Presentation is loading. Please wait.

Presentation is loading. Please wait.

Quantitative Review II

Similar presentations


Presentation on theme: "Quantitative Review II"— Presentation transcript:

1 Quantitative Review II
ISQS Introduction to Production and Operations Management Spring 2014 Quantitative Review II

2 Taguchi Loss Function Design the product or service so that it will not be sensitive to variations during the manufacturing or delivery process For example, design a manufactured good with a smaller design tolerance = better quality

3 Taguchi Loss Function where L(x) = the monetary value of the loss
associated with deviating from the target limit “T” k = the constant that translates the deviation into dollars x = the actual value of the dimension T = target limits

4 A quality characteristic has a specification (in inches) of 0. 200  0
A quality characteristic has a specification (in inches) of  If the value of the quality characteristic exceeds by the tolerance of on either side, the product will require a repair of $150. Develop the appropriate Taguchi loss function (k).

5 A quality engineer has a manufacturing specification (in cm) of 0
A quality engineer has a manufacturing specification (in cm) of plus or minus Historical data indicates that if the quality characteristic takes on values larger than .250 cm or smaller than .150 cm, the product fails and a cost of $75 is incurred. Determine the Taguchi Loss Function and estimate the loss for a dimension of cm.

6 Reliability Management
Series product components Parallel product components

7 The manufacturing of compact disks requires four sequential steps
The manufacturing of compact disks requires four sequential steps. The reliability of each of the steps is 0.96, 0.87, 0.92, and 0.88 respectively. What is the reliability of the process?

8 Parallel/Redundancy B .91 A C .98 .97 B .91

9 Given the diagram below, determine the system reliability if the individual component reliabilities are: A = 0.94, B = 0.92, C = 0.97, and D = 0.93. A D C B RaRb = 1 - ( )( ) = RcRd = 1 - ( )( ) = RabRcd = (0.9952)(0.9979) =

10 The system reliability for a two-component parallel system is 0. 99968
The system reliability for a two-component parallel system is If the reliability of the first component is 0.99, determine the reliability of the second component. = 1 – (1 – 0.99)(1 – p2) = 1 – (0.01 – 0.01p2) –1 = p2 p2 = 0.968

11 More Reliability Question
What is the reliability of this system? If you could add one process (must be one of the existing processes) to best improve reliability what would be the improved reliability? A 0.987 B 0.895 C 0.947 D 0.918

12 More Reliability Question -- Solution
0.987 B 0.895 C 0.947 D 0.918 Reliability = 0.987*0.895*0.947*0.918= 0.768 A 0.987 B 0.895 C 0.947 D 0.918 Parallel B Reliability = 1-( )*( ) = 0.989 System Reliability = 0.987*0.989*0.947*0.918 = 0.849 Improvement = – = 0.08

13 Kanban where: K = the number of Kanban cards
d = the average production rate OR demand of product p = the processing time w = the waiting time of Kanban cards α = safety stock as a %, usually ranging from 0 to 1 C = the capacity of a standard container

14 Computing the number of kanbans: An aspirin manufacturer has converted to JIT manufacturing using Kanban containers. They wish to determine the number of containers at the bottle filling operation which fills at a rate of 400 per hour. Each container holds 35 bottles, it takes 30 minutes to receive more bottles (processing plus delivery time) and safety stock is set at 10%. d = 400 bottles per hour p+w = 30 minutes or 0.5 hour C = 35 bottles per container α = 0.10

15 Location Analysis Methods
Factor Rating Method: Σ (Factor Weighti * Factor Scorei) 5*10= 2*10= 4*20= 2*20= 2*30= 5*30= 5*10= 3*10= 3*30= 5*30=

16 Location Analysis Methods
Center-of-Gravity Method: where dix = x-coordinate of location i diy = y-coordinate of location i Qi = Quantity of goods moved to or from location i

17 Center-of-Gravity Method
Where would be the best place to put the warehouse? Location X coordinate Y Number of Containers Shipped per Week Chicago 30 120 2,000 Pittsburgh 90 110 1,000 New York 130 Atlanta 60 40

18 Question 3 A Plus Logistics Co. has just signed a contract to deliver products to three locations, and they are trying to decide where to put their new warehouse. The three delivery locations are Chicago, Pittsburgh, and New York. Which town would be the best place to put the warehouse?

19 Question 3 (Continued)

20 Question 3 -- Solution (130)(1000) = (130)(1000) =120 Therefore, the best place to put warehouse is Insanity!

21 Location Analysis Methods
Load Distance Model: Find load distance score by: Calculate the rectilinear distance and multiply by the number of loads

22 Load Distance Score for AB = 45*4 = 180
Load Distance Model Calculate Rectilinear Distance Identify Loads, i.e., 4 loads from A to B Load Distance Score for AB = 45*4 = 180

23 TT Logistics Co. has just signed a contract to deliver products to three locations, and they are trying to decide where to put their new warehouse. The three delivery locations are A, B, and C. The two potential sites for the warehouse are D and E. The total quantity to be delivered to each destination is: 200 to A, 100 to B, and 300 to C. The x, y coordinates for the delivery locations and warehouses are as follows: Where to locate warehouse, D or E? Location X coordinate Y Location A 92 42 Location B 80 40 Location C 90 35 Warehouse D 45 Warehouse E

24 Load Distance Score Warehouse D Distance Loads Score
Location X coordinate Y Location A 92 42 Location B 80 40 Location C 90 35 Warehouse D 45 Warehouse E Load Distance Score Warehouse D Distance Loads Score Location A = Location B 10+5= Location C 0+10= 5500 Warehouse E Location A = Location B 10+0= Location C 0+5= 3300

25 Designing Process Layouts
Step 1: Gather information Space needed, space available, importance of proximity between various units Step 2: Develop alternative block plans Using trial-and-error or decision support tools Step 3: Develop a detailed layout Consider exact sizes and shapes of departments and work centers including aisles and stairways Tools like drawing, 3-D models, and CAD software are available to facilitate this process.

26 Process Layout (Step 1: Gather information)
Recovery First Sports Medicine Clinic Layout (total space 3750 sq.ft.) A 400 sq.ft. B 300 sq.ft. C D 800 sq.ft. E 900 sq.ft. F 1050 sq.ft.

27 Process Layout (Step 2: Develop a block layout)
Current Proposed A 400 sq.ft. B 300 sq.ft. C D 800 sq.ft. E 900 sq.ft. F 1050 sq.ft. A 400 sq.ft. D 800 sq.ft. C 300 sq.ft. E 900 sq.ft. B F 1050 sq.ft. Proposed layout would require less walking.

28 Load Distance Problem A B C D E F 10 30 15 20 5 25
What is the load distance for this layout? Trips between departments B A D C E F Dept. A B C D E F 10 30 15 20 5 25

29 Load Distance Problem A B C D E F 10 30 15 20 5 25 Depts. Trips
15 20 5 25 Depts. Trips Distance Score AB 10 1 AC 30 2 60 AD AF 20 BD BE 15 BF 3 45 CD CE CF 5 EF 25 345

30 Assembly Line Balancing
Step 1: Identify task & immediate predecessors Step 2: Calculate the cycle time Step 3: Determine the output rate Step 4: Compute the theoretical minimum number of workstations Step 5: Assign tasks to workstations (balance the line) Step 6: Compute efficiency, idle time & balance delay

31 Assembly Line Balancing (Step 1: Identify tasks & immediate predecessors)

32 Layout Calculation Step 2: Determine cycle time (The amount of time each workstation is allowed to complete its tasks.) Cycle time = Station A (50 seconds) -- the bottleneck Step 3: Determine output rate Step 4: Compute the theoretical minimum number of workstations (number of station needed to achieve 100% efficiency)

33 Assembly Line Balancing (Step 5: Balance the line)
3 Work Stations (A,B), (C,D,G), (E,F,H,I) 55 sec 55 sec 55 sec

34 Assembly Line Balancing (Step 6: Compute efficiency, idle time & balance delay)
Balance Delay = 1 – Assembly Line Efficiency

35 Line Balancing Problem
What is the bottleneck? What is the maximum production per hour? What is efficiency and balance delay? How to minimize work stations? How should they be groups? New efficiency? A B C 4.1 mins D 1.6 mins E 2.7 mins F 3.3 mins G 2.6 mins 2.3 mins 3.4 mins

36 Line Balancing Problem
What is the bottleneck? 4.1 minutes What is the maximum production per hour? 60/4.1 = units/hour What is efficiency and balance delay? Efficiency = 20/(7*4.1) = 69.69% Balance Delay = = 30.31% How to minimize work stations? Should we use 4 or 5 work stations?

37 4 Work Stations Efficiency = 20/(4*6) = 20/24 = 83.3%
Balance delay = = 16.7% Maximum production/hour = 60/6 = 10 units/hour A B C 4.1 mins D 1.6 mins E 2.7 mins F 3.3 mins G 2.6 mins 2.3 mins 3.4 mins 5.7 mins 6 mins 2.6 mins 5.7 mins

38 5 Work Stations Efficiency = 20/(5*5.7) = 20/28.5 = 70.18%
Balance delay = = 29.82% Maximum production/hour = 60/5.7 = units/hour A B C 4.1 mins D 1.6 mins E 2.7 mins F 3.3 mins G 2.6 mins 2.3 mins 3.4 mins 5.7 mins 2.7 mins 4.1 mins 2.6 mins 4.9 mins

39 Should we use 4 or 5 or 7 work stations?
Efficiency = 83.3% Balance delay = 16.7% Maximum production/hour = 10 units/hour 5 Work Stations Efficiency = 70.18% Balance delay = 29.82% Maximum production/hour = units/hour 7 Work Stations Efficiency = 69.69% Balance delay = 30.31% Maximum production/hour = units/hour

40 Supply Chain Efficiency
Measuring Cash to Conversion Cycle Inventory Turnover (IT) Inventory Days’ Supply (IDS) Accounts Receivable Turnover (ART) Accounts Receivable Days’ Supply (ARDS) Accounts Payable Turnover (APT) Accounts Payable Days’ Supply (APDS) Cash-to-Cash Conversion Cycle = IDS + ARDS - APDS

41 Inventory Ratios Inventory Turnover (IT):
# of times you turn your inventory annually Inventory Days’ Supply (IDS): how many days inventory you keep

42 Accounts Receivable Ratios
Accounts Receivable Turnover (ART): # of times you turn your accts. rec. annually Accounts Receivable Days’ Supply (ARDS): how long it takes to get $ owed paid to you

43 Accounts Payable Ratios
Accounts Payable Turnover (APT): # of times you turn your accts. payable annually Accounts Payable Days’ Supply (APDS): how long you take to pay your bills

44 Dell’s Financial data Revenue $35.40 billions
Cost of goods sold $29.10 billions Average Inventory Value $0.306 billions Average Accounts Receivable $2.586 billions Average Accounts Payable $5.989 billions

45 Dell’s Example Dell’s Inventory Turnover Dell’s Inventory Days’ Supply

46 Dell’s Example Dell’s Accounts Receivable Turnover
Dell’s Accounts Receivable Days’ Supply

47 Dell’s Example Dell’s Accounts Payable Turnover
Dell’s Accounts Payable Days’ Supply

48 Dell’s Example Dell’s Cash-to-Cash Conversion Cycle
= IDS + ARDS – APDS = 3.84 days days – days = days The negative value means that Dell receives customers’ payments (accounts receivable) days, on average, before Dell has to pay its suppliers (accounts payable). This means that Dell’s value chain is a self-funding cash model.

49 Dell’s Negative Cash-to-Cash Conversion Cycle

50 Breakeven Analysis (Make/Buy Decision)
Total Cost of Outsourcing: Total Cost of Insourcing: Indifference Point:

51 The Bagel Shop Problem Jim & John plan to open a small bagel shop.
The local baker has offered to sell them bagels at 50 cents each. However, they will need to invest $2,000 in bread racks to transport the bagels back and forth from the bakery to their store. Alternatively, they can bake the bagels at their store for 20 cents each if they invest $20,000 in kitchen equipment. They expect to sell 80,000 bagels each year. What should they do?

52 The Bagel Shop Problem Indifference Point Calculation:

53 The Bagel Shop Problem Make vs Buy Decision at 80,000 bagels
Outsource (Buy) In House (Make) $2,000+($.5*80,000) $20,000+($.2*80,000) = $42, = $36,000 Make vs Buy Decision at 50,000 bagels $2,000+($.5*50,000) $20,000+($.2*50,000) = $27, = $30,000 If the demand is lower than the indifference point, outsourcing is a cheaper alternative, and vice versa.

54 That’s all, folks! Good Luck!


Download ppt "Quantitative Review II"

Similar presentations


Ads by Google