Presentation is loading. Please wait.

Presentation is loading. Please wait.

VALUE ADDED FEATURES Who’s Excited??? 2015 Construction Academy Larry Ritchie July 28 th, 2015.

Similar presentations


Presentation on theme: "VALUE ADDED FEATURES Who’s Excited??? 2015 Construction Academy Larry Ritchie July 28 th, 2015."— Presentation transcript:

1 VALUE ADDED FEATURES Who’s Excited??? 2015 Construction Academy Larry Ritchie July 28 th, 2015

2 WHAT ARE VALUE ADDED FEATURES (VAF)?  Features of a Construction project designated by the Specifications to include a warranty  Requires the Contractor or a delegated Responsible Party to repair deficiencies found in a Value Added Feature for a certain period of time  Warranty period can vary by Specification

3 WHY DO WE USE VAF?  Allows the Department to shift the risk of maintenance and repairs identified after final acceptance to the Contractor that performed the work  Drives good construction practices and proper Quality Control during Construction  Provides a maintenance – free product for a specified time

4 VALUE ADDED FEATURES IN THE SPECIFICATIONS  Value Added Asphalt Pavement (Section 338)  Value Added Reworked Asphalt Concrete Pavement (338B)  Value Added Repaved Asphalt Concrete Pavement (338C)  Value Added Portland Cement Concrete Pavement (Section 355)

5 VALUE ADDED FEATURES IN THE SPECFICATIONS (cont.)  Value Added Bridge Components (D/B only) (Section 475)  Performance Turf (Section 570)  Galvanized Steel Strain Poles, Mast Arms and Monotube Assemblies (Section 649)  Pavement Markings (Section 701, 702, 709, 711 and 713)

6 THE VALUE ADDED FEATURES PROCESS  Covered in great detail in CPAM chapter 8.148.14  Warranty Coordinators are structured differently in different Districts  Important to familiarize yourself with your District’s Warranty coordinator/coordinators  Regardless of structure, process found in Chapter 8.14 should be followed

7 THE VALUE ADDED FEATURES PROCESS  Features entered in Contract Information and Monitoring System (CIM)  Minimum number of inspection intervals are scheduled in CIM  Final inspection should be scheduled just before the end of the warranty period  For Value Added Pavement, inspection are accompanied by Pavement Condition Surveys (PCS)

8 THE VALUE ADDED FEATURES PROCESS  If deficiencies are noted, the Contractor or other Responsible Party is contacted to perform remedial work  Department sends a “Notice of Remedial Action” via certified mail  Contractor must submit a Remedial Action Plan or request a hearing at the Statewide Disputes Review Board  If the Contractor is responsible, he performs the remedial work  If the Contractor is not responsible the Department determines how the remedial work will be accomplished

9 THE VALUE ADDED FEATURES PROCESS  Once remedial work is completed and accepted, Contractor is notified of the acceptance in writing  Failure to perform  If the Contractor does not perform the remedial work, request a Statewide Dispute Review Board meeting or compensate the Department the project is sent to the Statewide Warranty Coordinator for further action

10 VALUE ADDED FEATURES DURING CONSTRUCTION WHAT YOU NEED TO KNOW!

11 VALUE ADDED ASPHALT PAVEMENT (Section 338)  Three year Warranty period  When construction of embankment, subgrade or base below the pavement is included in the Contract, the Contract, the Contractor is responsible for the warranty period  When there is no construction of embankment subgrade or base below pavement (milling and resurfacing), Contractor can designate Responsible Party

12 VALUE ADDED ASPHALT PAVEMENT (SECTION 338)  Responsible Party must be a Sub-Contractor must be prequalified for asphalt  Contractor must designate a Responsible Party using Form # 700- 010-53700- 010-53  Form must be given to Warranty Coordinator for future remedial work

13 PAVEMENT DEFICIENCIES (SECTION 338)

14

15 PAVEMENT DEFICIENCIES (Section 338)

16

17

18 VALUE ADDED REWORKED ASPHALT CONCRETE PAVEMENT (Section 338B)  Three year warranty period  Contractor is responsible for the warranty of the feature  Contractor must perform remedial work and provide a Warranty/Maintenance bond  Bond must be submitted and accepted upon final acceptance  Bond only covers the reworked asphalt layer and hot mix friction course layer

19 VALUE ADDED REPAVED ASPHALT CONCRETE PAVEMENT (Section 338C)  Five year warranty period  Contractor is responsible for the warranty of the feature  Contractor must perform remedial work and provide a Warranty/Maintenance bond  Bond must be submitted and accepted upon final acceptance  Bond covers the binder course layer and the friction course layer

20 VALUE ADDED PORTLAND CEMENT CONCRETE PAVEMENT (Section 355)  Five year warranty period  Contractor is responsible for the warranty of the feature

21 VALUE ADDED BRIDGE COMPONENTS (Section 475 Design Build only)  Five year warranty period  Contractor is responsible for the warranty of the feature unless otherwise agreed to by the Department  Warranty covers materials and workmanship  Bridge Deck Expansion Joint Devices and Hardware  Armor and Hardware

22 VALUE ADDED BRIDGE COMPONENTS (Section 475 Design Build only)  Seals  Coatings  Bearing Devices  Bridge Lighting/Electrical Systems  Drainage Systems

23 PERFORMANCE TURF (Section 570)  Contractor must warranty the feature  No set time period for the warranty  Contractor must maintain all turf areas, including erosion prevention and sediment control until it meets the Department’s definition of “established”  Only VAF whose warranty period could end with final acceptance

24 PERFORMANCE TURF DEFICIENCIES (Section 570)

25

26 GALVANIZED STEEL STRAIN POLES, MAST ARMS AND MONOTUBE ASSEMBLIES (Section 649)  Five year warranty period that only applies when poles, mast arms and assemblies are painted as called for in the contract Documents  Contractor can designate the feature fabricator as the Responsible Party for the warranty period using Form # 700-010-20700-010-20  Failure to timely designate a Responsible Party will result in the Contractor being the Responsible Party for the duration of the warranty period.

27 MAST ARM DEFICIENCIES (Section 649)

28

29

30 PAVEMENT MARKINGS (Sections 701, 702, 709, 711, 713)  180 day observation/warranty period that begins with satisfactory completion and acceptance of the work  Contractor is responsible for the warranty of the feature  Direct replacement of items – no remedial work

31 QUESTIONS???


Download ppt "VALUE ADDED FEATURES Who’s Excited??? 2015 Construction Academy Larry Ritchie July 28 th, 2015."

Similar presentations


Ads by Google