Presentation is loading. Please wait.

Presentation is loading. Please wait.

Streamlining the EIA Process for Hydro Development 23 October 2012 Presented by Jennifer Ballantyne.

Similar presentations


Presentation on theme: "Streamlining the EIA Process for Hydro Development 23 October 2012 Presented by Jennifer Ballantyne."— Presentation transcript:

1 Streamlining the EIA Process for Hydro Development 23 October 2012 Presented by Jennifer Ballantyne

2 Environmental Impact Assessment – the law Town and Country Planning (EIA) (Scotland) Regulations 2011 “EIA Development” is either –Schedule 1 development (n/a to hydro) or –Schedule 2 development IF likely to have significant environmental effects due to its size, nature or location Schedule 2 development is a hydro development either –(a) with a capacity greater than 500kW or –(b) (irrespective of size) any part of which is located within a sensitive area "sensitive area" any SSSI, European site, National Park, NSA, scheduled monument or World Heritage Site N.B. Don’t forget the IF

3 Some Statistics Since 1 June 2011: –Highland Council : 33 applications (three +1MW) –Argyll & Bute Council: 10 applications (one +1MW) FREDS Hydro Resource Study 2008: –< 100kW – 6 schemes –100-500kW – 537 schemes –500kW-1MW – 300 schemes –1-5MW – 170 schemes –5-10MW – 6 schemes Must get the right approach to EIA for schemes <1MW

4 Some Trends Increasing number of applications Increasing costs Increasing length and complexity of Environmental Statements –Positive Improved understanding and science More robust assessments –Negative Risk averse approach One size fits all Commercial drivers

5 Some Guidance Scottish Government guidance (Planning Circular 3/2011) –“emphasis should be on the 'main' or 'significant' environmental effects to which the development is likely to give rise –other impacts may be of little or no significance for the particular development in question and will need only very brief treatment” IEMA Special Report on the State of Environmental Impact Assessment Practice in the UK (June 2011) –increased efficiencies in EIA coordination –improved engagement with communities –exchanging knowledge with stakeholders to tackle difficult issues

6 Streamlining the EIA Process KEY STAGES Screening* Scoping* & Initial Engagement Design Environmental Studies & Preparation of ES Submission of ES to LPA Review of adequacy of ES Consultation with key agencies and other interested parties Consideration of environmental information before making decision Issue of Decision * The highlighted steps form part of good practice in EIA but are not mandatory steps and are voluntary parts of the process.

7 Screening Applicant can request; decision by LPA within 3 weeks IEMA Special Report (June 2011) –“considerable anecdotal evidence to suggest that screening of all types of development proposals above the Schedule 2 thresholds is not regularly undertaken by all LPAs” Standard Checklist –leads to standard answer Bespoke Checklist? N.B. No EIA means less environmental information (not none)

8 Scoping Applicant can request; decision by LPA within 5 weeks Developers/Consultants –Keep it snappy –Forget scoping reports? –Challenge more LPAs –Exercise judgement wisely and specifically –One size doesn’t fit all – especially “wind impacts” –Avoid further information requests Statutory Consultees –Avoid generic responses and “wish lists” –Avoid duplication of controls

9 The Future Co-ordinated action EIA Forum? Hydro specific guidance? Aarhus-related increase in third party challenges? EU review of the EIA Directive to –ensure current level of environmental protection is maintained; –emphasise the quality of the EIA, rather than procedure; and –streamlining EIA requirements and remove duplication New EIA Directive in force 2016?

10 Contact Jennifer Ballantyne Partner, Planning & Environment Team T: 0141 567 8655 E: jennifer.ballantyne@pinsentmasons.comjennifer.ballantyne@pinsentmasons.com

11 Combining the experience, resources and international reach of McGrigors and Pinsent Masons Pinsent Masons LLP is a limited liability partnership registered in England & Wales (registered number: OC333653) authorised and regulated by the Solicitors Regulation Authority, and by the appropriate regulatory body in the other jurisdictions in which it operates. The word ‘partner’, used in relation to the LLP, refers to a member of the LLP or an employee or consultant of the LLP or any affiliated firm who is a lawyer with equivalent standing and qualifications. A list of the members of the LLP, and of those non-members who are designated as partners, is displayed at the LLP’s registered office: 30 Crown Place, London EC2A 4ES, United Kingdom. We use ‘Pinsent Masons’ to refer to Pinsent Masons LLP and affiliated entities that practise under the name ‘Pinsent Masons’ or a name that incorporates those words. Reference to ‘Pinsent Masons’ is to Pinsent Masons LLP and/or one or more of those affiliated entities as the context requires. © Pinsent Masons LLP 2012 For a full list of our locations around the globe please visit our websites: www.pinsentmasons.com www. O ut- L aw.com


Download ppt "Streamlining the EIA Process for Hydro Development 23 October 2012 Presented by Jennifer Ballantyne."

Similar presentations


Ads by Google