MyFloridaMarketPlace CRB Meeting

Similar presentations


Presentation on theme: "MyFloridaMarketPlace CRB Meeting"— Presentation transcript:

1 MyFloridaMarketPlace CRB Meeting
MFMP 2.0 Upgrade Status March 29, 2007

2 Agenda Review Summary status of upgrade
Review Project lifecycle review with highlights Review upgrade timeline MFMP 2.0 Go/No go Decision Point Summary MFMP 2.0-Aspire Project Schedule Synchronization Training Review Testing results Performance Testing Migration Process Overview of MFMP 2.0 migration weekend Closing

3 MFMP 2.0 Upgrade – Plan Status
Technical Infrastructure Plan Design Build Test Train Deploy Build 4/2/07 Accomplishments In progress Upcoming Development of 7.1 customized components Review of 8.2 test conditions System Test Pass 1 - 3 Workflow analysis Change Request evaluation Final upgrade scope Design of new key groups/roles/permissions Reporting assessment CR Designs/Development Training (Agency, SA, UAT) UAT Performance Testing/Tuning Implementation planning Go/No go decisions MFMP 2.0 Dress Rehearsals Requester Training Issue Resolution MFMP 2.0 cutover (3/29-4/2)

4 MFMP 2.0 Upgrade – Plan Dates

5 MFMP 2.0 Upgrade “Go/No Go” Decision Points
Go/No go decision points per the Upgrade Plan established Sept. ’06 and finalized in Oct. ’06: Can we synchronize schedules for Aspire go-live and MFMP 2.0 upgrade? – (target decision date 1/19/07) Do the MFMP 2.0 Training Plan and User Acceptance testing results support moving forward with the upgrade (target decision date 3/12/07)? Do the Performance test results and upgrade migration results (“Dress Rehearsals”) substantiate beginning the final cut over to MFMP 2.0 (target decision date 3/29/07)?

6 MFMP 2.0 Upgrade “Go/No Go” Decision Point #1
Can we synchronize schedules for Aspire go-live and MFMP 2.0 upgrade? Decision target date 1/19/07 Late December announcement Aspire schedule no longer viable MFMP 2.0 go/no go decision = GO!

7 MFMP 2.0 Upgrade “Go/No Go” Decision Point #2
Do the MFMP 2.0 Training Plan and User Acceptance testing results support moving forward with the upgrade? Decision target date 3/12/07 Training plan supports broad base of agency personnel covering the differences between current version and MFMP 2.0 results on following pages User (Functional) Acceptance testing meets exit criteria

8 MFMP 2.0 Upgrade “Go/No Go” Decision Point #2 - Training
MFMP 2.0 Training Total of 1925 people trained for the upgrade (as of 3/27/07) 877 core purchasing and finance specialists trained in 26 agencies 40 sessions in 10 days of requester 5 locations 963 requesters trained – number expected to exceed 1,000 59 System Administrators trained & 26 acceptance testers 26 acceptance testers trained Overall training satisfaction rating is Good+ The total number of people trained directly by MFMP Project is nearly double the number trained for the initial implementation MFMP 2.0 go/no go decision - Training= GO!

9 MFMP 2.0 go/no go decision - UAT = GO!
MFMP 2.0 Upgrade “Go/No Go” Decision Point #2 – Functional Acceptance Exit Criteria ID Criteria Description Status 1 Successful Execution Of Test Conditions for Modified Groups/Roles/ Permissions Review of available functionality and workflow based on newly defined user security structure through system administrator training and acceptance 2 Resolve and Close all Blocker and Major Issues identified in UAT Zero (0) remaining Blocker and Major issues outstanding 3 No more than 30 open moderate issues remaining with a corrective action plan for completion 12 total remaining Moderate issues with 7 of the issues forwarded to Ariba for resolution 4 No more than 50 open minor issues with a corrective action plan for completion 17 total remaining Minor issues with 6 of the issues forwarded to Ariba for resolution. 5 Obtain confirmation from Acceptance Testers (CRB Agency) 13 of 13 Acceptance Testing confirmations received. 6 Obtain UAT sign-off from MFMP Project Director Project Director received positive recommendation to accept the upgrade. MFMP 2.0 go/no go decision - UAT = GO!

10 MFMP 2.0 Upgrade “Go/No Go” Decision Point #3
Do the Performance test results and upgrade migration results (“Dress Rehearsals”) substantiate beginning the final cut over to MFMP 2.0? Decision target date 3/29/07 MFMP 2.0 performance testing meets exit criteria results on following pages Upgrade migration is accurate and can be completed in the time available

11 MFMP 2.0 go/no go decision - Performance = GO!
MFMP 2.0 Upgrade “Go/No Go” Decision Point #3 –Performance Testing Summary Performance Testing Exit criteria established from historical performance based on the highest productive day over the last Fiscal Year ID Criteria Description Status 1 Less than or equal to 2 seconds average response time between processing steps for a PR creation and IR review with 200 active users and 850 casual users over one hour PR response time: sec IR response time: sec Active users: 218 Casual users: 995 Run time: 1:03:53 2 200 Purchase Orders created in one hour 282 Purchase orders 3 190 Invoice Reconciliations created in an hour 265 Invoice Reconciliations MFMP 2.0 go/no go decision - Performance = GO!

12 MFMP 2.0 go/no go decision - Migration = GO!
MFMP 2.0 Upgrade “Go/No Go” Decision Point #3 – Migration Test Run Summary Migration Test Runs (“Dress Rehearsals”) Five test runs were completed 3 mock conversions: all programs and verifications to convert the data run to capture initial timings and validate data 2 full dress rehearsals: full-scale practice runs for the implementation Results: Starting the migration processes at 6:00 PM Thursday, 3/29 we expect to complete the entire cut-over by 8:00 PM Sunday. Data verification Control count totals: verifies the same number of records into the conversion process come out of the process Run reports before migration on current version and same reports after migration on MFMP 2.0 then compare MFMP 2.0 go/no go decision - Migration = GO!

13 MFMP 2.0 Upgrade “Go/No Go” Decision Summary
Criteria Status 1. Can we synchronize schedules for Aspire go-live and MFMP 2.0 upgrade? Yes 2. Do the MFMP 2.0 Training Plan and User Acceptance testing results support moving forward with the upgrade? 3. Do the Performance test results and upgrade migration results (“Dress Rehearsals”) substantiate beginning the final cut over to MFMP 2.0? MFMP 2.0 go/no go decision = GO!

14 MFMP 2.0 Implementation Planning
MFMP 2.0 implementation/contingency planning Readiness checklist Communication sent on 2/20 to Agency Purchasing and F&A Liaisons Posted to the toolkit: MFMP 2.0/Deployment section Communication approach Updates during the conversion weekend will be provided via s will be sent at the completion of tasks below in bold green font MFMP Customer Service Desk will be available 4/2-4/6 from 7:00 AM to 7:00 PM Overview of migration weekend 3/29 6:00 PM: Current MFMP shutdown 3/29 6:00 PM – 3/30 4:00 AM: Final MFMP 1.0 processing & close-out 3/30 2:00 AM – 3/31 10:30 PM: MFMP 2.0 conversion 3/31 10:30 PM – 4/1 11:30 AM: MFMP 2.0 environment configuration/Group & Role conversion 4/1 11:30 AM – 4/1 4:00 PM: MFMP 2.0 application verification 4/1 5:00 PM: Final production release decision 4/1 5:30 PM – 4/1 10:00 PM: Production configuration 4/1 10:00 PM – 4/2 7:00 AM: Production batch cycles MFMP 2.0 available 7:00 AM Monday, 4/2/07

15 Contingency Planning – Our Plan B!
Contingency Plans – only if needed Monday, 4/2 will be used for the implementation of MFMP 2.0 Project Team management will make decision no later than 4/1 5:00 PM communications will be sent to Purchasing Directors and Finance & Accounting Directors regarding execution of back up plan BuyerHelp voice response system will be updated Only if necessary, we will move the go-live date for MFMP 2.0 4/9/2007 Operations would continue on current version Same transition weekend approach applies – down Thurs after business day and until Monday 4/9/07

16 0 business days until MFMP 2.0!
What’s Next? Any closing discussion 0 business days until MFMP 2.0! Thank you!