Download presentation
Presentation is loading. Please wait.
Published byAdrian Wilkinson Modified over 9 years ago
1
Clinton Street Bridge over the Maumee River ODOT Project DEF-15-14.77 May 14, 2015 Public Meeting
2
Review the project and why it’s happening Share the results of the Feasibility Study Identify concerns Obtain input Purpose of Public Meeting
3
Address deteriorated condition of existing bridge Improve bicycle accommodations per City of Defiance Strategic Plan Improve pedestrian access to the bridge per Americans with Disabilities Act (ADA) guidelines Project Purpose
4
ODOT engaged services of Burgess & Niple (B&N) in June 2014 B&N performed bridge inspection, traffic studies, and survey work in the summer and fall of 2014 B&N developed alternatives and prepared feasibility study ODOT has held two stakeholder meetings for input Progress to Date – How we got here
5
Deteriorated condition of existing bridge
7
Improve Pedestrian and Bicycle Accommodations
8
Improve Pedestrian Access (ADA) to the bridge
9
Possible traffic congestion issues Accident history Southbound left turn from Clinton Street to River Road (City of Defiance request) Rear-end accidents at south end of bridge Investigate…
10
Southbound Left Turn at River Drive
11
Includes the bridge and the next two intersections north and south of bridge Engineering and environmental studies are performed within the study area Larger than the actual project work limits Why? Actual project work limits have not yet been determined. Study Area
12
Study Area (Yellow Outline)
13
Underground storage tanks (current and former) Pontiac and Fort Defiance Parks Maumee River and mussels Several buildings over 50 years old (none eligible for the National Register of Historic Places) One archaeological site (southwest corner; destroyed according to State Historic Preservation Office) Concerns? Environmental Concerns on the Project
14
Alternatives are first studied Feasible Alternatives are then determined A Preferred Alternative is then identified Draft Feasibility Study was submitted to ODOT in December 2014 Revised Draft version available at this meeting and on District 1 website Alternatives Evaluation
15
New four-lane bridge on existing piers (similar to existing bridge) New five-lane bridge on existing piers Allows southbound left turn from Clinton Street to River Drive. New four (or five) - lane bridge on new piers DEF-15-14.77 Study Alternatives
16
Reusing the existing piers as part of the new bridge was studied. Existing steel in concrete is deteriorating. Piers can be reused, but… Repair might last 20 years (or less) Future repair likely Conclusion: Reusing existing piers is not prudent. Re-Use of Existing Piers
17
Goal: 75 year design life for new bridge construction Wider sidewalks than those on the existing bridge Dedicated bike lanes (5 feet wide) adjacent to each sidewalk ADA compliant curb ramps off bridge Feasible Alternative 1 Entirely New Four-Lane Bridge
18
Feasible Alternative 1 - Entirely New Four-Lane Bridge
20
Feasible Alternative 1 Note the dedicated bike lanes and wider sidewalks.
21
Same 75 year design life goal Same sidewalk and bike lanes improvement as Feasible Alternative 1 Difference: Wider bridge to accommodate new lane north of bridge to allow southbound left turn at River Drive Feasible Alternative 2 Entirely New Five-Lane Bridge
22
Feasible Alternative 2 - Entirely New Five-Lane Bridge
24
Feasible Alternative 2 Note the striped lane, bike lanes and the wider sidewalks.
25
Next Step – Selecting a Recommended Preferred Alternative
26
Alternative 1 (New Four-Lane Bridge) Recommended Preferred Alternative –
27
Construction cost Traffic safety Environmental impacts Adjacent property impacts (public and private) Utility impacts (public and private) Maintenance of traffic during construction How well does it address project purpose? Factors Affecting Recommendation
28
Construction cost - Less construction and R/W cost ($8.7M) with Alternative 1 than with Alternative 2 ($9.9M) Traffic - No improvements to traffic delay at intersections (Level of Service) with Alternative 2 Factors Affecting Recommendation
29
Environmental impacts - Alternative 1 has either the same or fewer environmental impacts as Alternative 2 Adjacent property impacts (public and private) - Less commercial property impacts with Alternative 1 than with Alternative 2 (primary impacts is to Circle K underground storage tanks) Factors Affecting Recommendation
30
Alternative 2 - New Five-Lane Bridge (Impacts to Circle K)
31
Utility impacts (public and private) - Both have approximately the same impacts to existing utilities in the project area. Maintenance of traffic during construction Both alternatives maintain at least local traffic during construction. Anticipate maintaining one sidewalk for pedestrians Two construction seasons likely for either alternative (whether local traffic is maintained or detoured) Factors Affecting Recommendation
32
Final appearance not yet determined Construction costs are currently based on standard ODOT bridge type City preference is current bridge lighting Stakeholder and public comments will be sought Bridge Aesthetics (How the new bridge will look)
33
US 24 Bridge over the Maumee River (West of Defiance)
34
Construction in 2019 (preliminary estimate) Depends on funding, environmental concerns, right- of-way acquisition, and completion of construction plans Project schedule updates will be provided as changes in the schedule are known. Current Project Schedule
35
Funding will be secured when preferred alternative is finalized. Funding for the preferred alternative will be through state and federal sources Right-of-way acquisition anticipated to begin in late 2016 or early 2017. Project Funding
36
Preferred alternative selected by July 1, 2015 Preferred alternative announced through letters and media Next Steps
37
Comments, concerns, or any information you can provide are appreciated! Comments after the meeting should go to: Jenn Gasser, ODOT District 1, (419) 999-6871, jennifer.gasser@dot.state.oh.us or jennifer.gasser@dot.state.oh.us Jeff Griffin, Burgess & Niple, (614) 459-2050, jeff.griffin@burgessniple.com jeff.griffin@burgessniple.com Future project information – go to District 1 website, Construction Projects & click on DEF SR 15 Clinton Street Bridge www.transportation.ohio.gov/dist1www.transportation.ohio.gov/dist1 Public Meeting Concerns/Input
Similar presentations
© 2024 SlidePlayer.com Inc.
All rights reserved.