Presentation is loading. Please wait.

Presentation is loading. Please wait.

The Green Corridor Project

Similar presentations


Presentation on theme: "The Green Corridor Project"— Presentation transcript:

1

2 The Green Corridor Project
Green Infrastructure and Stormwater Pre-Treatment Concept “Silva Cell” Crate System “Freno” Modular Flow-Through Planters Micro-Pool Stormwater Swale Streetscape Planting Concepts

3

4 Design Considerations: Expected Pollutants
Landscaping sites (fertilizers -- phosphorus and nitrogen): greater cell depth will help filter these. Studies show that removal of these pollutants increases with the depth of the bio-retention cell, reaching removal levels up to 80% for phosphorus and 60% for nitrogen (TKN) with sufficient depth (study results relating to nitrogen vary). Parking lot or streetscape applications (metals, oils, grease and solids): Thicker mulch layer Studies support that a significant mulch layer will effectively remove greater than 90% of copper, zinc and lead. In urban areas where heavy metals are the focal pollutants, shallow bioretention facilities with a significant mulch layer may be recommended. In residential areas, however, where the primary pollutants of concern are nitrogen and phosphorus, the depth dependence will require deeper cells that reach approximately 2 to 3 feet

5 Bio-retention removes Pollutants (survey of studies)
Pollutant Removal Copper 43%-97% Lead 70%-95% Zinc 64%-95% Phosphorus 65%-87% Total Kjeldahl Nitrogen (TKN) 52-67% Ammonium (NH4+ ) 92% Nitrate (NO3-) 15%-16% Total nitrogen (TN) 49% Calcium 27% Bioretention BMP,

6 Fairfax Boulevard Stormwater Pre-Treatment Filtration Based System
Filtration Systems provide temporary storage and filtration of stormwater, contributing to: Water quality control Percentage Reduction of Stormwater Volume Channel protection, Overbank protection, and Extreme flood control Used where soils are not suitable for infiltration The system stores and treats stormwater before returning it to the stormwater drainage system typically through a perforated under-drain. Use of small scale, natural drainage features to slow, clean and capture runoff to reduce the impacts of development on rivers, streams, lakes, coastal waters, and ground water.

7 “Silva Cell” Crate System
Fairfax Boulevard Lancaster Cir. To 6th Ave “Silva Cell” Crate System Suspended Concrete and Brick Paving Stormwater Distribution/Irrigation Lines “Silva Cell” Structural Crates Containing Uncompacted Engineered Soils for Tree Root Growth and Water Retention Perforated Under Drains for Large Storm Events Geomembrane Liner to prevent Infiltration beyond the Structural Crate System Connection to the Underground Storm Sewer System

8 How the “Silva Cell” Crates works

9

10 Washington DC- SW 1st street- Silva Cells 2008- 2010

11 City of Charlotte Soil Vaults- 1985
Willow Oak (Quercus phellos) Planted 1985, 25 years old in 2010 Avg DBH 16 inches; Avg 44 feet; Avg Soil Volume 700 cubic feet

12 Modular Flow-Through Planters
Fairfax Boulevard 6th Ave. to 12th Ave. Modular Flow-Through Planters Precast Concrete Curb Drain/Inlet Gravel Filter Strip Herbaceous Plantings 2 inch Mulch Layer Engineered Soils Sand and Gravel Drainage Bed Overflow Drain for Large Storm Events Perforated Under Drains Geomembrane Liner to prevent Infiltration beyond the Flow-Through Planter Modular Precast Concrete Flow-Through Planter Walls Connection to the Underground Storm Sewer System

13 “Freno” Modular Flow-Through Planters

14

15 Life Cycle Benefits As a modular system the Freno Flow-Through Planter can be removed and reused. Similarly, components can be removed and reconfigured if the site is redesigned. The system can be repaired with replacement parts if accidental damage occurs.

16 Suggested Modular Flow-Through Planter Maintenance
Activity Schedule Water plants daily for 2 weeks At project completion Inspect soil and repair eroded areas Remove litter and debris Re-mulch void areas As Needed Remove and replace dead and diseased vegetation Twice per year Add mulch Cut back herbaceous plantings during winter dormancy Once per year Test soil treatment performance and replace soil/plants Testing 3 years As needed (7-10years) Bioretention BMP,

17 6th Ave. to Fairfax Crossing
Fairfax Boulevard 6th Ave. to Fairfax Crossing Micro-Pool Stormwater Swale Landscape Micro-Pool Plantings w/ Street Trees Weir Wall Spillways 3 ft. Turf Filter Strip Herbaceous Plantings with Formal Planting Border Perforated Under Drains Overflow Drain for Large Storm Events Connection to the Underground Storm Sewer System

18 Layered and “Over” Planting Approach to Micro-Pool Planting

19 Suggested Micro-Pool Weir Planting Maintenance
Activity Schedule Water plants daily for 2 weeks At project completion Inspect soil and repair eroded areas Remove litter and debris Re-mulch void areas As Needed Mow monthly for the First year First year Only Add mulch Mow and/or cut back plantings during winter dormancy Selectively Remove Invasive exotic Plants Once per year Re-plant eroded and bare areas after large storm events As needed Bioretention BMP,

20 The Key to the Overall Success of the Micro-Pool Planting is to not over maintain after the First Year Mow and/or cutback once a year No irrigation needed No fertilizing needed

21 Bio-diverse Planting of Street Trees

22 Layered and “Over” Planting Modular Flow-Through Planters

23 Micro-Pool Strategic Combination Plantings

24 Brick and Concrete Paving between Lancaster Cir. And 6th Ave.

25

26

27

28

29

30

31

32

33


Download ppt "The Green Corridor Project"

Similar presentations


Ads by Google