King James Construction Cost Estimating Rob Himler, Ken Coutain, David Reger, Ruoyu Huang, Bei Xiong, Hanbing Ye.

Similar presentations


Presentation on theme: "King James Construction Cost Estimating Rob Himler, Ken Coutain, David Reger, Ruoyu Huang, Bei Xiong, Hanbing Ye."— Presentation transcript:

1 King James Construction Cost Estimating Rob Himler, Ken Coutain, David Reger, Ruoyu Huang, Bei Xiong, Hanbing Ye

2 Letter of Transmittal Bid proposal for King James project – 3-bedroom/2-bath/-1-car garage Estimations broken down into several categories Proposed bid includes all materials, labor, equipment, taxes and any other additional needed costs

3 Division of Duties

4 Breakdown of Bid by Components

5 Concrete Assumptions: Use Earth as Forms Use Chute to Pour Concrete

6 Woods & Plastics The Floor The floor system consists of joists covered with OSB or plywood sheathing and bears on sills, walls, or girders supported by posts.

7 Walls Walls consists of top and bottom plates, studs, headers, blockings, and sheathing. Double top plate of untreated lumber, and one bottom plate of treated lumber. Woods & Plastics

8 The roof Sales tax—6% Labor tax---25% OH & Profit---12% Woods & Plastics

9

10 Thermal + Moisture Waterproofing Insulation Batt Insulation in Wall R-30 Insulation above Ceiling Exterior Insulation Finish System Building Paper and Vapor Barriers Shingles Fiberglass roof shingle Metal Drip edge

11 Thermal + Moisture 1.Waterproofing Film Vapor Barrier Underlayment Area = 1460SF 2. R-30 Insulation above Ceiling Area = 1460SF

12 Thermal + Moisture 3.3-1/2" Batt Insulation in Wall Exterior Wall 1052SF Interior Wall 313.31SF Area Wall = 1365.31 SF

13 Thermal + Moisture 4. Exterior Insulation Finish System Area Wall = 1052SF

14 Thermal + Moisture 5. Building Paper and Vapor Barriers (must be lapped to be effective) To be lapped 12 inches on the ends 6 inches on the side Area Builders paper = 3363.89SF The Dormer

15 6. Fiberglass Roof Shingles 5in exposure and 1in width Starter/Field/Hip&Valley/Cap Shingle Area shignles = 2053.27SF 7. Metal Drip Strip come in 11-foot length need to be lapped 2 inches Length = 164.55LF Number = 16 each Thermal + Moisture Hip Shingle

16 Thermal + Moisture

17 Plumbing Plumbing (DWV)  Material cost priced through Home-Depot  Labor cost priced through RS- Means (Section 22)  Estimates broken up in the following sections:  Main Sewer Connection  Central Bathroom  Left Bathroom  Garage and Kitchen  All PVC Schedule 40 for Sanitary

18 Plumbing Plumbing (Water Line)  Material cost priced through Home-Depot  Labor cost priced through RS- Means (Section 22)  Estimates broken up in the following sections:  Garage (WM)  Kitchen (SINK)  Living Room  Central Bathroom (LAV, SHW, WC)  Left Bathroom (LAV, WC, TUB)  Hot Water (HW) lines in house are all ½” CPVC  Cold Water (CW) lines in house are ¾” in-wall and reduce to ½” for fixture connections.

19 HVAC

20

21

22 Electrical Outlet: 12 GFI 2 Waterproof GFI Cover 1 J-Box 23 AFCI 35 GFI/AFCI Cover 3 220V Outlet 20 outlet 22 Outlet Box 2 Breaker for AC 3 Breaker for others 1 Electrical Panel

23 Electrical

24 4 Fans 2 Exhaust Fan 8 Lighting Fixtures 13 Single Pole Switches 2 Three Pole Switches 4 Smoke Detector 1 Co/smoke Detector

25 8’ 6’ 4’ 2’ 3’ 7’ 6’ 8’ 6’ 3’ 4’ 6’ 10’ 6’ 40ft Electrical

26 Facilities: 200ft #12 Electrical Wires 1 Washer 1 Dryer Electrical

27

28 Openings

29 Finishes Assumptions: Paint Rolled On Carpet in Bedrooms Vinyl in Bathrooms and Kitchen Laminate in Halls and Living/Dining Room

30 Bid Summary Direct Costs

31 Bid Summary Indirect Costs

32 Bid Summary Total Cost Breakdown by Component

33 Questions?