Presentation is loading. Please wait.

Presentation is loading. Please wait.

Concrete Construction

Similar presentations


Presentation on theme: "Concrete Construction"— Presentation transcript:

1 Concrete Construction

2 3 major costs of concrete
Formwork costs including labor, equipment, and materials Cost of reinforcing steel and placement Concrete materials, equipment, and labor for placing, curing, and finishing F11-1

3 Cast in Place Traditional method
Allows concrete to be formed to site conditions Used on most construction sites for structural members Concrete placed in forms to cure Forms removed after enough strength in concrete to support self and additional construction loads

4 Cast in Place Walls and wall footings
Need to avoid voids and separation of materials due to large fall Special care for areas under windows , pipe chases and other formwork installed inside wall forms Can pump concrete from bottom of form to get rid of voids

5 Cast in Place Floors and roofs
One way slab – only supported in one direction F 11-3 Slab and beam Slab, beam & girder Outside beam is called spandrel beam Columns poured before slabs – shrinkage If poured same time could stress floors and beams due to shrinkage

6 Cast in Place Floors and roofs
One way slab – only supported in one direction F 11-3 Slab and beam Slab, beam & girder Outside beam is called spandrel beam Two directional slabs (waffles) provide support in two perpendicular directions supported by columns

7 Cast in Place 2 way Flat slabs Basically joists in both directions
Supported directly by columns Uses column capitals to distribute load over larger area More reinforcement needed to carry loads to columns F 11-6

8 Precast concrete Cast into desired shape at plant and moved to site
Controlled environment -> better finish and quality All prestressed and pretensioned members are precast F 11-7, 11-8

9 Precast concrete Types Joists and purlins F 11-7 Roof and floor panels
Flat 1-4” thick, 15 – 32” wide, 4-10’ long hollow core 4 – 12” thick, 4-8’ wide, 15 – 50’ long tee, double tee 4-12’ wide span 12 – 100 feet channel slabs 2 – 5 ‘ wide, ‘ long F11-8

10 Precast concrete Types Walls
Usually curtain wall construction panels fit between structural components to form wall But used in tilt up construction Panels cast horizontally on existing slab and tilted upright F 11-9

11 Prestressed Concrete Initial compression load applied to concrete
Places entire beam in compression Makes beam stronger since more force is required to induce a tension component Reduces deflection F11-10

12 Prestressed Concrete 2 ways to do
Pretension – place prestressing material in tension in the form while concrete is poured Once concrete hardened remove tension Bond between steel and concrete keeps steel in place Post tensioning – steel is placed inside a plastic tube during concrete pouring Upon placement steel is tensioned and the steel is mechanically anchored to the concrete at each end Load is removed and steel cut flush

13 Architectural Concrete
Appearance effects Shape, size, texture, and color F & 11-13

14 Concrete Construction Practices
Transporting and Hauling Need to avoid segregation of materials in concrete Wheelbarrows, buggies, chutes, pumps, conveyors, buckets, trucks Placing and consolidating Need to make sure form surfaces and bracing is right before placing concrete

15 Placing Forms must be coated in oil to allow removal
If placing concrete on ground – must moisten ground If pouring on top of cured concrete must place bonding agent between pours Shotcrete (gunite) – concrete placed pneumatically Consolidation – removing air voids vibration

16 Finishing & Curing Finishing – bring surface of concrete to its final position and surface texture Screeding – striking off excess concrete Floating – smoothes and compacts concrete imbeds aggregates Troweling – compacts surface F 11-16 Brooming – surface texture

17 Curing To get good concrete must cure properly
Moisture and temperature are key Moisture – wet straw or burlap, curing compounds Vacuum dewatering – mat placed on concrete Vacuum applied to mat – takes out excess water Lower W/C ratio -> denser mix

18 Hot weather Concreting
Curing accelerates when concrete temp above 50 – 60 F How to lower temp Use cold water in mix Cool aggregates before mixing Use Type IV (low heat cement) Add a retarder Decrease max time to discharge to 1 hour

19 Cold weather Concreting
Concrete should not freeze for 1st 24 hours Min temp for placement is 50F Use type III (hi early strength) Use accelerator Heat water and aggregates before mixing Use vented heaters to keep concrete warm


Download ppt "Concrete Construction"

Similar presentations


Ads by Google