CAPITAL COST ESTIMATES INSTALLED EQUIPMENT COSTS
2
INSTALLED COST ESTIMATE METHODS FOR TYPE 1 OR 2 FEASIBILITY ESTIMATE USE PURCHASED EQUIPMENT COSTS AND FACTORS SIMPLEST IS SIMPLY 4.0 FACTOR FOR PLANT TYPE ADJUSTMENT SEE TABLE 6- 10. RANGES ARE FROM 4.7 -6.0.7 USE M&S INDICES FOR INFLATION COST SCALE- UP FOR INDIVIDUAL EQUIPMENT, USE FACTORS FROM CHEMICAL ENGINEERING PLANT COST INDEX (ALSO IN CHEMICAL ENGINEERING MAGAZINE)
3
SPECIFIC PLANTS THE TEXT HAS SOME PLANT DATA IN TABLE 6-11 DATA IS SCALED UP FROM 1970 DATA SO IS IN QUESTION MOST ESTIMATES ARE BASED ON EQUIPMENT COSTS THAT EQUIPMENT COSTS CARRY AN ACCURACY LIMIT AS WELL - +25% IS TYPICAL FOR PEP PROJECTS AT SRI
4
ESTIMATE EXAMPLE EQUIPMENT FOR PROCESS MODIFICATION
5
ESTIMATE EXAMPLE RELATIVE MATERIALS COSTS
6
FOR TYPE 3 FUNDING ESTIMATE USE PROJECT DATA - DESIGN CRITERIA, DESIGN BASES, INITIAL SITE DATA NEED STRUCTURAL DATA NEED SHOP VS. FIELD FABRICATION DATA NEED LABOR VALUES USE VENDOR QUOTES FOR EQUIPMENT PLUS SHIPPING TO GET DELIVERED COSTS
7
FOR CONTROL BUDGET NEED FINAL DRAWINGS NEED QUOTATIONS FROM CONSTRUCTION SUBCONTRACTORS WHERE AVAILABLE NEED SPECIFIC COSTS FOR EQUIPMENT, MATERIALS, LABOR AND ERECTION EQUIPMENT NEED DEFINITION OF SHOP VS. FIELD RESOURCES
8
CAPITAL ESTIMATE COMPONENTS DIRECT FIXED CAPITAL INCLUDES COMPONENTS AS PER TABLE 6-3 DEFINITION SUMMARY (TABLE 6-9) TOTAL PLANT CAPITAL (TPC) = TOTAL PLANT DIRECT CAPITAL (TPDC) + TOTAL PLANT INDIRECT COSTS (TPIC) + WORKING CAPITAL (WC) TPC = TPDC + TPIC+ WC
9
FEASIBILITY ESTIMATE DEVELOP PEC AND USE PEC FACTORS METHOD TYPICAL FACTORS FOR ESTIMATE COMPONENTS ARE IN TABLE 6-3 & 6-17
10
INSTALLATION COSTS DEPENDS ON AMOUNT OF PIPING VS. SOLIDS HANDLING (NON-SLURRY) INCLUDES FOUNDATION AND STRUCTURAL BUT NO INTERCONNECTING SYSTEMS IF ESTIMATED ON AN EQUIPMENT ITEM BASIS, SEE TABLE 6-5 FOR TYPICAL VALUES PROCESS PIPING FACTOR RANGES OVER PLANT TYPE FROM SOLIDS ONLY TO FLUIDS ONLY SEE TABLE 6-6 FOR FACTORS
11
INSTRUMENTATION FACTORS RANGE FROM MANUAL TO TOTAL COMPUTER CONTROL, 10% - 50% OF PEC MOST PLANTS USE THE 35% LEVEL WITH DISTRIBUTED CONTROL SYSTEMS BATCH OR INTERMITTENT OPERATION THROUGH PROGRAMMABLE CONTROLLERS FOR A DISCUSSION OF THE USE OF WIRELESS INSTRUMENTATION : http://www.automationworld.com/view-1936
12
OTHER FACTORS INSULATION FACTORS USED FOR CONTROL OF HEAT LOSS, HEAT GAIN AND PERSONNEL PROTECTION TOTALS RUN AROUND 8% OF PEC ELECTRICAL FACILITIES FACTOR DOES NOT INCLUDE CONTROL, BUT DOES INCLUDE POWER SUPPLIES. ASSUMES POWER FROM SOURCE OUTSIDE OF BATTERY LIMITS AMOUNTS TO ABOUT 15% OF PEC SEE COMPONENTS IN TABLE 6-8
13
OTHER FACTORS BUILDINGS FACTOR DEPENDS ON CRITERIA FOR JOB FOR JOB FOR EXISTING PLANTS, TYPICAL VALUES ARE SHOWN IN TABLE 6-9 YARD IMPROVEMENT INCLUDES ALL THE CIVIL ASPECTS OF THE PROJECT INITIAL GRADING UNDERGROUND UTILITY SYSTEMS TRANSPORTATION COMPONENTS AND FINISH OUTSIDE OF PROCESS AREAS
14
OTHER DIRECT COSTS AUXILIARY SYSTEMS THE UTILITY COMPONENTS FROM OUTSIDE THE BATTERY LIMITS REQUIRED FOR OPERATION MAY INCLUDE UPGRADE OF EXISTING UNITS.
15
INDIRECT COMPONENT FACTORS ENGINEERING COSTS INCLUDE COSTS FOR DESIGN THROUGHOUT THE PROJECT. TEND TO INCLUDE ASPECTS OF CONSTRUCTION. VALUES ARE SHOWN AS TOTAL IN TABLE 6-9 CONSTRUCTION INCLUDES ADMINISTRATION OF ALL ASPECTS OF PROJECT DEPENDS ON MANY FACTORS AS INDICATED IN TABLE 6-9
16
INDIRECT COMPONENT FACTORS CONTRACTORS FEE PROFIT AND OVERHEAD COMPONENT FOR ENGINEERING AND CONSTRUCTION FIRMS RANGES AROUND 4-6% OF TOTAL FIXED CAPITAL INVESTMENT CONTINGENCY - ANTICIPATED COSTS FOR CHANGES THAT WILL OCCUR DURING THE PROJECT FOR THIS PROJECT USE THE VALUES IN TABLE 6.17 AND EXPLAIN BASIS OF CHOICE
17
METHOD D - LANG FACTORS BASED ON PEC (4.7x TO 6.0x PEC) BASED ON CORRELATION FOR A LARGE NUMBER OF PROJECTS OFTEN AS ACCURATE AS DETAILED FACTOR METHOD TYPICAL LANG FACTORS ARE SHOWN IN TABLE 6-10