LADOTD CONSTRUCTION COST ESTIMATING Charles Nickel, P.E. Cost Estimate & Value Engineering Director Office: (225) 379-1078

Similar presentations


Presentation on theme: "LADOTD CONSTRUCTION COST ESTIMATING Charles Nickel, P.E. Cost Estimate & Value Engineering Director Office: (225) 379-1078"— Presentation transcript:

1 LADOTD CONSTRUCTION COST ESTIMATING Charles Nickel, P.E. Cost Estimate & Value Engineering Director Office: (225) 379-1078 E-mail: Charles.Nickel@la.gov

2 Cost Estimating Process GOAL: To provide guidance in developing and maintaining accurate, consistent, and reliable project cost estimates. To provide guidance in developing and maintaining accurate, consistent, and reliable project cost estimates.

3 Project Management Body of Knowledge (PMBOK) Cost Management Involves 3 Processes: 1)Cost Estimating 2)Cost Budgeting 3)Cost Control

4 Project Management Body of Knowledge (PMBOK) Cost Management Involves 3 Processes: 1)Cost Estimating 2)Cost Budgeting 3)Cost Control

5 Cost Estimating Process Types of Project Cost Estimates: 1.) Engineering 2.) Construction 3.) Right-of-Way 4.) Utilities 5.) Mitigation (Permits, Approvals, etc.)

6 Cost Estimating Process Types of Project Cost Estimates: 1.) Engineering 2.) Construction 3.) Right-of-Way 4.) Utilities 5.) Mitigation (Permits, Approvals, etc.)

7 Cost Estimating Process Some common methods of Cost Estimating: Historical Bid Based Historical Bid Based Cost Based Cost Based Parametric Parametric Risk Based Risk Based

8 Cost Estimating Process Some common methods of Cost Estimating: Historical Bid Based Historical Bid Based Cost Based Cost Based Parametric Parametric Risk Based Risk Based

9 Historical Bid Based Estimating Uses previous bid data as a basis for cost estimating. Uses previous bid data as a basis for cost estimating. Items with little or no bid history are much more difficult to estimate with this method, if not impossible. Items with little or no bid history are much more difficult to estimate with this method, if not impossible.

10 Historical Bid Based Estimating Long Range Estimates Long Range Estimates Detailed Estimates Detailed Estimates

11 Historical Bid Based Long Range Estimating Estimating Using Major Item Cost Groups

12 Historical Bid Based: Long Range Estimating Asphalt Asphalt Base Base Concrete Concrete Drainage Drainage Earthwork Earthwork Erosion Control Erosion Control Cost groups are based on line items classified into major item categories such as: Gates & Fences Gates & Fences Guiderail Guiderail Landscaping Landscaping Mobilization Mobilization Pavement marking Pavement marking etc. etc.

13 Historical Bid Based: Long Range Estimating Item Group Cost = XX% Project Cost Project Cost = Item Group Cost / XX%

14 Historical Bid Based: Long Range Estimating For example, for a particular type of roadway project, historically; Asphalt Items:58% of Project Cost Base Items:12% of Project Cost Mobilization:10% of Project Cost Other Items:20% of Project Cost

15 Historical Bid Based: Long Range Estimating Item Group Cost = Quantity ∙ Item Group Cost = Quantity ∙ Unit Price

16 Historical Bid Based: Long Range Estimating Quantities for cost groups can be estimated based on early project measurements such as: Length of roadway Length of roadway Width of roadway Width of roadway Depth of pavement Depth of pavement Number of intersections Number of intersections Etc. Etc.

17 Historical Bid Based: Long Range Estimating Once the quantities are estimated, Unit Prices can be determined based on historical bid data.

18 Historical Bid Based: Long Range Estimating Estimate of Asphalt Group:$1.5 M Estimate of Base Group:$1.2 M $2.7 M $2.7 M / (58% + 12%) = $3.8 M Construction Cost = $3.8 M + contingencies

19 Detailed Estimates

20 Historical Bid Based: Detail Estimating Involves past item level relationships between the unit price and other measurable parameters of the item such as: Quantity Quantity Letting Date Letting Date Number of Bidders Number of Bidders Location Location Size Size Type of Work Type of Work Etc., Etc., Etc., … Etc., Etc., Etc., …

21 Historical Bid Based: Detail Estimating Modeling Unit Price relationships Simple Linear Regressions Not so Simple Linear Regressions

22 Simple Linear Regression Models Simple Linear Regression Models For example: Unit Price =  0 +  1 ∙ (Bid Date) Log(Unit Price) =  0 +  1 ∙ Log(Quantity) Historical Bid Based: Detail Estimating

23

24

25

26

27

28

29

30

31

32 More Complex Linear Regression Models More Complex Linear Regression Models For example: Log(Unit Price) =  0 +  1 ∙ Log(Quantity) +  2 ∙ (Bid Date) Historical Bid Based: Detail Estimating

33

34 Adjust the bid points to reflect only one relationship at a time.

35

36

37

38

39

40 Historical Bid Based: Detail Estimating The more relationships that can be identified and modeled, the closer the adjusted bid points will be to the trend lines. The amount of time and resources spent identifying and modeling these relationships will determine the level of accuracy achievable.

41

42 Estimating Tools: Excel Spreadsheets Access Database Applications Trns*port CES All these tools rely on the EXPERIENCE of the ESTIMATOR to use them wisely to develop the Construction Cost Estimate.

43 QUESTIONS? Charles Nickel, P.E. Cost Estimate & Value Engineering Director Office: (225) 379-1078 E-mail: charles.nickel@la.gov