API 6A 21 st Edition WG API Subcommittee SC-6 Discussions Valves and Wellhead Equipment.

Similar presentations


Presentation on theme: "API 6A 21 st Edition WG API Subcommittee SC-6 Discussions Valves and Wellhead Equipment."— Presentation transcript:

1 API 6A 21 st Edition WG API Subcommittee SC-6 Discussions Valves and Wellhead Equipment

2 Introduction TG Committee consists of 96 members Meetings started in June 2013 with typically 30- 35 members per meeting Held approximately 18 full-day WG meetings to date and numerous team/small group meetings TG approach – Build worklist (cut-off for initial items was Aug 2013) – Identify Teams and Team Captains – Divide worklist between teams – Met as teams to resolve work items

3 Work Teams/Captains – Design / Jean Brunjes – Materials, Welding and Cladding / Sterling Lewis – Organization / Eric Wehner – Qualification / Tom Lambert – Quality / Mike Briggs – Documentation Specialist / Jill Bell – Co-Chairs / Eric Wehner & David Zollo

4 Worklist Currently there are 180 items in the worklist that have been addressed. – Not all items in the worklist have been accepted for action some have been rejected at the TG meetings A draft document with 220 changes has been generated. Tabulated in a spreadsheet. Spreadsheet reviewed at last meeting Spreadsheet

5 Key Items addressed Definition of a manufacturer requirements added Tied pressure / NACE limitations to PSL’s Annex M reworked to move requirements to main body of the document. Annex M is normative. PSL 4 requirements changed to align with potential HPHT requirements (no welding requirement removed) PSL 3 – heat lot traceability requirement added Welding hardness survey requirements removed to default to NACE Minimum clad thickness requirement added Better definition of design criteria when referring to clad thickness

6 Key Items addressed Moved repair Annex J to 6AR Removed Annex H – Tools (TR needed) Design rules moved to 6X Defined performance and product testing for bleeder plugs Revised Annex L and added 4” HPVR Added language to reference 20 series specification requirements (castings, bolting-BSL- 1 minimum requirement) Eliminated PR1 in Annex F Annex C stud length replaced by AWHEM TR

7 HPHT for 6A 21 st Edition Brainstorm How can we modify PSL 4 to make it normative base requirement for HPHT equipment?  Remove no welding restriction  Require prolongation or sacrificial part; no separate QTC  Testing per heat treat batch  Separate quench loads not allowed with just a single prolongation  What do we do with elastomers?  Pressure testing (1.25x or 1.5x)

8 HPHT for 6A 21 st Edition Brainstorm How can we modify Annex G to capture normative requirements for HPHT  Invoke BSL 3 per 20E bolting  Invoke 20H HSL level 2 or 3 o 2 is tighter calibration and survey requirements o 3 is full AMS 2750 compliance  Reference applicable sections in 17TR8  Make AWHEM derating factors normative unless actual test data is available  High strength nickel based alloys shall conform to the requirements of API 6A718  Sour Service compliance per NACE MR0175 is mandatory

9 Plan forward Send current draft out as comment only ballot Start reorganization work / Annex Work – Annex J replace by 6AR – Annex C revise to AWHEM bolting dimensions – Annex B revise to incorporate Imperial tables – Annex D revise to accommodate gasket lubrication – Annex H, I & O - Eliminate Resolve comments Reorganize per Eric’s plan Address HPHT Have final document ready for ballot by June 2016