Presentation is loading. Please wait.

Presentation is loading. Please wait.

June 2004 Andrea Gaddi, PH-CMI USC Installation Commissioning Task Force 1st Run Meeting, June 3rd, 2004.

Similar presentations


Presentation on theme: "June 2004 Andrea Gaddi, PH-CMI USC Installation Commissioning Task Force 1st Run Meeting, June 3rd, 2004."— Presentation transcript:

1 June 2004 Andrea Gaddi, PH-CMI USC Installation Commissioning Task Force 1st Run Meeting, June 3rd, 2004

2 June 2004 Andrea Gaddi, PH-CMI USC Layout /1 Shaft Gas room Laser room Counting rooms (2 floors) Service area (2 floors) TS/CV zone

3 June 2004 Andrea Gaddi, PH-CMI USC Layout /2

4 June 2004 Andrea Gaddi, PH-CMI USC Layout /3

5 June 2004 Andrea Gaddi, PH-CMI Planning overview SCX - Jan 05 to July 05 SDX - June 04 to Dec 05 USC - June 04 to Feb 06 UXC - Nov 04 to April 07

6 June 2004 Andrea Gaddi, PH-CMI USC planning USC planning Planning of activities related to USC and PM shaft (from today to Magnet test)

7 June 2004 Andrea Gaddi, PH-CMI First activities in PM shaft and US cavern: Concrete blocks into elevator basement Closing of shaft basement Temporary ventilation Temporary electricity Protection plug on top of shaft 4 weeks - from June 04

8 June 2004 Andrea Gaddi, PH-CMI First components to be lowered trough PM shaft to US cavern: (lowering done during night time) Auxiliary mobile crane 10-t gantry crane for USC service area LHe transfer lines USC metallic structures (*) 10 weeks - from July 04

9 June 2004 Andrea Gaddi, PH-CMI PM shaft Material lowering (night time) Ventilation units and ducts TS/EL transformers Coil bus-bars Vacuum transfer line rails Activities (daytime) Permanent ventilation ducts Lift modules and machinery (*) Metallic staircase modules (*) 10 weeks “window” - from Sept 04

10 June 2004 Andrea Gaddi, PH-CMI US cavern USC Shaft area Elevator installation (*) Coil discharge lines Cooling and fire fighting pipes Gas piping 55 weeks (14 weeks idle) - from Oct 04

11 June 2004 Andrea Gaddi, PH-CMI US cavern USC Service Area 10-t crane assembly Metallic structures (*) Coil bus-bars into US - UX tunnel/1 Vacuum transfer line rails into US - UX tunnel/2 LHe transfer line into US - UX tunnel/2 Electric safe room Ventilation ducts and units (*) Cooling and gas piping (*) Cable trays (*) TS/EL switchboards 55 weeks - from July 04

12 June 2004 Andrea Gaddi, PH-CMI US cavern USC Control area Metallic structures (*) Ventilation ducts (*) Cable trays (*) Cooling pipes (*) Ready for racks (March 05) Rack installation Power distribution to racks Ready for crates (June 05) Crates installation 55 weeks - from July 04

13 June 2004 Andrea Gaddi, PH-CMI Conclusions Components to be installed in USC Service area and related activities are well defined. For the time being, nothing has showed to be critical, unless a minor problem involving the LHe transfer line that needs some works in UXC to be completed before being put in place. Racks and related services to be installed in USC counting rooms are clearly on the critical path. Many sub-system have to be integrated (cooling pipes, ventilation ducts, power lines, cable trays) into a relatively confined space. It is really important to have the final layout of racks and cable routing validated asap. Some services from surface wouldn’t be available before Sept 05


Download ppt "June 2004 Andrea Gaddi, PH-CMI USC Installation Commissioning Task Force 1st Run Meeting, June 3rd, 2004."

Similar presentations


Ads by Google