart 1 2 3 4 5 6 7 8 9 10 11 Procurement of
raw material D raw material F part C part H raw material I Fabrication of part G of part E Subassembly A Subassembly B Final assembly and inspection 1 2 3 4 5 6 7 8 9 10 11
17
Time-Phased Product Structure
Must have D and E completed here so production can begin on B Start production of D | | | | | | | | Time in weeks Lead time 2 weeks 1 week D (2) E (2) A B C D E F G 1 2 3 weeks 2 weeks to produce B (2) 1 week A F (2) 2 weeks 3 weeks E (2) 2 weeks D (2) G (1) 1 week 1 week C (3)
18
Gross Requirements Plan
Week Lead Time Required date Order release date week Required date Order release date weeks Required date Order release date week Required date Order release date week Required date Order release date weeks Required date Order release date week Required date Order release date week
19
Net Requirements Plan
20
Net Requirements Plan
21
MRP Processing Gross requirements Schedule receipts Projected on hand
Net requirements Planned-order receipts Planned-order releases
22
MPR Processing Gross requirements Scheduled receipts Projected on hand
Total expected demand Scheduled receipts Open orders scheduled to arrive Projected on hand Expected inventory on hand at the beginning of each time period
23
MPR Processing Net requirements Planned-order receipts
Actual amount needed in each time period Planned-order receipts Quantity expected to be received at the beginning of the period Offset by lead time Planned-order releases Planned amount to order in each time period
24
Lot-Sizing Techniques
Lot-for-lot techniques order just what is required for production based on net requirements May not always be feasible If setup costs are high, costs may be high as well Economic order quantity (EOQ) EOQ expects a known constant demand and MRP systems often deal with unknown and variable demand
25
Lot-Sizing Techniques
Part Period Balancing (PPB) looks at future orders to determine most economic lot size EPP = setup cost / holding cost Programming technique Assumes a finite time horizon Effective, but computationally burdensome
26
Lot-for-Lot Example Week 1 2 3 4 5 6 7 8 9 10 Gross requirements 35 30 40 55 Scheduled receipts Projected on hand Net requirements Planned order receipts Planned order releases Holding cost = $1/week; Setup cost = $100/times; Lead time = 1 week
27
Lot-for-Lot Example No on-hand inventory is carried through the system
Total holding cost = $0 There are seven setups for this item in this plan Total setup cost = 7 x $100 = $700 1 2 3 4 5 6 7 8 9 10 Gross requirements 35 30 40 55 Scheduled receipts Projected on hand Net requirements Planned order receipts Planned order releases Holding cost = $1/week; Setup cost = $100/times; Lead time = 1 week
28
Average weekly gross requirements = 27; EOQ = 73 units
EOQ Lot Size Example Week 1 2 3 4 5 6 7 8 9 10 Gross requirements 35 30 40 55 Scheduled receipts Projected on hand 43 66 26 69 39 Net requirements 16 Planned order receipts 73 Planned order releases Holding cost = $1/week; Setup cost = $100/times; Lead time = 1 week Average weekly gross requirements = 27; EOQ = 73 units
29
Average weekly gross requirements = 27; EOQ = 73 units
EOQ Lot Size Example Annual demand = 1,404 Total cost = setup cost + holding cost Total cost = (1,404/73) x $100 + (73/2) x ($1 x 52 weeks) Total cost = $3,798 /year Cost for 10 weeks = $3,798 x (10/52) = $730 Or Total cost = 4 x $ x ($1 /weeks) Total cost = $718 1 2 3 4 5 6 7 8 9 10 Gross requirements 35 30 40 55 Scheduled receipts Projected on hand Net requirements 16 Planned order receipts 73 Planned order releases Holding cost = $1/week; Setup cost = $100/times; Lead time = 1 week Average weekly gross requirements = 27; EOQ = 73 units
30
Holding cost = $1/week; Setup cost = $100; Lead time = 1 week
PPB Example 1 2 3 4 5 6 7 8 9 10 Gross requirements 35 30 40 55 Scheduled receipts Projected on hand 50 60 Net requirements Planned order receipts 80 100 Planned order releases Holding cost = $1/week; Setup cost = $100; Lead time = 1 week ; EPP = 100 units
31
Holding cost = $1/week; Setup cost = $100;
PPB Example Trial Lot Size Periods (cumulative net Costs Combined requirements) Part Periods Setup Holding Total 2 30 0 2, = 40 x 1 2, 3, = 40 x 1 2, 3, 4, = 50 x x 2, 3, 4, 5, = 90 x x 2 + 40 x 1 + = 1 2 3 4 5 6 7 8 9 10 Gross requirements 35 30 40 55 Scheduled receipts Projected on hand Net requirements Planned order receipts Planned order releases Combine periods as this results in the Part Period closest to the EPP 6 40 0 6, = 30 x 1 6, 7, = 30 x 1 6, 7, 8, = 60 x x + = Combine periods as this results in the Part Period closest to the EPP Total cost + = Holding cost = $1/week; Setup cost = $100; EPP = 100 units
32
Lot-Sizing Summary For these three examples Lot-for-lot $700 EOQ $730
PPB $490 Wagner-Whitin would have yielded a plan with a total cost of $455 for this example
33
Holding cost = $1/week; Setup cost = $100; Lead time = 1 week
Example 1 2 3 4 5 6 7 8 9 10 Gross requirements 35 30 40 55 Scheduled receipts Projected on hand 50 Net requirements Planned order receipts 80 70 85 Planned order releases Holding cost = $1/week; Setup cost = $100; Lead time = 1 week ; EPP = 100 units
34
Lot-Sizing Summary In theory, lot sizes should be recomputed whenever there is a lot size or order quantity change In practice, this results in system nervousness and instability Lot-for-lot should be used whenever economical Lot sizes can be modified to allow for scrap, process constraints, and purchase lots
35
Lot-Sizing Summary Use lot-sizing with care as it can cause considerable distortion of requirements at lower levels of the BOM When setup costs are significant and demand is reasonably smooth, PPB, Wagner-Whitin, or EOQ should give reasonable results
36
Updating the System Regenerative system Net-change system
Updates MRP records periodically Net-change system Updates MPR records continuously
37
MRP Primary Reports Planned orders - schedule indicating the amount and timing of future orders. Order releases - Authorization for the execution of planned orders. Changes - revisions of due dates or order quantities, or cancellations of orders.
38
MRP Secondary Reports Performance-control reports
system evaluation, deviation, late delivery, stockouts Planning reports useful for forecasting future inventory, assess future material requirement Exception reports late or overdue orders, excessive scrap rate, requirement of non-existing parts
39
Material Checking & Balancing
Use for monitoring of amount of part and product during processes Needs information to balance materials Accumulative production planning or target plan BOM or Assembly diagram Normally periodic checked
40
Material Checking & Balancing
Week A B C D E F G H I J K Assembly diagram D N O S A J M F Target Plan Accumulative production K J I H G F E D C B A Balancing chart
41
Resource Requirements Profile
200 – 150 – 100 – 50 – – 1 2 3 4 5 6 7 8 Period (a) Standard labor hours 200 – 150 – 100 – 50 – – 1 2 3 4 5 6 7 8 Period (b) Standard labor hours Capacity exceeded in periods 4 & 6 Lot 6 “split” Lot 11 moved Lot 1 2 4 7 8 3 5 10 13 9 12 14 16 6 15 11 Available capacity Available capacity Lot 1 2 4 7 8 3 5 10 13 9 12 14 16 6 15 11
42
Smoothing Tactics Overlapping Operations splitting Lot splitting
Sends part of the work to following operations before the entire lot is complete Reduces lead time Operations splitting Sends the lot to two different machines for the same operation Shorter throughput time but increased setup costs Lot splitting Breaking up the order into smaller lots and running part ahead of schedule
43
Other Considerations Safety Stock Lot sizing Lot-for-lot ordering
Economic order quantity Fixed-period ordering
44
MRP in Services Food catering service End item => catered food
Dependent demand => ingredients for each recipe, i.e. bill of materials
45
Benefits of MRP Low levels of in-process inventories
Ability to track material requirements Ability to evaluate capacity requirements Means of allocating production time Ability to easily determine inventory usage by backflushing Backflushing: Exploding an end item’s bill of materials to determine the quantities of the components that were used to make the item.
46
Requirements of MRP Computer and necessary software
Accurate and up-to-date Master schedules Bills of materials Inventory records Integrity of data
47
MRP II Expanded MRP with emphasis placed on integration
Financial planning Marketing Engineering Purchasing Manufacturing
48
MRP II Market Demand Production plan Problems? Yes No Finance
Rough-cut capacity planning Yes No Finance Marketing Manufacturing Adjust production plan Master production schedule MRP Capacity planning Requirements schedules Adjust master schedule
49
ERP Enterprise resource planning (ERP):
Next step in an evolution that began with MPR and evolved into MRPII Integration of financial, manufacturing, and human resources on a single computer system.
50
ERP Software ERP software provides a system to capture and make data available in real time to decision makers and other users in the organization Provides tools for planning and monitoring various business processes Includes Production planning and scheduling Inventory management Product costing Distribution
51
MRP in Services Service applications such as: Professional services
Postal services Retail Banking Healthcare Higher education Engineering Logistical services Real estate
52
ERP Strategy Considerations
High initial cost High cost to maintain Future upgrades Training