Presentation is loading. Please wait.

Presentation is loading. Please wait.

PRINCE2: 2009 Project Progress Update Andy Murray – Outperform

Similar presentations


Presentation on theme: "PRINCE2: 2009 Project Progress Update Andy Murray – Outperform"— Presentation transcript:

1 PRINCE2: 2009 Project Progress Update Andy Murray – Outperform
BPUG Workshops at Project Challenge are supported by:

2 Progress Update Version 3.2
PRINCE2: 2009 Project Progress Update Version 3.2 Warning: this presentation provides a snapshot of the current approach. As the development is based on continued user consultation the final result may be different. Always check the website for latest information.

3 Reasons For Change - mandate
Reason for change: 10 years old – reviewed for ‘fitness’ every 3 to 5 years Projects are different – e.g. New Thinking MSP and M_o_R updated – needed to integrate to (finally) create an integrated set Decision for a refresh (step change) not a rewrite (incremental, corrections) Public consultation started November 2006 and concluded in June 2007. Summarised in Public Consultation Report issued in June 2007 More than 160 organisations and individuals consulted from all sectors and internationally OGC mandate stated that the revised method still needed to look like PRINCE2 – therefore we asked people what they regarded as the essential elements Interesting to note how many mis-truths were captured in the consultation. It became clear that the method is largely ok, it is mainly the perception and application of the method that is weak This is what happens when the immovable object meets the irresistible force Users want more content and OGC want ‘new thinking’ included Users say manual is too big and OGC set limit of 200 pages. Therefore needed to take an alternate approach (see next slide re 3 publications) NB, Core Manual size raised to <275 (April 08)

4 Proposed Approach Supporting Guides The Method PRINCE2
Knowledge Centre (on-line) Templates Case Studies Checklists Guides The Method Directing Successful Projects Using PRINCE2 Managing Successful Projects Using PRINCE2 Supporting Guides Pocketbook Think PRINCE2 P2MM Guide PRINCE2 and DSDM etc

5 New PRINCE2 Explain: Processes largely unchanged – explain more later
Components are now “Key Themes” – reason is that components implied they added up to 100%, whereas there is more to project management than PRINCE2 – will explain more later Have added PRINCIPLES – to overcome the issue of PINO Explicitly covers the need to adapt the method to the project’s environment (context) – resolving the issue of a universal method (general) being applied to a given project (specific)

6 The Project Environment
Summary of changes 2005 2009 Principles - 7 Principles Themes 8 Components 7 Key Themes Processes 8 Processes 7 Processes Sub-processes 45 sub-processes Techniques 3 techniques Cross-references to other BoKs including ‘soft’ aspects Management Products 36 products 27 products The Project Environment Context rich Trouble-shooting Hints & Tips Hints & Tips in FAQ style Explain: 7,7,7 by chance We defined what we meant by a Theme and Principle and then applied the test against the current manual content and against recommendations from the public consultation – this provided us with the short list of principles, themes and processes. For each major change we produce a design note covering for/against options We held a design review to seek external (expert) opinion on the proposed changes Management Products defined for the typical project – can still scale up and down

7 What are Principles? Principles are: Universal Self Validating
Empowering “A guiding obligation for good practice”

8 The PRINCE2 Principles Business Justification Learn Lessons
A PRINCE2 project has continued business justification Learn Lessons PRINCE2 project teams learn from previous experience (lessons are sought and recorded throughout) Roles & Responsibilities A PRINCE2 project has defined and agreed roles and responsibilities with an organisation structure that engages the business, user and supplier stakeholder interests Manage by Stages A PRINCE2 project is planned, monitored and controlled on a stage by stage basis Manage by Exception A PRINCE2 project has defined tolerances for each project objective to establish limits of delegated authority Product Focus A PRINCE2 project focuses on the definition and delivery of products, in particular their scope and quality requirements Tailor PRINCE2 is tailored to suit the project’s size, environment, complexity, importance, capability and risk These principles were also derived from the ‘common causes of project failure’

9 PRINCE2 Processes Processes Activities Recommended Actions No sub-processes No codification of processes (e.g. DP1, SU2) Less emphasis on prescriptive sequence “The processes provide the lifecycle based list of project management activities”

10 PRINCE2 Processes DP SU SB SB CP IP CS CS MP MP Pre-project
Initiation Stage Subsequent Stage(s) Final Stage DP Directing SU SB SB CP Managing IP CS CS Delivering MP MP Key: SU = Starting Up a Project DP = Directing a Project IP = Initiating a Project SB = Managing a Stage Boundary CS = Controlling a Stage MP = Managing Product Delivery CP = Closing a Project Note: SU is used by both the direction and management layers There should be at least two management stages, the first of which is the initiation Stage. SB is first used at the end of the initiation Stage and repeated at the end of each subsequent Stage except the final Stage.

11 The Process Model

12 Example Process

13 What are Key Themes? Key Themes are: And
aspects of project management that need to be continually addressed. They are not one off activities And aspects of project management that requires specific treatment for the PRINCE2 processes to be effective Explain previous issue with components (a component is an element of project management). Give example of specific treatment (organisation roles) Explain why Configuration Management was dropped. “If the processes are considered as the time-based activity list then the Key Themes are the reference manual. If the process requires action the Key Theme provides guidance on how it should be done.”

14 The PRINCE2 Key Themes Business Case Organisation Quality Plans Risk
Defining the business objectives (the why) Organisation Establishing the structure of accountability and responsibilities (the who) Quality Defining and verifying products that are fit-for-purpose (the what) Plans Facilitate communication and control by defining the means of delivering the products (the where and how, and estimating the when and how much) Risk Identifying, assessing and controlling uncertainty (what if) Change Managing the integrity of products and making decisions on issues which may affect the objectives Progress Monitoring the achievement of objectives and making decisions based on actual and forecast progress

15 The Project Environment
Embedding Tailoring Done by the organisation to adopt PRINCE2 Done by the project team to adapt the method to the context of a specific project scale of project within a programme industry sector (e.g. private/public, customer/supplier) type of project (e.g. R&D, policy, construction) multi-organisation corporate/programme standards (e.g. procurement) working with other methods and frameworks Focus on: process ownership scaling rules / guidance (e.g. score card) Standards (templates, definitions) training and development strategy integration with business processes tools process assurance roles & responsibilities to allocate management products to use and how number, length and nature of stages reporting and reviewing tolerances use of PRINCE2 processes Guidance in PRINCE2 Maturity Model Guidance in the Method

16 Project Scale Non-Projects Scary Projects Typical Projects
Programmes Simple Projects Typical Projects Scary Projects Projects Non-Projects Tasks

17 Project Scale Non-Projects Scary Projects Typical Projects
MSP Scary Projects Guidance No business case Work Package Product Description (s) Logs PM = team Typical Projects PRINCE2 Simple Projects Non-Projects Managing Product Delivery

18 Project Scale Non-Projects Scary Projects Typical Projects
MSP Guidance As per non-projects + Business case and PID Single Stage Exec & PM only Scary Projects Typical Projects PRINCE2 Simple Projects Non-Projects Managing Product Delivery

19 Project Scale Non-Projects Scary Projects Typical Projects
Guidance As per simple projects + Most Management Products Single or Multi-stage Stage Full Project Board Non-Projects MSP Scary Projects Typical Projects PRINCE2 Simple Projects Non-Projects Managing Product Delivery

20 Project Scale Non-Projects Scary Projects Typical Projects
Guidance As per typical projects + Multi-stage Stage Full Management Products Team Managers Project Support Non-Projects MSP Scary Projects Typical Projects PRINCE2 Simple Projects Non-Projects Managing Product Delivery

21 Directing Successful Projects Using PRINCE2
Duties & Behaviours Be accountable Provide unified direction Delegate effectively Facilitate cross-functional integration Commit resources Ensure effective decision-making Support the project manager Ensure effective communication Approach Lifecycle oriented Pre-project Project Post-project Providing Example Agenda Decision checklist Role guidance by stakeholder perspective Business User Supplier Focus on ‘duties & behaviours”

22 Management Products Philosophy Will be supported by a set of templates
designed for typical projects can be scaled up can be scaled down Will be supported by a set of templates with embedded guidance and quality criteria “PRINCE2 requires information and decisions, not documents and meetings”

23 Management Products Organised by Baseline products Records Reports
Nesting of management products is explicit

24 Next Steps Quality Reviews (second draft, final draft)
Feedback from pilots Surveys – to address options and test quality criteria Proof of Concept (for exam syllabus) Further consultation (for enhanced exam scheme) Transition period Q1 2009

25 Any Questions? Warning: this presentation provides a snapshot of the current approach. As the development is based on continued user consultation the final result may be different. Always check the website for latest information:

26 Speaker Profile – Andy Murray
Andy Murray is a Chartered Director and PRINCE2 Registered Consultant, having worked in the field of Projects and Programmes for over 15 years. He is currently a director of Outperform UK Ltd ( an Accredited Consultancy Organisation (ACO) licensed to consult in the OGC’s best practice trilogy of PRINCE2™, MSP and M_o_R®. Andy was an early adopter of PRINCE2™, back in 1997, and has been helping organisations implement and gain value from PRINCE2™ ever since. He has helped implement PRINCE2™ in numerous organisations in more than a dozen countries. Andy has been using maturity models as a consulting aid for more than five years, since they help diagnose an organisation’s strengths and weaknesses, prioritise improvement initiatives and measure progress. Andy has used the OGC’s PRINCE2™ Maturity Model (P2MM) and Portfolio, Programme and Project Management Maturity Model (P3M3) as a means to both benchmark organisations via the APM Group assessment process and to define improvement plans. Andy is the co-author the P2MM Guide - published in July 2007 by TSO. Andy is the Lead Author for PRINCE Key Points: ACO Independent ISO 9001 Registered Consultants Practitioners, NOT trainers


Download ppt "PRINCE2: 2009 Project Progress Update Andy Murray – Outperform"

Similar presentations


Ads by Google