Presentation is loading. Please wait.

Presentation is loading. Please wait.

INTEROPERABILITY Tests IOP11/2002 1 IEC 61850 Interoperability with IEC 61850 IEC 61850 INTEROPERABILITY BETWEEN ABB, ALSTOM and SIEMENS STATUS REVIEW.

Similar presentations


Presentation on theme: "INTEROPERABILITY Tests IOP11/2002 1 IEC 61850 Interoperability with IEC 61850 IEC 61850 INTEROPERABILITY BETWEEN ABB, ALSTOM and SIEMENS STATUS REVIEW."— Presentation transcript:

1 INTEROPERABILITY Tests IOP11/2002 1 IEC 61850 Interoperability with IEC 61850 IEC 61850 INTEROPERABILITY BETWEEN ABB, ALSTOM and SIEMENS STATUS REVIEW November 2002 IEC 61850 the global standard for communication in substations

2 INTEROPERABILITY Tests IOP11/2002 2 IEC 61850 Support for IEC 61850  ABB, Alstom and Siemens (A-A-S) are deeply engaged in the elaboration of the IEC 61850 standard.  Each of these companies will implement IEC61850 in its power automation products and systems.  A roadmap for the staged implementation of IEC 61850 has been defined in line with the progress of the standard.  To verify the implementation of IEC61850 of all three suppliers, joint interoperability tests have been specified. The first test step has now been completed successfully.

3 INTEROPERABILITY Tests IOP11/2002 3 IEC 61850 IEC 61850 Interoperability in two phases Specification level Phase 1 (P1): Basic functions GOOSE* Phase 2 (P2): Advanced functions Best practice used for the implementation with respect to the standard. Phase1Phase 2 Typical functions of a substation automation system *GOOSE: Generic Object Oriented Substation Event

4 INTEROPERABILITY Tests IOP11/2002 4 IEC 61850 Schedule of activities The way to interoperable substation automation 20022003200420012000 20022003200420012000 Further interoperability tests Test P2a Test P1 First interoperability tests of bay devices Committee draft Final draft International Standard International Standard Committee draft for vote Kickoff IEC 61850 IEC A-A-S Test P2b

5 INTEROPERABILITY Tests IOP11/2002 5 IEC 61850 What is GOOSE?  GOOSE ( Generic Object Oriented Substation Event)  It is a mechanism for the fast transmission of substation events, such as commands, alarms, indications, as messages  A single GOOSE message sent by an IED * can be received and used by several receivers  GOOSE takes advantage of the powerful Ethernet and supports real-time behaviour  It is used for e.g.  tripping of switchgear  starting of disturbance recorder  providing position indication for interlocking * IED: Intelligent Electronic Device

6 INTEROPERABILITY Tests IOP11/2002 6 IEC 61850 IEC 61850 GOOSE Principle GOOSE Sender Device X GOOSE Receiver Device Y GOOSE Receiver Device Z Ethernet One device (sender) publishes information, only the subscriber devices are receiving it. The reaction of each receiver depends on its configuration and functionality. EXAMPLE: GOOSE message

7 INTEROPERABILITY Tests IOP11/2002 7 IEC 61850 Test configuration of phase 1 100 Mbit/s redundant switched Ethernet ring KEMA UniCA- IEC61850 GOOSE Simulator Network Analyser KEMA UniCA- IEC61850 Analyser GOOSE messages GOOSE: Generic Object Oriented Substation Event

8 INTEROPERABILITY Tests IOP11/2002 8 IEC 61850 Substation Configuration Language (SCL) SCL is the basis for the success of Plug & Play SCL provides a common object and configuration description Result of Phase 1 Test: Plug & Play! SCL file distributed and agreed by A-A-S via email

9 INTEROPERABILITY Tests IOP11/2002 9 IEC 61850 Tripping via GOOSE GOOSE Sender Device X GOOSE Receiver Device Y GOOSE Receiver Device Z Ethernet Fault Simulation GOOSE message with commands for CB * tripping and disturbance recorder starting Configuration: sender X --> receiver Z „Y does not react“ „Z starts its disturbance recording“ „CB* off“ Injection test device * CB = Circuit Breaker

10 INTEROPERABILITY Tests IOP11/2002 10 IEC 61850 Negative tests GOOSE Sender Device X GOOSE Sender Device Y GOOSE Receiver Device Z Ethernet Fault simulation GOOSE message with commands for CB tripping and disturbance recorder starting Configuration: sender Y --> receiver Z not configured „no reaction“ Injection test device

11 INTEROPERABILITY Tests IOP11/2002 11 IEC 61850 Positive tests GOOSE Sender Device X GOOSE Sender Device Y GOOSE Receiver Device Z Ethernet GOOSE message with commands for CB tripping and disturbance recorder starting Configuration: sender Y --> receiver Z Fault simulation Injection test device „CB off“

12 INTEROPERABILITY Tests IOP11/2002 12 IEC 61850 Performance tests: Background traffic GOOSE Sender Device X GOOSE Receiver Device Y GOOSE Receiver Device Z KEMA UniCA- IEC61850 GOOSE Simulator Produced 10, 50,150, 300 GOOSE messages within 50ms measured time Fault CB off 100 Mbit/s redundant switched Ethernet ring Heavy busload

13 INTEROPERABILITY Tests IOP11/2002 13 IEC 61850 Performance tests: Device load 100 Mbit/s redundant switched Ethernet ring GOOSE Sender Device X GOOSE Receiver Device Y GOOSE Receiver Device Z KEMA UniCA- IEC61850 GOOSE Simulator measured time Fault CB off Produced 10, 50,150, 300 GOOSE messages within 50ms Heavy busload Heavy device load

14 INTEROPERABILITY Tests IOP11/2002 14 IEC 61850 Phase 1: Performance tests The transmission time was dependent of today`s software implementation. Bus load or device load had no major effect. Software implementation

15 INTEROPERABILITY Tests IOP11/2002 15 IEC 61850 Interoperability test concept Number of tests  Positive tests9 Correct message transmission between configured senders and receivers  Negative tests (selectivity & security)9 Message ignored by non-configured receiver  Degraded tests (quality, testmode...)10 No reaction to faulty or test messages in all receivers  Performance / Load tests11 Response times measured with different background loads

16 INTEROPERABILITY Tests IOP11/2002 16 IEC 61850 Test results Experience from the rejected resp. dismissed test cases was used to improve the IEC 61850 specification and implementation. Number of test cases

17 INTEROPERABILITY Tests IOP11/2002 17 IEC 61850 A week of successful work The teams from A-A-S

18 INTEROPERABILITY Tests IOP11/2002 18 IEC 61850 Conclusion  An important part of the standard was tested successfully  39 cases have been tested within one week  The standardisation documents are well defined  Three major companies in the substation and substation automation business are on track with their implementation of IEC 61850 A-A-S is on track - and on the right way


Download ppt "INTEROPERABILITY Tests IOP11/2002 1 IEC 61850 Interoperability with IEC 61850 IEC 61850 INTEROPERABILITY BETWEEN ABB, ALSTOM and SIEMENS STATUS REVIEW."

Similar presentations


Ads by Google