Presentation is loading. Please wait.

Presentation is loading. Please wait.

Success Stories in DOE’s ARRA Smart Grid Program

Similar presentations


Presentation on theme: "Success Stories in DOE’s ARRA Smart Grid Program"— Presentation transcript:

1 Success Stories in DOE’s ARRA Smart Grid Program
Steve Bossart, Senior Energy Analyst Smart Grids & Microgrids for Government & Military Symposium October 24-25, 2013, Arlington, VA. 

2 Topics OE ARRA Smart Grid Program OE ARRA Smart Grid Progress
Case Studies/Success Stories Life After ARRA Smart Grid Elements of OE ARRA smart grid program Progress Results, case studies, and successes Challenge of smart grid deployment after ARRA

3 DOE OE ARRA Smart Grid Program

4 Smart Grid ARRA Activities
American Recovery and Reinvestment Act ($4.5B) Smart Grid Investment Grants (99 projects) $3.4 billion Federal; $4.7 billion private sector > 800 PMUs covering almost 100% of transmission ~ 8000 distribution automation circuits > 15 million smart meters Smart Grid Demonstration Projects (32 projects) $685 million Federal; $1 billion private sector 16 storage projects 16 regional demonstrations Biggest effort for smart grid in US is through the $4.5 B provided from ARRA. SGIG emphasis is on building out smart grid in US. Thus , early efforts are on smart meter deployment, communications network, consumer displays, PMUs in transmission, early DA SGDP is focused on demonstrating a fuller suite of smart grid applications and benefits. In a smaller service area. Almost a $10 billion investment with funds from government and private sector Still only a few percent of a national smart grid; EPRI (2011) $ billion over 20 years; Brattle $800 billion

5 Smart Grid ARRA Activities (continued)
Additional ARRA Smart Grid Activities Interoperability Framework by NIST ($12M) Transmission Analysis and Planning ($80M) State Electricity Regulator Assistance ($49M) State Planning for Smart Grid Resiliency ($52M) Workforce Development ($100M) Other ARRA smart grid activities include Interoperability framework by NIST - SG Interoperability Panel Transmission analysis and planning – ISO/RTO, NERC – improve planning within transmission RTO/ISO and between RTO/ISOs State electricity regulator assistance – state and local government to process smart grid applications State planning for SG resiliency – create and update energy assurance plans Workforce development – universities, two-year colleges, trade schools, industry to train and educate next generation of electric utility workers and those already in utility workforce

6 Technology Deployment
Customer Systems SGIG/SGDP Areas of Smart Grid Technology Deployment Advance Metering Infrastructure Electric Distribution Systems Electric Transmission Systems Displays Internet portals Direct load controls Programmable thermostats EV Chargers Smart meters Data management Back office integration Auto switches Automated capacitors Auto voltage regulators Equipment monitoring Energy Storage Wide area monitoring Synchrophasor Technology Phasor data concentrators Dynamic line rating Equipment Manufacturing Energy devices Software Appliances SG technologies deployed in SGIG and SGDP ranged from Customer systems – displays, PCTs, EV chargers AMI – meters, communications, data management Distribution – DA, power quality, equipment health Transmission – PMUs, DLRs Equipment Manufacturing – connected appliances, smart meters,

7 ARRA Smart Grid Progress

8 SGIG Deployment Status
15.5 million residential and commercial smart meters (11% US coverage ) Distribution automation equipment on about 8,000 circuits (Roughly 5% US coverage) Over 800 networked phasor measurement units (nearly 100% US coverage)

9 Customer Devices in SGIG Projects

10 Customers with Smart Meters Enrolled in Pricing Programs in SGIG

11 Case Studies/Success Stories

12 Peak Demand Reduction from AMI, Pricing, and Customer Systems
Selected examples from SGIG projects reporting initial results A subset of nine CS projects are conducting 11 rigorous studies of consumer behavior to estimate reductions in peak demand, shifts in demand from on-peak to off-peak periods, and reductions in overall electricity consumption. The studies also assess customer acceptance and retention. The nine projects are implementing experimental designs involving randomized assignment of participants to treatment and control groups to minimize bias and maximize the internal and external validity of the results. The projects are taking these steps because they are interested in determining the levels of impact with a high degree of statistical precision and accuracy. Summary of results from the Demand Reduction Report published 12/2012. OG&E and MMLD are CBS projects.

13 AMI Improvements in Operational Efficiencies
Results from 15 projects due to automation of metering service tasks and reductions in labor hours and truck rolls Smart Meter Capabilities O&M Savings % Reduction Remote meter reading Remote service connections/disconnections Meter Operations Cost 13-77 Vehicle Miles 12-59 Future SGIG examples to provide information on other benefits Smart Meter Capabilities Expected Benefits Tamper detection and notification Enables potential recovery of ~1% of revenues that may be lost from meter tampering Outage detection and notification Enables faster restoration (e.g., PECO avoided 6,000 truck rolls following Superstorm Sandy and accelerated restoration by 2-3 days) Voltage and power quality monitoring Enables more effective management of voltages for conservation voltage reductions and other VVO applications

14 Reliability Improvements from Automated Feeder Switching
Selected examples from SGIG projects reporting initial results 4 Projects involving 1,250 feeders April 1, 2011 through March 31, 2012 Index Description Weighted Average (Range) SAIFI System Average Interruption Frequency Index (outages) -22 % (-11% to -49%) MAIFI Momentary Average Interruption Frequency Index (interruptions) (-13% to -35%) SAIDI System Average Interruption Duration Index (minutes) -18 % (+4% to -56%) CAIDI Customer Average Interruption Duration Index (minutes) +8 % (+29% to -15%) Examples: Detroit Edison In the portions of DTE’s service area that have new distribution automation devices, customers are seeing faster system restoration after outages. “This past summer we had a power outage caused by concurrent cable failures. With the new distribution management system analysis capabilities and remotely controlled switches, we were able to restore service within 30 minutes, instead of the eight hours it would have taken with the old technologies,” explains Heather Storey, Manager of DTE’s Smart Circuits Program Florida Power and Light For example, FPL’s SGIG-upgraded Transmission Performance and Diagnostic Center (TPDC) remotely monitors power transformers in 500 FPL substations. New bushing monitors – monitors that can detect and diagnose problems before they occur – have been installed on some of those transformers to evaluate the health of both the high and low voltage bushings, including capacitance, power factor, and the extent of current imbalance. Bushing failures can damage transformers, which means costly repairs and the possibility of extended service interruptions. In January 2012, a newly installed monitor detected an out-of-tolerance high voltage bushing. Customers served by this transformer were temporarily switched to another one, and the affected transformer was removed from service. Meanwhile, the faulty bushing was replaced, preventing an outage that would have affected several thousand customers. Electric Power Board of Chattanooga On April 27, 2011, EPB’s service territory was hit by the most damaging storm in the utility’s history. Nine tornados ripped through neighborhoods and business districts, impacting the entire EPB system. “The whole community was devastated by the damage done in terms of loss of life and property,” says David Wade, EPB Executive Vice President and Chief Operating Officer. “Three quarters of our customers — 129,000 residences and businesses — were out of power.” In the wake of the April storm, EPB conducted the largest system restoration it has ever undertaken. When the storm hit, EPB had 123 smart switches in service, and only one of those switches went off line during the storm. Even though company staff spent days manually switching circuits that would have been automatically switched had the smart switches been fully deployed, restoration was improved with the data from the initial switches and other sensing devices. EPB was able to avoid sending repair crews out in the field 250 times since the data provided outage information not previously available. Restoration was formerly done by EPB dispatchers sending repair crews to outage locations only after customers informed the company of such outages, costing time, money and longer outage periods. During the storms, the smart switches proved to be very valuable as thousands of hours of outage time were avoided due to the devices and automation already installed. Moreover, the experience with the new devices and automation indicates that EPB is on track to realize significant improvement once all of the automation is complete. Information derived from the smart switches will help the company analyze the impact of storms and will be useful for future planning purposes. "We expect the number of customer-minutes lost to power outages to be down by 40 percent or more, and that's something that will benefit customers throughout the whole area,” said Jim Glass, Manager of Smart Grid Development at EPB. EPB officials estimate the increased reliability from its project is worth at least $35 million a year to Chattanooga area businesses and homeowners. Weighted average based on numbers of feeders

15 Value of Service from Improvements in Reliability
Selected example from an SGIG project reporting initial results 1 project involving 230 automated feeder switches on 75 circuits in an urban area From Apr 1 – Sep SAIDI improved 24%; average outage duration decreased from 72.3 to 54.6 minutes Estimated Average Customer Interruption Costs US 2008$ by Customer Type and Duration Customer Type Interruption Cost Summer Weekday Interruption Duration Momentary 30 mins 1 hr 4 hr 8 hr Large C&I Cost Per Average kWh $173 $38 $25 $18 $14 Small C&I $2,401 $556 $373 $307 $272 Residential $21.6 $4.4 $2.6 $1.3 $0.9 Value of service is a measure of the amount that customers are willing to pay for electricity. It is used by many utilities in power system planning for determining the amount of new capacity needed to keep the system reliable and customers satisfied. VOS is estimated through surveys of customers involving sophisticated questionnaires and statistical models to determine their “willingness to pay” and from analysis of actual outage costs to customers from events. For the past decade, DOE-OE has supported data collection and analysis activities at LBNL on VOS. LBNL has published several reports including one that estimates national annual outage costs at about $75 billion. The LBNL studies are based on a “meta” analysis of value of service studies conducted by dozens of utilities across the country. LBNL, and its consultant, Freeman-Sullivan Group, has developed a downloadable analysis tool for applying value of service estimates to determine the monetary benefits from reliability improvements. The Interruption Cost Estimate (ICE) calculator is available from smartgrid.gov. Estimated monetary value of this improvement in reliability based on value-of-service data is $21 million VOS Improvement Δ = Δ SAIDI x Customers Served x Avg Load x VOS Coefficient VOS Estimate for SAIDI Improvement on 75 feeders from Apr 1 to Sep Customer Class Δ SAIDI Customers Served within a Class Average Load (kW) Not Served VOS Coefficient ($/kWh) Δ VOS Residential 17.7 mins (0.295 hrs) 107,390 2 $ $ 164,736 Commercial 8,261 20 $ $ 18,179,477 Industrial 2,360 200 $ $ 3,481,325 Total 118,011 $ 21,825,537 Sullivan J, Michael, 2009 Estimated Value of Service Reliability for Electric Utility Customers in the US, xxi

16 Applying Volt/VAR Optimization to Improve Energy Efficency
Conservation voltage reduction (CVR) reduces customer voltages along a distribution feeder for lowering peak demands and overall energy consumption Example Using SGIG Project Data Energy and Capacity CVR Factors Results averaged across 11 circuits % Reductions Potential savings for a 7 MW peak circuit with 53% load factor Customer Energy Reduction 2.9% 943 MWh/year $75,440 (at $.08/kWh) Peak Demand Reduction 3% 210 kW Defer construction of peaking plants Customer Voltage “CVR-off” voltage profile Voltage reduced by adjusting the LTC set-points “CVR-on” voltage profile OG&E Example: Implementing control algorithms to set voltage levels at the substation Applying smart meter data Capability turned on when power price exceeds $0.22/kWh Achieved 8 MW reduction from application of CVR technologies on 50 circuits during peak periods in the Summer 2011 Goal – 74 MW reduction over 400 circuits by 2017 (SGIG contributes 16 MW) Typical feeder is approximately 5 MW; however, utilities are targeting larger, heavier-loaded feeders to apply CVR. Therefore, used a 7 MW feeder in the example. (PNNL estimated that targeting 40% of the feeders nationwide for CVR results in 80% of the energy savings benefits nationwide) Studies dating back to the 1980s have shown that small reductions in distribution voltage can reduce electricity demand from customer equipment and save energy. This has become known as “conservation voltage reduction (CVR)”. Recent utility pilot programs have demonstrated that lowering distribution voltage by 1% can reduce demand and energy consumption by 1% or more. Distribution Source Voltage Distance along circuit 16

17 Case Study Investor-Owned Utility

18 Smart transformers report on health and status to FPL control centers
Florida Power and Light (FPL) Smart Grid Solutions Strengthen Electric Reliability and Customer Services in Florida Key Activities 3 million smart meters being installed with pilot programs testing customer systems and time-based rate programs. Thousands of substation devices for automating switches, capacitors, transformers, and regulators and equipment health monitors at substations. 45 phasor measurement units and supporting transmission line monitors. Aims and Strategies Improve reliability by monitoring key transmission and distribution equipment for preventative maintenance and avoidance of outages. Make operational efficiency improvements by reducing truck rolls for service calls by automating meter functions. Engaging customers through information exchange via web portals and pilot programs with customer systems and time-based rates Results and Benefits In January, 2012, monitor detected an out-of-tolerance high voltage bushing and customers served by this transformer temporarily switched to another one. Meanwhile, the faulty bushing replaced, preventing an outage that would have affected several thousand customers. In September, 2011, an alarm signaled a potential problem with a degraded phase on a capacitance voltage transformer. Field engineers located the damaged transformer, removed the affected transmission line section from service, and replaced the defective device thus preventing an extended outage and that could have affected several thousand customers. One of SGIG’s largest and most comprehensive projects Smart transformers report on health and status to FPL control centers Talking Points The Florida Power & Light (FPL) project is deploying advanced metering infrastructure (AMI), distribution automation, new electricity pricing programs, and advanced monitoring equipment for the transmission system. AMI supports two-way communication between FPL and its 3 million consumers receiving smart meters associated with the DOE grant, providing detailed information about electricity usage and the ability to implement new electricity pricing programs. New distribution automation devices expand the functionality of FPL’s distribution system to increase reliability, reduce energy losses, and reduce operations and maintenance costs. Synchrophasor and line monitoring devices help increase the reliability and security of the transmission system. Equipment: Advanced Metering Infrastructure Automated Capacitors Automated Distribution Circuit Switches Automated Voltage Regulators Distributed Energy Resource Interface Distribution Automation Equipment Condition Monitor Home Area Network In-Home Display Phasor Measurement Unit (PMU) Smart Meter - Industrial Transmission Line Monitoring System Targeted Benefits: Reduce Electricity Costs for Customers Reduced Meter Reading Costs Reduced Operating and Maintenance Costs Improved Electric Service Reliability and Power Quality Reduced Costs from Equipment Failures and Theft Reduced Greenhouse Gas Emissions Reduced Truck Fleet Fuel Usage Facts & Figures Total Project Budget: $578,000,000 Federal Share: $ 200,000,000 FPL Facts: 4.5 million customers 70,000 miles of power lines 16 power plants

19 Case Study Electric Cooperative

20 eEnergy Vermont A State-Wide Strategy for Smart Grid Development
Utilities working together to modernize the grid. Key Activities Smart metering roll-out for outage management and time-based rates for demand response. Distribution system automation including switches, reclosers, SCADA, and communications backbone systems. Consumer behavior studies by Vermont Electric Cooperative (VEC)and Central Vermont Public Service to assess customer acceptance, response, and retention. Aims and Strategies A collaborative effort involving all of the state’s electric distribution companies to modernize Vermont’s electric grid and foster economic growth as part of the state’s “eState Initiative” with telecommunications and health care. Results and Benefits VEC’s outage management system has improved SAIFI by 50% and CAIDI by 40% since installed in 2008. VEC’s smart metering roll-out and outage management system has a 5 year payback period from operational saving alone. VEC received POWER Magazine’s first “Smart Grid Award” in August for its pioneering efforts in outage management. Restoration of the grid from Tropical storm Irene occurred quicker and with greater customer awareness of repair schedules due to smart meters, web portals, and more effective outage management. Vermont Electric Cooperative’s Smart Grid Operations Center Facts & Figures Total Project Budget: $137,857,302 Federal Share: $69,928,650 Distribution Automation: 47 circuits and substations Smart meters: 311,380 Time-Based Rates: 1,500 customers targeted Talking Points Tropical storm Irene hit several eastern states during August 2011 and caused flooding, wind damage, and power outages. In Vermont, restoration of the power grid was accomplished more efficiently than in other places because of smart grid investments by the utilities there, some of which were made possible by eEnergy Vermont, a $138 million Smart Gird Investment Grant (SGIG) project involving $69 million in Recovery Act funds. Striving for a more competitive position in the global economy, eEnergy Vermont is part of a broader “eState Initiative” that includes telecommunications and health care and involves broadband and advanced information technologies deployed throughout the state. The project is already playing a role in Vermont’s economy. For example, a business in northern Vermont is expanding and plans to triple its electric demand from 5 to 15 megawatts over the next three years. By employing smart grid approaches to peak load management and energy efficiency, the serving utility says they will be able to make the business one of the state’s “most efficient electric customers.” Of the eEnergy Vermont utilities, VEC is furthest along the smart grid learning curve. since 2008, when VEC’s outage management system was completed, improvements have been realized in two key reliability indicators: the System Average Interruption Frequency Index decreased 50% and the Customer Average Interruption Duration Index decreased 40%. Participation in eEnergy Vermont enabled VEC to extend its smart meter roll-out to 100% of customers and to install automation equipment and SCADA systems on most of its substations. For these and other reasons, POWER Magazine gave VEC its first “POWER Smart Grid Award” in August 2011 saying, “A cooperative in northern Vermont serving a largely rural area has proven that even small utilities can achieve great smart grid results by planning wisely. For improving service to its members by developing a grid modernization strategy before “smart grid” was a buzz phrase, Vermont Electric Cooperative is the winner of the first POWER Smart Grid Award.” Participation in eEnergy Vermont has also been an opportunity for VEC to make workforce improvements. VEC has retained all positions and there have been no significant job losses even with the economic slowdown and the efficiency improvements from the smart grid investments. VEC now has a new “Substation Automation Group” comprised of 4-5 new positions, several of which were filled by retraining former meter technicians. DRAFT v. 1

21 Case Study Municipal Power

22 Smart switches help ensure grid reliability and power quality
Electric Power Board of Chattanooga Improved System Restoration Key Activities EPB’s Smart Grid Project covers 600 miles throughout 9 counties of Georgia and Tennessee affecting 170,000 customers. Installing automated feeder switches, automated circuits, advanced SCADA, AMI, in-home displays, and communications infrastructure. Aims and Strategies Electric Distribution System Automation – installing automated feeder switches and sensor equipment for distribution circuits that can be used to detect faults and automatically switch to reroute power and restore all other customers. Communications Infrastructure – includes fiber optic systems that enable two-way communication between the meters, substations, and control office which provides EPB with expanded capabilities and functionality to optimize energy delivery, system reliability, and customer service options. Results and Benefits During the April 2011 storms, three fourths of EPB customers – 129,000 residences and businesses – lost power. Smart switches avoided thousands of hours of outage time due to the devices and automation already installed   EPB was able to avoid sending repair crews out 250 times Integrating Smart Grid Applications Smart switches help ensure grid reliability and power quality Facts & Figures Total Project Budget: $226,707,562 Federal Share: $111,567,606 Equipment Deployed: Smart Switches: 1,500 AMI:170,000 Direct LC Devices: 5,000 HEMS: 5,000 Thermostats: 5,000 Automated Circuits:164 Talking Points EPB’s service territory (portions of TN and GA) experiences frequent severe weather. More than half of its customers lost power during April 2011 tornadoes, but already installed smart switches enabled fast system restoration for most customers. The smart switches are able to remotely detect customer outages, isolate damaged sections of their power lines, and restore power to customers more quickly and for much less cost. EPB expects customer-minutes lost to power outages to decrease by 40% or more as a result of the system upgrades. EPB will also upgrade its SCADA system, which will improve system controllers’ ability to see events happen in real time over the entire EPB service territory. Advanced metering infrastructure with improved two-way communications capabilities will also be deployed throughout EPB’s service territory. Project facts and figures: Total budget: $227 million Federal share: $111.5 million - 170,000 customers - Service territory of approximately 600 square miles - One of the largest publicly-owned power providers in the U.S. DRAFT DRAFT v. 1

23 Life After ARRA Smart Grid Program

24 Life After ARRA Smart Grid Program
Build and maintain momentum Make business case Identify, allocate, and quantify benefits Identify and quantify costs Address technical issues Address regulatory issues Address customers concerns Key is to build and maintain momentum of ARRA smart grid program Make the business case for electric service providers and consumers that benefits outweigh costs Identify, quantify, and monetize benefits and allocate to utility, consumer, and society Identify and quantify incremental costs Address technical issues such as interoperability, cyber, communications, controls, stability Address regulatory issues of allocation of costs and benefits and recovery of costs; address issues with costs outweighing benefits during early implementation Address consumers concerns such as privacy, benefits, cyber risks, comfort and convenience, understanding

25 Contact Information Steve Bossart (304) Federal Smart Grid Website Smart Grid Clearinghouse Smart Grid Implementation Strategy Questions ?


Download ppt "Success Stories in DOE’s ARRA Smart Grid Program"

Similar presentations


Ads by Google