Presentation is loading. Please wait.

Presentation is loading. Please wait.

CRITICAL PATH ANALYSIS aka NETWORK PATH ANALYSIS DESIGNED to help managers who are planning complex projects that involve many interrelated tasks The idea.

Similar presentations


Presentation on theme: "CRITICAL PATH ANALYSIS aka NETWORK PATH ANALYSIS DESIGNED to help managers who are planning complex projects that involve many interrelated tasks The idea."— Presentation transcript:

1 CRITICAL PATH ANALYSIS aka NETWORK PATH ANALYSIS DESIGNED to help managers who are planning complex projects that involve many interrelated tasks The idea is to help identify which of these interrelated task are the CRITICAL ones. Any change in these ‘critical’ tasks will have a significant impact* on the overall project * “impact”, relates firstly to time delays in this context

2 The general idea BUILDING A BRIDGE Lots of interrelated tasks eg To build the bridge you need both the passway and the base. They are in fact interrelated by by TIME. To build the passway you FIRST have to build the base. Any delay in the building of the base, is going to cause a delay in the building of the passway Building of the base is a critical activity

3 Don’t copy any of these down !

4 THE CRITICAL PATHWAY is made up of NODES. Node number [in order of the network] Earliest Start Time Latest Finishing Time Activity / task Duration of activity A node for each independent activity/task On the very first node these will both be ZERO For the preceding task For this task = EST of following node - Duration of current activity

5 For node 5 the Latest Finishing Time [for activity D & E] is 10. They must both be finished by the 10 th week or else the Final Finishing Time will be delayed. This makes sense because if the activity F cannot be started until the 11 th week and takes 1 week itself, the Final Finishing Time will be week 12! Therefore all activities preceding Node 5 must be finished by week 10 at the latest. It can be calculated by the “EST of node 6 (11) – Duration of F (1) = 10”

6 Node number [in order of the network] Earliest Start Time Latest Finishing Time Activity / task Duration of activity For the preceding task For this task = EST - Duration The LFT [for activity 4] recorded in Node 8 will be the same as the EST in Node 8 because there is no following node and no activity The EST means ‘what is the earliest the ‘end’ can start’ and will be : the EST of node 7 + Duration of Activity 4 The activity of the final node is not shown as it is the ‘end’

7 Lets try a simple example You cannot leave the classroom until you have finished your work and tidied up 0 0 a. Finish work 30 mins 30 b. Tidy up 7 mins 37 ESTs & LFTs are the same because this is a simple example with no parallel tasks

8 Lets try one that’s a little harder You cannot leave the classroom until you have all finished your work, girls should then tidy up and put up the chairs while guys put away the laptops 0 0 a. Finish work 30 mins 30 b. Tidy up 7 mins 45 37 39 c. clear laptops 15 mins d. Put up chairs 6 mins EST’s Duration of task is the next issue to identify… 1 : same as before = 0 2 : same as before = 30 3 : 30 + 7 = 37 4: 37 + 6 = 43 or 30 + 15 = 45 ? Always the LONGER therefore = 45 LFT’s Go in reverse 4: 45, remember it’s the same. 3 :45-6 = 39 2 : 39 – 7 = 32 or 45 – 15 = 30 Always the SHORTER therefore 30 1. 0, remember it’s the same.

9 A A A B B B C C D Neither task C nor D can start until tasks A and B are completed Neither task B nor D can start until tasks A and C are completed Task D can be started when Task C is completed Neither task B nor C can start until tasks A is completed Task A will be divided up into two tasks : B & C Task B cannot be started before Task A is complete Task A must be started before Task B, but either could finish first

10 BUT AT THIS STAGE WE HAVE NOT YET LOOKED AT THIS IDEA OF ‘CRITICAL’ “TASKS THAT CANNOT BE ALTERED WITHOUT AFFECTING THE WHOLE PRODUCTION PROCESS”

11 0 0 a. Finish work 30 mins 30 b. Tidy up 7 mins 45 37 39 c. clear laptops 15 mins d. Put up chairs 6 mins To identify the critical tasks Lets assume a universal small change of 1 minute Now last 31 minutes. That will affect the EST of Node 2 – & push it up to 31 min. Now last 8 minutes. That will affect the EST of Node 3 and push it up to 39 min. Now last 16 minutes. That will affect the EST of Node 4 and push it up to 47 min. Now last 7 minutes. That will affect the EST of Node 4 and push it up to 46 min. ? The Critical Tasks are A and B, so the Critical Path is shown by the route connecting Nodes 1, 2 and 3 ALL CRITICAL tasks WILL HAVE E.S.T.s THAT ARE EQUAL TO THEIR L.F.T.s

12 Common Error a b c c 2 tasks starting at the same time, with the same follow-on task. You cant draw it as we see because this would indicate that task a & b are the same duration It would need to be as we have drawn before [see left] A B C

13 (Code) TaskPreceded by Duration (mins) A. Take a shower-10 B. Have breakfastA15 C. Text friendsA6 D. Get dressedC10 E. Drive to interviewB & D25 1. Draw the NETWORK Diagram 2. Identify the Critical Path 3. How long should you allow yourself to get to the interview on time?

14 0 0 15 10 B C A 6 26 16 D 10 25 E 51 We also talk about a FLOAT Is an activity which has an amount of time by which it can be extended and not affect the overall project time frame Which task here has a float? And how large is this float? Activity B! 1 minute

15 P719 -722 reading p723 Q5.8.1 7 3 A B F 0 0 5 7 7 5 5 D 5 2 C 9 10 13 E 3

16 P723 reading p724 Q5.8.2 0 0 6 weeks 1 week A. foundation 1 1 7 7 3 8 11 B. Construction C. Pool E&F 2 weeks D. Pool T&S 2 weeks E. House ID&F 3 weeks 10 F. Final Testing 1 week Explain why its important?..... 4 marks

17 P724 -726 reading p727 Q5.8.3 FREE FLOAT = EST (of next) – Duration (of current) – EST (of current) The amount of time that an activity can be delayed without affecting the EST of the next activity TOTAL FLOAT = [ LFT (of next) – Duration (of current) – EST (of current) ] You then add up all the Total Floats The amount of time a sequence of tasks can be delayed without affecting the whole process 0 0 4 4 A. 4 4 8 11 7 7 B. C. 3 11 14 16 21 5 E. 5 H 4 D 3 F 2 G FF = ActB = 8-4-4 = 0 ActE = 16-5-8 = 3 TF = ActB = 11-4-4 = 3 ActE = 16-5-8 = 3 = 6

18 P727 -728 reading p729 Q5.8.4

19 P729 - 730 reading

20 The revised times are: CODETASK D45 E120 F30 Recalculate the network diagram and show the new time for the whole project. State whether the critical path has changed [3 marks] 3. Using this information and evidence from the case itself evaluate whether Max should go ahead and build the cottages [6 marks] MAXS COTTAGES [revised] QUESTION 2. continued [6 marks]

21 0 0 30 A 45 B 60 C 105 75 105 30 D 195 90 E 5 J 20 I F 235 255 260 215 30 G 20 H 275 15 K 195 Assume you need to B.Build Access Road in order to bring in the cement needed to C.Lay Foundation ie Task C is preceded by A&B Assume also that you need to B.Build Access Road in order to bring in the materials needed to C.Lay Cables + Water Pipes ie Task D is preceded by A&B too 0 0 MAXS COTTAGES [revised] ANSWER

22 0 0 30 A 45 B 60 C 105 75 105 30 D 225 90 E 5 J 20 I F 275 295 300 255 30 G 20 H 315 15 K 225 Assume you need to B.Build Access Road in order to bring in the cement needed to C.Lay Foundation ie Task C is preceded by A&B Assume also that you need to B.Build Access Road in order to bring in the materials needed to C.Lay Cables + Water Pipes ie Task D is preceded by A&B too 0 0 45 120 30 MAXS COTTAGES [revised] ANSWER

23 QUANTITATIVE You originally reduced the Project Time by 90 days, to 275 days. Which is a 25% reduction. He then, in his re-estimations, bought it back up again by 55 days. Which is 20% increase (in relation to your New Project Time.) However 15 of those 55 days where part of the Float in Activity D so the Project Time only went up by 40 days which represents a 15% increase (in relation to your New Project Time). The Final Revised Project Time is now 315 days, which is still 50 days less than originally quoted. Or 14% less. He has bought his final prices down by $30 000 which represents 20%. His prices have gone from $411/day to $381/day (although this ignores material costs) QUALITATIVE He seems to be an over-charger, and requires careful watching. Do we want to get into a relationship with him? HOWEVER Do we have other options? Will they be any better. What is the likelihood of getting the Planning Permission? On time? If there is delays not caused by the Builders, what will be their overtime charge rates? Significant saving possible with Just-in-Time, provided motivation sand weather remain predictable Conclusion : We seem to have got a more competitive prices now and if we are willing to commit time to building a positive relationship with our supplier then I would recommend we go ahead. We should of course bear in mind that the CPA has limitations and numerous unforeseen factors might extend the actual task time. MAXS COTTAGES [revised] ANSWER

24 The revised times are: CODETASK D45 E120 F30 Recalculate the network diagram and show the new time for the whole project. State whether the critical path has changed [3 marks] 3. Using this information and evidence form the case itself evaluate whether Max should go ahead and build the cottages [8 marks] MAXS COTTAGES [original] QUESTION 2. continued

25 0 0 30 A 45 B 30.. 60 C 45 260 90 60 30 D 180 90 E 5 J 20 I F 220 240 245 200 30 G 20 H 260 15 K 180 Assume you need NOT B.Build Access Road in order to C.Lay Foundation MAXS COTTAGES [original] ANSWER

26 0 0 30 A 45 B 30 60 C 45 300 90 75 60 30 D 210 90 E 5 J 20 I F 260 280 285 240 30 G 20 H 300 15 K 210 Assume you need NOT B.Build Access Road in order to C.Lay Foundation 45 120 30 MAXS COTTAGES [original] ANSWER

27 QUANTITATIVE You originally reduced the Project Time by 105 days, to 260 days. Which is a 29% reduction. He then, in his re-estimations, bought it back up again by 55 days. Which is 21% increase (in relation to your New Project Time.) However 15 of those 55 days where part of the Float in Activity D so the Project Time only went up by 40 days which represents a 15% increase (in relation to your New Project Time). The Final Revised Project Time is now 300 days, which is still 65 days less than originally quoted. Or 18% less. He has bought his final prices down by $30 000 which represents 20%. His prices have gone from $411/day to $400/day (although this ignores material costs) QUALITATIVE He seems to be an over-charger, and requires careful watching. Do we want to get into a relationship with him? HOWEVER Do we have other options? Will they be any better. What is the likelihood of getting the Planning Permission? On time? If there is delays not caused by the Builders, what will be their overtime charge rates? Conclusion : We seem to have got a more competitive prices now an dif we are willing to commit time to building a positive relationship with our supplier then I would recommend we go ahead MAXS COTTAGES [original] ANSWER


Download ppt "CRITICAL PATH ANALYSIS aka NETWORK PATH ANALYSIS DESIGNED to help managers who are planning complex projects that involve many interrelated tasks The idea."

Similar presentations


Ads by Google