Contemporary Engineering Economics, 4 th edition, © 2007 Discounted Cash Flow Analysis Lecture No.16 Chapter 5 Contemporary Engineering Economics Copyright.

Similar presentations


Presentation on theme: "Contemporary Engineering Economics, 4 th edition, © 2007 Discounted Cash Flow Analysis Lecture No.16 Chapter 5 Contemporary Engineering Economics Copyright."— Presentation transcript:

1 Contemporary Engineering Economics, 4 th edition, © 2007 Discounted Cash Flow Analysis Lecture No.16 Chapter 5 Contemporary Engineering Economics Copyright © 2006

2 Contemporary Engineering Economics, 4 th edition, © 2007 Net Present Worth Measure  Principle: Compute the equivalent net surplus at n = 0 for a given interest rate of i.  Decision Rule for Single Project Evaluation: Accept the project if the net surplus is positive.  Decision Rule for Comparing Multiple Alternatives: Select the alternative with the largest net present worth. 2 3 4 5 0 1 Inflow Outflow 0 PW(i) inflow PW(i) outflow Net surplus PW(i) > 0

3 Contemporary Engineering Economics, 4 th edition, © 2007 Example 5.5 - Tiger Machine Tool Company $75,000 $24,400 $27,340 $55,760 0 12 3 outflow inflow

4 Contemporary Engineering Economics, 4 th edition, © 2007 ABC 1PeriodCash Flow 20($75,000) 31$24,400 42$27,340 53$55,760 6 7PW(15%)$3,553.46 =NPV(15%,B3:B5)+B2 Excel Solution:

5 Contemporary Engineering Economics, 4 th edition, © 2007 i (%)PW(i)i(%)PW(i) 0$32,50020-$3,412 227,74322-5,924 423,30924-8,296 619,16926-10,539 815,29628-12,662 1011,67030-14,673 128,27032-16,580 145,07734-18,360 162,07636-20,110 17.45*038-21,745 18-75140-23,302 *Break even interest rate Present Worth Amounts at Varying Interest Rates

6 Contemporary Engineering Economics, 4 th edition, © 2007 Present Worth Profile

7 Contemporary Engineering Economics, 4 th edition, © 2007 How To Use Cash Flow Analyzer Cash Flow Input Fields Output or Analysis results Graphical Plots

8 Contemporary Engineering Economics, 4 th edition, © 2007 Solving Example 5.3 with Cash Flow Analyzer Net Present Worth Net Future Worth Payback period Project Cash Flows

9 Contemporary Engineering Economics, 4 th edition, © 2007 Obtaining a Graphical Plot of NPW Specify the Range of Interest Rate to plot NPW plot Between 0% and 100%

10 Contemporary Engineering Economics, 4 th edition, © 2007 Can you explain what $3,553 really means? 1. Project Balance Concept 2. Investment Pool Concept

11 Contemporary Engineering Economics, 4 th edition, © 2007 Project Balance Concept Suppose that the firm has no internal funds to finance the project, so will borrow the entire investment from a bank at an interest rate of 15%. Then, any proceeds from the project will be used to pay off the bank loan. Then, our interest is to see if how much money would be left over at the end of the project period.

12 Contemporary Engineering Economics, 4 th edition, © 2007 Project Balance Concept N0123N0123N0123N0123 Beginning Balance Interest Payment Project Balance -$75,000 -$11,250 +$24,400 -$61,850 -$9,278 +$27,340 -$43,788 -$6,568 +$55,760 +$5,404 Net surplus PW(15%) = $5,404 (P/F, 15%, 3) = $3,553

13 Contemporary Engineering Economics, 4 th edition, © 2007 Project Balance Diagram 60,000 40,000 20,000 0 -20,000 -40,000 -60,000 -80,000 -100,000 -120,000 01230123 -$75,000 -$61,850 -$43,788 $5,404 Year(n) Terminal project balance (net future worth, or project surplus) Discounted payback period Project balance ($)

14 Contemporary Engineering Economics, 4 th edition, © 2007 Investment Pool Concept Suppose the company has $75,000. It has two options. (1)Take the money out and invest it in the project or (2) leave the money in the pool and continue to earn a 15% interest. If you take Option 1, any proceeds from the project will be returned to the investment pool and earn 15% interest yearly until the end of the project period. Let’s see what the consequences are for each option.

15 Contemporary Engineering Economics, 4 th edition, © 2007 $75,000 0 1 2 3 $24,400 $27,340 $55,760 Investment pool How much would you have if the Investment is made? $24,400(F/P,15%,2) = $32,269 $27,340(F/P,15%,1) = $31,441 $55,760(F/P,15%,0) = $55,760 $119,470 How much would you have if the investment was not made? $75,000(F/P,15%,3) = $114,066 What is the net gain from the investment? $119,470 - $114,066 = $5,404 Project Return to investment pool N = 3 Meaning of Net Present Worth PW(15%) = $5,404(P/F,15%,3) = $3,553

16 Contemporary Engineering Economics, 4 th edition, © 2007 What Factors Should the Company Consider in Selecting a MARR in Project Evaluation? Cost of capital  The required return necessary to make an investment project worthwhile.  Viewed as the rate of return that a firm would receive if it invested its money someplace else with a similar risk Risk premium  The additional risk associated with the project if you are dealing with a project with higher risk MARR Cost of capital Risk premium


Download ppt "Contemporary Engineering Economics, 4 th edition, © 2007 Discounted Cash Flow Analysis Lecture No.16 Chapter 5 Contemporary Engineering Economics Copyright."