Presentation is loading. Please wait.

Presentation is loading. Please wait.

March 14, 2002GJG NCSX CRYOGENICS DESIGN DEVELOPMENT STATUS WBS-63.

Similar presentations


Presentation on theme: "March 14, 2002GJG NCSX CRYOGENICS DESIGN DEVELOPMENT STATUS WBS-63."— Presentation transcript:

1 March 14, 2002GJG NCSX CRYOGENICS DESIGN DEVELOPMENT STATUS WBS-63

2 March 14, 2002GJG PURPOSE OF STATUS REVIEW Review serves as a design intent checkpoint These concepts will serve as the basis for the upcoming cost and schedule exercise Known requirements for technical design will be presented Approximate schedule for estimate will be discussed

3 March 14, 2002GJG NCSX SITE EQUIPMENT STATUS PBX-M (ORNL) beamline’s dewar hookup: 1.LN 2 & LHe Transfer Lines 2.Control Valves & Misc. Elements 1 1. 2.

4 March 14, 2002GJG NCSX SITE EQUIPMENT STATUS PPPL care taking staff has carefully removed and stored the transfer lines, valves, etc. Upcoming effort will remove and retain: 1.Twin bayonet heads 2.LN 2 -traced LHe rigid lines 1. 2.

5 March 14, 2002GJG NCSX SITE EQUIPMENT STATUS The 9,000 gallon LN 2 tank is in service and will soon support the Hall Thruster Project at less than 200 gallons per day The NCSX heat load (updated 3/13/02) is about 6,000 gallons (one trailer) per plasma day This tank is fine!

6 March 14, 2002GJG NCSX SITE EQUIPMENT STATUS Helium Dewar Shed: The PBX-M implementation of the ORNL beams featured a once-through, then vent to atmosphere LHe system. NCSX should use the same approach. A 1000 gallon portable dewar is forked from the vendor’s trailer and moved through the overhead door.

7 March 14, 2002GJG NCSX SITE EQUIPMENT STATUS The shed is past due for corrosion control and paint. The dewar scale (mandatory for ops) requires rehab or replacement Dewar Scale Assembly

8 March 14, 2002GJG NCSX SITE EQUIPMENT STATUS The LHe spear, hose, and phase separator are in serviceable condition. Some new seals and start-up labor will be required.

9 March 14, 2002GJG NCSX SITE EQUIPMENT STATUS This is an example of LN 2 -traced LHe cryo line and is very similar to the lines in the PBX-M area.

10 March 14, 2002GJG NCSX SITE EQUIPMENT STATUS Unfortunate conflict: The service entrance and main “tee”for the LN 2 -traced LHe rigid lines rests on the soon- to-be-dismantled north shield wall

11 March 14, 2002GJG SIMPLIFIED LIQUID CRYOGEN DISTRIBUTION N.C. Alarm Response Valve LN2 Dewar Skid Mount LHe Dewar Cryostat & Field Coil Beamline #1Beamline #2Beamline #3Beamline #4 Vent to High Bay Vent to Stack

12 March 14, 2002GJG SIMPLIFIED LN 2 FIELD COIL COOLING SUPPLY Hermetic Suction/Expansion Tank Field Coil Flow Paths 45 @ 15 lpm P P FIELD COIL HEAT EXCHANGER CLOSED, PRESSURIZED PRIMARY OPEN, BOILING SECONDARY PX TX.36 MPa (52 psia) For 90 K Ops P LN2 MAKEUP

13 March 14, 2002GJG SIMPLIFIED GN 2 CRYOSTAT COOLING SUPPLY NCSX PXTXPX FIELD COIL HEAT EXCHANGER CLOSED, PRESSURIZED PRIMARY OPEN, BOILING SECONDARY PITOT/STATIC ASS’YSUPPLY TEMPDIFF PRESS TO ATM OUTSIDE BUILDING RESISTIVE HEATER PX PITOT/STATIC ASS’Y M M LN2 SUPPLY OUTDOOR VENT (SAFETY) STACK RESISTIVE HEATER

14 March 14, 2002GJG WBS-63 REQUIREMENTS Vent effluent gases without personnel injury Survive worst probable indoor liquid spill without personnel injury Deliver about 6000 LN 2 gal/day to cryostat, field coil cooling, and beam pumps Deliver about 200 liters/day LHe to beam pumps for PBX-M-style beam ops

15 March 14, 2002GJG WBS-63 REQUIREMENTS, CONTINUED Remove 6E7 kJ/pulse from field coils at ABOUT a flow rate of 15 l/s and pressure drop of 1.4 MPa to support a 15 minute machine cycle. Circulate warming and cooling GN 2 around machine at *** kg/sec (pressure drop?) to support a thermal cycle of time of *** hours (days?)

16 March 14, 2002GJG INTERFACE CONTROL - WHO HAS THE WBS BALL? WHO PAYS? Oxygen Level Monitors – Multiple Locations N 2 /Air Exchange Emergency Blower –Changes Air in TC VERY Quickly –Needs Review, Maybe Not Necessary (NC valve?) Magnet Coolant Flow Monitoring Magnet Flow Balancing Valves/Plumbing Cryostat High/Low Pressure Monitor and Control Algorithms High Current 480 VAC circuits


Download ppt "March 14, 2002GJG NCSX CRYOGENICS DESIGN DEVELOPMENT STATUS WBS-63."

Similar presentations


Ads by Google