Presentation is loading. Please wait.

Presentation is loading. Please wait.

Software Engineering: A Practitioner’s Approach

Similar presentations


Presentation on theme: "Software Engineering: A Practitioner’s Approach"— Presentation transcript:

1 Software Engineering: A Practitioner’s Approach
Chapter 23 Estimation Software Engineering: A Practitioner’s Approach 6th Edition Roger S. Pressman

2 Software Project Estimation (1)
S/W is the most expensive element of virtually all computer based systems S/W cost and effort estimation will never be an exact science Too many variables Human Technical Environmental Political

3 Software Project Estimation (2)
Options for estimation Delay estimation until late in the project Attractive, but not practical Base estimates on similar projects that have already been completed Unfortunately, past experience has not always been a good indicator of future results Use relatively simple decomposition techniques to generate project cost and effort estimates “Divide and conquer” approach Use one or more empirical models for software cost and effort estimation Can be used as a cross-check for the previous option and vice versa

4 Decomposition Techniques
Two different points of view for the decomposition approach Decomposition of the problem Decomposition of the process But first, the project planner must Understand the scope of the s/w to be built Generate an estimate of its “size”

5 Software Sizing Sizing represents the project planner’s first major challenge Size refers to a quantifiable outcome of the s/w project (e.g. LOC and/or FP) Four different approaches to the sizing problem [PUT92] “Fuzzy Logic” sizing Function point sizing Standard component sizing Change sizing

6 An Example of LOC-Based Estimation (1)
Function Estimated LOC User interface and control facilities (UICF) Two-dimensional geometric analysis (2DGA) Three-dimensional geometric analysis (3DGA) Database management (DBM) Computer graphics display facilities (CGDF) Peripheral control function (PCF) Design analysis modules (DAM) 2,300 5,300 6,800 3,350 4,950 2,100 8,400 Estimated lines of code 33,200

7 An Example of LOC-Based Estimation (2)
Estimated lines of code = W = 33,200 Let, Average productivity = 620 LOC/pm = X Labor rate = $8,000 per month = Y So, Cost per line of code = Z = Y/X = $13 (approx.) Total estimated project cost = W*Z = $431,000 (approx.) Estimated effort = W/X = 54 person-months (approx)

8 An Example of FP-Based Estimation (1)
Information Domain Value Count Weighting factor Simple Average Complex External Inputs (EIS) 3 X 4 6 = 9 External Outputs (EOs) 2 5 7 8 External Inquiries (EQs) Internal Logical Files (ILFs) 1 10 15 External Interface Files (EIFs) 20 Count Total 50 Figure 15.4: Computing function points

9 An Example of FP-Based Estimation (2)

10 An Example of FP-Based Estimation (3)
Value Adjustment Factors 1.17

11 An Example of FP-Based Estimation (4)
Now, FPestimated = count-total  [   (Fi)] Fi (i = 1 to 14 are value adjustment factors) So, FPestimated = W = 320  [  52] = 375 (approx.) Let, Average Productivity = X = 6.5 FP/pm Labor rate = Y = $8,000 per month Cost per FP = Z = Y/X = $1,230 (approx.) Total estimated project cost = W*Z = $461,000 (approx.) Estimated effort = W/X = 58 person-months (approx)

12 Empirical Estimation Models
Uses empirically derived formulas to predict effort as a function of LOC or FP The empirical data are derived from a limited sample of projects So, no estimation model is appropriate for all classes of s/w and in all development environments The results obtained from such models must be used judiciously An estimation model should be calibrated to reflect local conditions

13 The Structure of Estimation Models (1)
Derived using regression analysis on data collected from past s/w projects Overall structure, E = A + B  (ev)c Here, A, B, and C are empirically derived constants E is effort in person-months ev is the estimation variable (either LOC or FP) Some form of project adjustment component is also used

14 The Structure of Estimation Models (2)
Example of a LOC-oriented estimation model (Bailey-Basili model) E =  (KLOC)1.16 Example of a FP-oriented estimation model (Kemerer model) E = FP Estimation models must be calibrated for local needs.

15 The COCOMO II Model (1) COnstructive COst Model
A hierarchy of estimation models Addresses the following areas Application composition model Early design stage model Post-architecture stage model Three different sizing options are available Object points Function points Lines of source code

16 The COCOMO II Model (2) The COCOMO II application composition model uses object points Object point is computed using counts of the number of Screens (at the user interface) Reports Components likely to be required to build the application

17 Figure 23.6: Complexity weighting for object types
The COCOMO II Model (3) Object type Complexity weight Simple Medium Difficult Screen 1 2 3 Report 5 8 3GL component 10 Figure 23.6: Complexity weighting for object types

18 Figure 23.7: Productivity rate for object points
The COCOMO II Model (4) Developer’s experience/capability Very low Low Nominal High Very High Environment maturity/capability PROD 4 7 13 25 50 Figure 23.7: Productivity rate for object points

19 The COCOMO II Model (5) NOP = (object points)  [(100-%reuse)/100]
NOP = New Object Points Object Points = Weighted Total %reuse = Percent of reuse Estimated effort = NOP/PROD PROD = Productivity Rate PROD = NOP/person-month

20 The Software Equation [PUT92] (1)
It is a multivariate model Has been derived from productivity data collected for over 4000 contemporary s/w projects E = [LOC  B0.333/P]3  (1/t4) Here, E = effort in person-months or person-years t = project duration in months or years B = “special skills factor” P = “productivity parameter”

21 The Software Equation [PUT92] (2)
For small programs (KLOC = 5 to 15) B = 0.16 For programs greater than 70 KLOC B = 0.39 P = 2000 for development of real-time embedded s/w P = 10,000 for telecommunication and systems s/w P = 28,000 for business systems applications

22 The Software Equation [PUT92] (3)
Simplified formulas tmin = 8.14 (LOC/P)0.43 in months for tmin > 6 months tmin = minimum development time E = 180 Bt3 in person-months for E  20 person-months Here t is represented in years

23 The Make/Buy Decision S/W acquisition options
s/w may be purchased (or licensed) off the shelf “full-experience” or “partial-experience” s/w components may be acquired and then modified and integrated to meet specific needs s/w may be custom built by an outside contractor to meet the purchaser’s specifications

24 Creating a Decision Tree

25 Computing Expected Cost
(path probability) x (estimated path cost) i i For example, the expected cost to build is: expected cost = 0.30 ($380K) ($450K) build = $429 K similarly, expected cost = $382K reuse expected cost = $267K buy expected cost = $410K contr

26 Outsourcing S/W engineering activities are contracted to a third party who does the work at lower cost and, hopefully, higher quality S/W work conducted within a company is reduced to a contract management activity The decision to outsource can be either strategic or tactical Has both merits and demerits

27 Chapter 23 23.5, 23.6, , , 23.7 23.10 Exercises- 23.4, 23.5, 23.7


Download ppt "Software Engineering: A Practitioner’s Approach"

Similar presentations


Ads by Google