DITS Project – M. Houry 27 th of april Y07 DITS PROJECT SCHEDULE.

Similar presentations


Presentation on theme: "DITS Project – M. Houry 27 th of april Y07 DITS PROJECT SCHEDULE."— Presentation transcript:

1 DITS Project – M. Houry 27 th of april Y07 DITS PROJECT SCHEDULE

2 DITS Project – M. Houry 27 th of april Y07 A Project Management Office has been established in the DITS project organization DITS project organization. The PMO provides a help in terms of : Schedule, Human ress., Risk, Cost, Communication, Reviewing Management Mean Goals : Built ONE Work-Plan based on Work-Packages What you must do Periodic progression measurements Analysis of shifts & risks anticipation Appropriate corrections or treatments Management Team Project Time & Res. Management Project Risk, Cost & Quality Management Project Safety Management

3 DITS Project – M. Houry 27 th of april Y07 The DITS schedule is made of 6 Work-Packages WP0 - Management Time, cost, human resources, quality, risk, safety, communication, reviews WP1 – Particle balance experiments D 2 Plasma experiments for TPL loading WP2 – TPL Dismantling Extraction – Operations – Mounting WP3 – ANALYSIS Preparations and analysis on the TPL, fingers, tiles and samples WP4 – SATELLITE PROGRAMS IR program (R. Reichle) PFC (J. Schlosser) Detritiation (H. Roche) DUST (S. Rosanvallon) WP5 – CO ACTIVITIES Acoustic sensors (X. Courtois) Tore Supra Summer Shut-down Tore Supra Experimental program

4 DITS Project – M. Houry 27 th of april Y07 Work Package 1 & 2 : TPL loading and Dismantling Sept.Mai MayJuin JuneJuil..July.Août Aug. Removing ICRH(Q1) & TPL(Q6A)TPL Loading : 24/05 to 07/06 Fingers exchange Spare Fingers validation Qualification tests TPL & ICRH installing 3D Cartography Meas. WP1 WP2 WP3 Tore Supra Summer Shut-down for maintenance operations

5 DITS Project – M. Houry 27 th of april Y07 WP3 : Analysis 3D Cartography on fingers TPL back in TS Assembly - tests 18/07 AprilMayJuneJulyAug.Sept. 3D cartography measurements Structure 22/06 Optics 04/07 3D Cartography on sector 02/08 24/08

6 DITS Project – M. Houry 27 th of april Y07 WP3 : Preparation for analysis Fingers – Tiles extraction – Samples cutting Aug.Sept.Oct. Samples characterization Fingers activity control Safety authority agreement 13/09 Tiles dismantling 26/09 Tiles cutting Samples 11/10 3D Cartography Ready for analysis 22/10