US Army Corps of Engineers BUILDING STRONG ® Portland District - Navigation Update COL Steve Miles Commander Portland District PNWA Annual Meeting 13 October.

Similar presentations


Presentation on theme: "US Army Corps of Engineers BUILDING STRONG ® Portland District - Navigation Update COL Steve Miles Commander Portland District PNWA Annual Meeting 13 October."— Presentation transcript:

1 US Army Corps of Engineers BUILDING STRONG ® Portland District - Navigation Update COL Steve Miles Commander Portland District PNWA Annual Meeting 13 October 2009

2 BUILDING STRONG ® PORTLAND DISTRICT 2 Topics  The Dalles D/S Gate Emergency Repairs  Columbia River Channel Improvements  MCR Jetty Major Rehab  MCR Buoy Installation  Long-Term Planning ► Joint Portland / Walla Walla 5-Year Planning ► Columbia River Long-Term Outage (Dec 2010) The Dalles John Day

3 BUILDING STRONG ® PORTLAND DISTRICT 3 The Dalles Downstream Miter Gate - Emergency Repairs What Happened: Mar 07, 08, 09: Intermediate Repairs Nov 07: Instrument Install 28 Sep 09: ► Operator Identifies Possible Problem ► Instrumentation Review ► Remote Vehicle Inspect ► Project Stops Operation 29 Sep 09: ► Corporate Review ► River Closed 30 Sep 09: ► Diver Inspection ► Dewatering ► Letter Contract to AAC 1 Oct 09: ► Cleaning / Inspection / Repair Plan ► Repairs Begin 12 Oct 09: Lock Re-Opens

4 BUILDING STRONG ® PORTLAND DISTRICT 4 The Dalles Downstream Miter Gate - Emergency Repairs The Problem: ► Cracks in both miter gate leaves. ► Gate vibrates upon un-mitering/opening. ► Gate has no adjustability. ► Lower 30’ not mitering.

5 BUILDING STRONG ® PORTLAND DISTRICT 5 The Fix: ► Interior girder pockets reinforced with boxes bolted in place. ► Web of lower girder doubled up and bolted into place. ► Replace and Re-tensioned all pintle bolts. ► Repaired 32 different areas where cracks existed by welding. ► End post to quoin block stiffeners reinforced with bolted plates. ► Additional Instrumentation The Dalles Downstream Miter Gate - Emergency Repairs

6 BUILDING STRONG ® PORTLAND DISTRICT 6 The Fix: ► Interior girder pockets reinforced with boxes bolted in place. The Dalles Downstream Miter Gate - Emergency Repairs

7 BUILDING STRONG ® PORTLAND DISTRICT 7 The Dalles Downstream Miter Gate - Emergency Repairs

8 BUILDING STRONG ® PORTLAND DISTRICT 8 The Fix: ► Interior girder pockets reinforced with boxes bolted in place. ► Web of lower girder doubled up and bolted into place. ► Replace and Re-tensioned all pintle bolts. ► Repaired 32 different areas where cracks existed by welding. ► End post to quoin block stiffeners reinforced with bolted plates. ► Additional Instrumentation The Dalles Downstream Miter Gate - Emergency Repairs

9 BUILDING STRONG ® PORTLAND DISTRICT 9 The Fix: ► Interior girder pockets reinforced with boxes bolted in place. ► Web of lower girder doubled up and bolted into place. ► Replace and Re-tensioned all pintle bolts. ► Repaired 32 different areas where cracks existed by welding. ► End post to quoin block stiffeners reinforced with bolted plates. ► Additional Instrumentation The Dalles Downstream Miter Gate - Emergency Repairs Additional Instrumentation

10 BUILDING STRONG ® PORTLAND DISTRICT 10 The Dalles Downstream Miter Gate - Emergency Repairs The Future: ► Increased Monitoring Instrumentation Periodic ROV / Dive Inspections ► Engineering Review of repair work needed during Long-Term Outage ► Dec 09 (tent.): Interim Inspection & Lock Closure (ICW Walla Walla) ► Mar 10: Annual Outage ► Mar 10 – Dec 10 (if needed): Interim Inspection / Lock Closure ► Dec 10 – Apr 11: Long-Term Outage

11 BUILDING STRONG ® PORTLAND DISTRICT 11 Topics  The Dalles D/S Gate Emergency Repairs  Columbia River Channel Improvements  MCR Jetty Major Rehab  MCR Buoy Installation  Long-Term Planning ► Joint Portland / Walla Walla 5-Year Planning ► Columbia River Long-Term Outage (Dec 2010) The Dalles John Day

12 BUILDING STRONG ® PORTLAND DISTRICT 12 Columbia River Channel Improvements  Project Completion: 31 Dec 10  FY 10 Work: ► Completion of Dredging w/ Dredge Oregon (Summer ’10) ► St. Helens: Dredging Begins 13 Oct 09Dredging Begins 13 Oct 09 Blasting 1 Nov 09 – 28 Feb 10Blasting 1 Nov 09 – 28 Feb 10 Ross Island DisposalRoss Island Disposal ► Slaughter’s Bar: Dredging RM 66+00 to RM 67+05Dredging RM 66+00 to RM 67+05 Dibblee Point DisposalDibblee Point Disposal

13 BUILDING STRONG ® PORTLAND DISTRICT 13 Columbia River Channel Improvements http://www.youtube.com/watch?v=tMxyspJgGHk&feature=related

14 BUILDING STRONG ® PORTLAND DISTRICT 14 Topics  The Dalles D/S Gate Emergency Repairs  Columbia River Channel Improvements  MCR Jetty Major Rehab  MCR Buoy Installation  Long-Term Planning ► Joint Portland / Walla Walla 5-Year Planning ► Columbia River Long-Term Outage (Dec 2010) The Dalles John Day

15 BUILDING STRONG ® PORTLAND DISTRICT 15 MCR Jetty Major Rehab North Jetty 2.5 miles long 1914-1917 Washington Pacific Ocean Columbia River Estuary Oregon South Jetty 6 miles long 1885-1913 Jetty “A” 1 mile long 1938-39 View to NE

16 BUILDING STRONG ® PORTLAND DISTRICT 16 MCR Jetty Major Rehab North Jetty 2.5 miles long 1914-1917 Washington Pacific Ocean Columbia River Estuary Oregon South Jetty 6 miles long 1885-1913 Jetty “A” 1 mile long 1938-39 View to NE  Final approval in March 2010 (For FY ’12 Budget Cycle) ► Recommended Plan: Review - Agency Technical Review ► Model Code: Review - Planning Center of Expertise ► Environmental Assessment: Public Review in November  The Recommended Plan: ► Addresses North, South and Jetty “A” ► Include spur groins and capping

17 BUILDING STRONG ® PORTLAND DISTRICT 17 SOUTH JETTY MAJOR REHABILATION Pacific Ocean Mouth of Columbia River N 255 270 285 300 330 345 180 195 210 225 240 360 375 = spur groin 315 MCR Jetty Major Rehab - Example

18 BUILDING STRONG ® PORTLAND DISTRICT 18 31 JAN 2006 HIGH DUNE LOW Backshore Trestle Bay South Jetty Initial Priorities: - Major scour areas on South Jetty Beach - Depressed area north of North Jetty North Jetty MCR Jetty Major Rehab

19 BUILDING STRONG ® PORTLAND DISTRICT 19 Topics  The Dalles D/S Gate Emergency Repairs  Columbia River Channel Improvements  MCR Jetty Major Rehab  MCR Buoy Installation  Long-Term Planning ► Joint Portland / Walla Walla 5-Year Planning ► Columbia River Long-Term Outage (Dec 2010) The Dalles John Day

20 BUILDING STRONG ® PORTLAND DISTRICT 20 DATAWELL Directional Wave Buoy CDIP Wave Rider Buoy MCR Buoy Installation  Constructed in the Netherlands  Centimeter accuracy in wave height  Data transmitted via satellite.  All data are disseminated on the CDIP  Website updates @ 30 minutes.  Alert system if buoy breaks loose.

21 BUILDING STRONG ® PORTLAND DISTRICT 21 Washington Oregon North Jetty South Jetty Jetty “A” Mouth of the Columbia River (MCR)

22 BUILDING STRONG ® PORTLAND DISTRICT 22 Topics  The Dalles D/S Gate Emergency Repairs  Columbia River Channel Improvements  MCR Jetty Major Rehab  MCR Buoy Installation  Long-Term Planning ► Joint Portland / Walla Walla 5-Year Planning ► Columbia River Long-Term Outage (Dec 2010) The Dalles John Day

23 BUILDING STRONG ® PORTLAND DISTRICT 23 Portland / Walla Walla District: 5-Year Planning  Joint Portland / Walla Walla Long-Term Planning since 2006  In 2007: Identified Columbia and Snake River Project Maintenance / Repair Needs and draft timeline  Served as basis for Dec 10 – Apr 11 Outage  Next steps: Update and Refine FY 12 to FY 14 Needs

24 BUILDING STRONG ® PORTLAND DISTRICT 24 Columbia River Long-Term Outage (Dec 10 – Apr 11) ?

25 BUILDING STRONG ® PORTLAND DISTRICT 25 The Dalles Critical Repairs (Dec 10 – Apr 11) History Mar 06, 07, 08: Intermediate Repairs Mar 07: Instrument Install Sep 09: Emergency Outage Dec 09: Tentative Short-Term Outage Mar 10: Normal Outage – Prep for Long-Term Repairs FY 10: $5 mil for TD Repairs

26 BUILDING STRONG ® PORTLAND DISTRICT 26 The Dalles Critical Repairs (Dec 10 – Apr 11) Scope of Repairs  Replace Pintle Bearing Assembly  Replace Quoin Block Assembly  Replace Miter Assembly  Replace lower Portion of Gate  Re-establish Load Path -Quoin Block -Miter Blocks -Pintle Bearing

27 BUILDING STRONG ® PORTLAND DISTRICT 27 The Dalles Critical Repairs (Dec 10 – Apr 11) Acquisition Strategy  Feb 10: 2 Supply Contracts ► Pintle Assembly ► Adjustable Quoin and Miter Block Assembly  Apr 10: Repair Contract -Quoin Block -Miter Blocks -Pintle Bearing

28 BUILDING STRONG ® PORTLAND DISTRICT 28 John Day Critical Repairs (Dec 10 – Apr 11) History  Mid -90s: Critical D/S Gate Repairs  Jul 07: Cracking in Friction Drum  FY 08 – FY 10: Major Rehab Study  Jan 08: Friction Drum Cracks Expand  Mar 08: Friction Drum Emergency Repair  FY 10: Friction Drum Replacement  FY 09: ARRA for D/S Gate Replacement

29 BUILDING STRONG ® PORTLAND DISTRICT 29 John Day Critical Repairs (Dec 10 – Apr 11) Scope of Work  Replace D/S Gate  Replace Friction Drums Acquisition  Contract Awarded to Advanced American Construction (AAC) for Fabrication and Installation

30 BUILDING STRONG ® PORTLAND DISTRICT 30 North Wall Monolith Cracking John Day Major Rehab Report  3 Year Study (2008-2010)  Issues / Concerns ► At Start (62) ► Currently (4) (Includes D/S Gate and Friction Drums) ► In Final Report (Est 2) Movement of Lock Monoliths (Needs Stabilizing) Spillway Gates (May Need Strengthening)  Implement Repairs ► Depends on Report Approval and Funding (Approx 3-5 Years)

31 BUILDING STRONG ® PORTLAND DISTRICT 31 Topics  The Dalles D/S Gate Emergency Repairs  Columbia River Channel Improvements  MCR Jetty Major Rehab  MCR Buoy Installation  Long-Term Planning ► Joint Portland / Walla Walla 5-Year Planning ► Columbia River Long-Term Outage (Dec 2010) The Dalles John Day

32 US Army Corps of Engineers BUILDING STRONG ® Portland District - Navigation Update COL Steve Miles Commander Portland District PNWA Annual Meeting 13 October 2009

33 BUILDING STRONG ® PORTLAND DISTRICT 33 Columbia River Treaty 2014 / 2024 Review: Purpose & Objectives  A series of studies to collect critical information needed to support possible renegotiation of the Columbia River Treaty (CRT)  Identify benefits and costs to hydropower, flood risk management and other outputs of the system under alternative treaty scenarios  U.S. Department of State decision on alternative courses of action regarding the treaty.

34 BUILDING STRONG ® PORTLAND DISTRICT 34 1)The Treaty has no specified end date; however, it does have a provision allowing either nation to terminate most of the provisions of the Treaty in or after 2024, with a minimum 10 years ’ written advance notice, hence the name “ 2014/2024 Review ”. 2)Current flood control operating procedures will end in 2024, independent of Treaty decision. Why a Columbia River Treaty 2014/2024 Review?