Presentation is loading. Please wait.

Presentation is loading. Please wait.

QUALITY CONTROL QUALITY ASSURANCE INDEPENDENT ASSURANCE

Similar presentations


Presentation on theme: "QUALITY CONTROL QUALITY ASSURANCE INDEPENDENT ASSURANCE"— Presentation transcript:

1 QUALITY CONTROL QUALITY ASSURANCE INDEPENDENT ASSURANCE
CLARK COUNTY DEPARTMENT PUBLIC WORKS Construction Management QUALITY PROGRAM QUALITY CONTROL QUALITY ASSURANCE INDEPENDENT ASSURANCE

2 QUALITY --Quality Control is the responsibility of the primary installer or fabricator of the material; they are the experts in what they build. --Quality Assurance is the oversight by the agency of the Quality Control; they want to receive what is specified. Uses verified QC testing and inspection as acceptance (like when observing the production of a car you want to buy ) --Independent Assurance is the responsibility of the agency to ensure QA and QC are verifiable Make sure QC and QA testing are compatible and consistent

3 Contractor Quality Control
Sections 111 thru 117 and website 111 Administration- General Gives overview of program Check to see Responsible Person in Charge and Quality Control Coordinator; both required or only one See exceptions (inspector separate from foreman) Contractor responsible for the Quality of the work. Owner oversight and verification of Contractor is acceptance. 112 QC Administration Organization structure based on 113 Documentation Contractor responsible

4 Contractor Quality Control
112 QC Administration (continued) Documentation Be legible, identifiable, and retrievable. Protected in a manner to prevent damage, deterioration, or loss. Readily available for review within 4 hours. Retain documents until transmitted to the Engineer at substantial completion Filing Section has list of requirements Submittal procedure Logging and Submission Process

5 Contractor Quality Control
112 QC Administration (continued) Submittal procedure Reviewing Returned Submittals No exceptions taken With Corrections Noted Amend and Resubmit Rejected Deficiency tracking Deficient Work work that is not in accordance with Contract Documents it can be readily corrected

6 112 QC Administration (continued)
Deficiency tracking Deficient Work Non-Conforming Work (non-compliance) A Deficiency which cannot be readily corrected For example, concrete compressive strengths being below specification, or Field soils density test being below specification and no longer accessible. Informational Tests Determine the amount of effort necessary to provide work that complies with the Contract Documents Need to notify ahead of time if want to use for acceptance

7 112 QC Administration (continued)
Deficiency tracking Deficient Work When found and resolved same day, do not list Deficiency Reporting At minimum Weekly Review Before the Weekly Progress Meeting, review the Deficiency Tracking Log for outstanding Deficiencies. Generate a summary of outstanding deficiencies including status of each. Deliver the Summary at the Weekly Meeting

8 112 QC Administration (continued)
Deficiency tracking Deficiency Resolution Resolution by Contractor, not Engineer Engineer can disapprove the resolution Resolution must be reviewed by a contractor PE Conflict Resolution Process 24 hrs for position 5 Quality Control Inspector 48 hrs for position 3 Responsible Person-in-Charge 96 hrs for position 1 Contractor Principal Representative

9 112 QC Administration (continued)
CONFLICT RESOLUTION PROCESS 3rd party testing Agreed by contractor and engineer Costs for 3rd party CERTIFICATION, MATERIAL DELIVERY, TRACKING Logs see section 115,116 Complete the Materials Delivery documentation. REMEMBER ON LPA PROJECTS, BUY AMERICA CLAUSE Track materials until incorporation into the work. Ensure that all materials are noted on the Materials Tracking Log. Resolve certification problems.

10

11 112 QC Administration (continued)
ACTIVITY CARDS AND CONTROL MEASURES (Form CCPW QC-103) RPC to ensure in conformance with section 114 Section 1 Actual Work Performed

12 112 QC Administration (continued)
Section 2 Deficiency Check Section 3 Inspection Items

13 112 QC Administration (continued)
Section 4 – Testing & Sampling Table 1 on web Test turn-a-round important! $100 per day deduction for late tests Need appropriate documentation for various lifts, use stations, lift elevations. Use the materials & sample tracking log. Sequential test numbering for entire project Section 5- Remarks Section 6- Sign-Off

14

15 112 QC Administration (continued)
Testing & Sampling List potential testing for the project Log from inspection of Asphalt Concrete

16 112 QC Administration (continued)
Concrete Placement log

17 112 QC Administration (continued)
Sample Tracking Log Attach lab tests

18 112 QC Administration (continued)
DAILY REPORTING Activity card completed and attach: Field Tests Inspection reports (CCPW QC-100) Inspection forms (see ) MONTHLY REPORTING Summary of QC performed Include quantity and amount of testing Cover letter attest that the month has been reviewed Indicate short falls in testing, quality and other pertinent items State resolution actions in letter or being resolved Material resolution to be reviewed and stamped by an engineer

19

20

21 112 QC Administration (continued)
MONTHLY REPORTING Submitted using in part or whole: CD-Rom Word processing documents Spectraqest Or combination In format in the section FINAL REPORTING Same as previous, but shall not be submitted until all discrepancies and non-conformances have been resolved, including the close-out audit. Testing shortfalls will have fees assigned

22 112 QC Administration (continued)
QC AUDITING PROCEDURES Project over 90 calendar days, no audit needed Items: Advanced Notification Cards Logs - 24-hour notice being given Pre-Activity Meetings Logs Activity Cards Logs - accurate, correct, and complete on a daily basis Materials tracking log Sampling and Testing completed with tracking information and results Record dwg’s are being updated monthly QC documentation and overall program is being implemented effectively Documentation for resolution of Deficiencies/Non-Conformances Logs correct and complete Written document with checklist Follow-up audit for corrections within one week

23

24 112 QC Administration (continued)
QC PROGRAM REVISIONS Changes in procedures Forms Organization Need approval of engineer

25 113 CONTRACTOR ORGANIZATION
Basic chain of command Position 1 - Contractor Principal Representative Owner or representative Position 2 - Professional Engineer (PE) Position 3 - Responsible Person-in-Charge (RPC) Superintendent level Position 4 - Quality Control Coordinator (QCC) Position 5 - Quality Control Inspector (QCI) Positions 6 - Quality Control Field Technician (QCFT) Positions 7 - Quality Control Lab Technician (QCLT) All positions need resumes submitted

26 113 CONTRACTOR ORGANIZATION (cont)
Responsible Person-in-Charge (RPC) Responsible for the work Min 8 yrs in type of construction Stop work authority QC Laboratory Engineer Min 5 years experience construction experience Nevada PE Quality Control Coordinator (QCC) Ensures that the documents are coordinated to all levels of the project Min 2 yrs experience or resume

27 113 CONTRACTOR ORGANIZATION (cont)
Inspectors or foremen (if acting inspector per section 111) Min 3 years experience Must submit form (Tables 1 thru 7) One form per individual Inspections and persons MUST also be identified during pre-activity mtg

28 113 CONTRACTOR ORGANIZATION (cont)
Laboratories AASHTO AMRL/CCRL accredited Must be maintain throughout project Subject to non-payment ID all labs used

29 114 INSPECTION PROCEDURES
INSPECTION PROCESS Shall have experience PRE-ACTIVITY MEETINGS First start of any bid item work, or after long period of in-activity Meet with all involved Meet at location of work Setup by contractor but Engineer may ask for one RPC facilitates Provide documentation, follow list RPC, QC & QA Inspectors, foremen

30

31

32 114 INSPECTION PROCEDURES (cont)
ADVANCE NOTIFICATION CARDS Use form on website

33 114 INSPECTION PROCEDURES (cont)
QUALITY CONTROL ACTIVITY CARD PROCESS Section 1 – Actual Work Performed Section 2 – Deficiency Check If none, initial If exists, note in row and log number

34 114 INSPECTION PROCEDURES (cont)
Section 3 – Item/Material for Inspection For inspections of work in Section 1 QC initial & date Minimum one day advance notification for QA If QA cannot inspect, note it then continue the work Attach inspection forms to card

35 114 INSPECTION PROCEDURES (cont)
Section 4 – Testing and Sampling Requirements Used for documenting work in Section 1 RPC indicate actual tests Indicate amount of material that could be tested Amount of tests based on Table I frequency

36 114 INSPECTION PROCEDURES (cont)
SAMPLING AND TESTING Table I on website Density tests to be clearly marked with paint FINAL INSPECTION(S) AND TESTING Ensure all deficiencies are corrected and documented

37 114 INSPECTION PROCEDURES (cont)
HOLD POINT PROCESSES Defined on website Used for work stop for inspection Contractor can add hold points Shall not proceed with work

38

39 MATERIAL SOURCES Delivery onsite inspected by Contractor and Engineer
Source inspection performed as required by contract

40 114 INSPECTION PROCEDURES (cont)
ELEVATION REFERENCES Elevations minus from one of grades Example: Finish Grade Aggregate Base minus 0.5 feet or FGAB-0.5'

41 114 INSPECTION PROCEDURES (cont)
FIELD PROBLEM IDENTIFICATION AND REPORTING PROCESS Read the procedure for each Non-quality personnel Testing tech QC inspector

42 114 INSPECTION PROCEDURES (cont)
TRACKING RESPONSIBILITY RPC shall track discrepancy on the activity card Compare to log Ensure all resolved

43 114 INSPECTION PROCEDURES (cont)
INSPECTION REPORTS Use form CCPW QC-100 or similar approved by the Engineer Full-time documented inspection Oversight writing shall include Observation of Quality Control and Quality Assurance tests Review or spot check of procedures

44 114 INSPECTION PROCEDURES (cont)
Evaluation of project controls Coordination Review all field and lab test data Written inspection report to include: Date including the year. Weather conditions; cloudy, rain, etc. Temperature – high and low (the web site wunderground.com is a good resource).

45 114 INSPECTION PROCEDURES (cont)
Wind velocity and direction (approximate). Total calendar days. Contractors and Subcontractor’s working hours. Specify work activities performed on that day/week The work in progress. Pay Quantities for the day’s activities. Note any unusual situations encountered, such as accidents, damages to vehicles or to the project, unusual material (bentonite, etc.), or anything that you would bring to the attention of others.

46 114 INSPECTION PROCEDURES (cont)
Important calls, Conversations, Verbal discussions with Engineer relative to the work, including any. instructions or suggestions from the Engineer. Communication with the property owners. Official visitors and their recommendations; official visitors may include FHWA, Central. Office Personnel, Region Personnel. Major equipment. Sizable work forces being moved onto or away from the job. General locations where equipment is working, not working, and/or idle for repairs. Material rejected and reason.

47 114 INSPECTION PROCEDURES (cont)
Substandard materials and justification. Any phase shut down, justification and by whom. Time spent with Engineer on disputable items of work. Describe any delays and duration. Progress of surveying and staking. Deviations and corrective action taken. Traffic Control. Changes to Plans. Project personnel. Contractor Inspector signature and title

48 INDEPENDENT ASSURANCE

49 Independent Assurance Testing
Verifies visually Care Custody and Control Verifies QC and QA testing procedures 3-way split, IA retain one, only QA/QC testing If test by IA are required Use 3rd sample

50 General Responsibilities IA Testers
IA unit is responsible for auditing field testers by : Performing visual audits, Direct the splitting material samples Maintaining testing consistency Verifying that all testing personnel possess the necessary qualifications Performing inspections on QA and QC labs

51 General Responsibilities of IA
FHWA Area Engineers may collaborate in sampling and testing QA and/or QC testers sampling in the presence of and at the locations by IA tester QA and QC Equipment Evaluation Lab inspections

52 QA and QC Equipment Evaluation
IA shall evaluate the QC and QA laboratory and field equipment Calibrated per the AASHTO AMRL-CCRL calibration frequency Be performed during the laboratory audit, beginning of project, Recorded on the audit form (Appendix A)

53 QA and QC Personnel Evaluation
IA is responsible for the split sample program Split Samples 3-way splits, but 3rd for retain only IA retain custody until given to QA or QC Split samples and tests on the following materials: Select Borrow , Selected Material , Granular and Drain Backfill ,

54 QA and QC Personnel Evaluation
Base Aggregates, Concrete Aggregates, Aggregates for Plantmix Bituminous Surface, and UTACS Concrete Plantmix Bituminous Surface UTACS

55 Reporting Procedures QA QC data given to IA for tabulation onto one form CCPW form IA-001- Compaction Curve CCPW form IA way or 3 way split samples- Use for QA and QC sample comparisons

56

57

58 Reporting Procedures CCPW form IA-004- Audit Report Form for Concrete Aggregates CCPW form IA 005, Audit Report Form of Concrete Tests CCPW form IA-006- Visual Audit Form for QC and QA Laboratories CCPW form IA-008- Lab Inspection Report

59

60

61

62

63


Download ppt "QUALITY CONTROL QUALITY ASSURANCE INDEPENDENT ASSURANCE"

Similar presentations


Ads by Google