Canadian Heavy Oil Association Presentation November 10 th, 2011 A Different View of Project Execution.

Similar presentations


Presentation on theme: "Canadian Heavy Oil Association Presentation November 10 th, 2011 A Different View of Project Execution."— Presentation transcript:

1

2 Canadian Heavy Oil Association Presentation November 10 th, 2011 A Different View of Project Execution

3 SAGD Construction Project Timelines

4 Background in SAGD Deer Creek Energy - Joslyn Pilot Plant

5 Background in SAGD Deer Creek Energy - Joslyn Commercial Facility

6 Background in SAGD Connacher Oil and Gas – Pod I Commercial Facility

7 Background in SAGD Connacher Oil and Gas – Algar Commercial Facility

8 Current Projects Pengrowth Energy Corporation – Lindbergh Pilot Plant Currently Under Construction Scheduled for Startup in Q1 of 2012 Southern Pacific Resources – McKay River Commercial SAGD Currently Under Construction Scheduled for Startup in Q2 of 2012 N-Solv Corporation – McKay River Pilot Project Currently undergoing Engineering Scheduled for Startup in Q4 of 2012

9 Typical Project Algar Commercial Facility – Early Road Construction

10 Typical Project Algar Commercial Facility – Road Construction Complete

11 Typical Project Algar Commercial Facility – Plantsite Civil Preparation

12 Typical Project Algar Commercial Facility – Pile Driving

13 Typical Project Algar Commercial Facility – Day 30

14 Typical Project Algar Commercial Facility – Day 150 – Evaporator Lift

15 Typical Project Algar Commercial Facility – Typical Module Installation

16 Typical Project Algar Commercial Facility – Day 240

17 Typical Project Algar Commercial Facility – First Steam

18 Project Execution Process Design Detailed Process Review Early Involvement of Operations Ability of the Team to quickly evaluate process options incorporating input from all stakeholders & to implement decisions rapidly Ability of the Team to recognize unit operations that have been successfully utilized in similar applications and not waste time in re-evaluation unless justified Contracting Strategy & Risk Management Best scenario for a successful project is where the goals of the Owner, Project Managers, Vendors, and Contractors are all aligned. Lump Sum for Engineering Contractor based on a % of +/- AFE Sole Source Supply where justified Detailed bid process where justified Time and materials based contracts Field contracts a mix of fixed price and hourly

19 Project Execution Shop Fabrication Procurement Onus heavily on Engineering Contractor Schedule of IFC drawings determines the project schedule and predicted cash burn Management of Change Attention to detail & very rigorous shop inspection Constructability Logistics and Transport Difficulty of the Transportation Corridor Close communication between Shop Coordinators, Field Supervisors, and Transport Contractor $/km contract for transport Flexibility of field contracting strategy

20 Project Execution Field Construction Under this execution strategy this area presents the greatest risk for cost control Success is highly dependent on accuracy of engineering contractor – stuff has to fit Primary Mechanical Contractor on hourly Secondary Mechancial Contractor on hourly Typical to go lump sum of E&I Flexibility for Field Supervisors System in place to closely monitor Cash Burn vs Productivity.

21 Specific Techniques Tight Spooling

22 Specific Techniques Pipe Modules

23 Specific Techniques Pouring Pod I Tank Base

24 Specific Techniques Algar - Pile Supported Steel Tank Floors

25 Specific Techniques Pod I Grade Beam, Floor, Supports, & Mod Installation

26 Specific Techniques Algar Grade Beam / Piles

27 Specific Techniques Algar Equipment Setting

28 Closing Remarks “It’s about the People, not the process” Neal Gartner, Engineering Manager, AMEC BDR October 2011