Presentation is loading. Please wait.

Presentation is loading. Please wait.

Work Breakdown Structure Workshop

Similar presentations


Presentation on theme: "Work Breakdown Structure Workshop"— Presentation transcript:

1 Work Breakdown Structure Workshop

2 WBS Workshop Objectives
To reinforce the value of and approach towards work breakdown structures To reinforce the value of integrated scope, cost, time based estimates To illustrate the use of WBS for Project

3 Workshop Structure Theory Review Work an example together Lunch
Individual WBS development Share in breakout groups Debrief whole group

4 WBS Purpose Definition Structure Guidelines Work Packages
Implementation Exercise

5 WBS - Purpose To plan a project, the total scope of work must be:
identified subdivided into manageable segments assigned to individuals responsible to do the work documented

6 WBS - Definition A deliverable oriented grouping of project elements which organizes and defines the total scope of the project. Each descending level represents an increasingly detailed definition of a project component.

7 WBS - Guidelines Should reflect how the Project Manager plans to manage the project Emphasis must be on meeting project objectives The larger or more complex the project, the more levels in the WBS If work is needed that requires effort or funding, it should be included in the WBS It should reflect the total effort

8 Guidelines - continued
Include three types of project work Product Specifically assigned to a physical product as a unique deliverable This subset is sometimes referred to as the product breakdown structure Integration When products are brought together as a unit Can be at any level Support Level of Effort, Administration, Expenses, Improvement Practices, Contractor Management

9 Guidelines (cont) Sometimes the top level in the WBS should be the project phases Often though, a work breakdown structure is constructed for each phase

10 WBS - Structure

11 WBS - Product

12 WBS - Integration

13 Typical Integration Elements
Regulatory Permitting Legal Intellectual Property Logistics SOP’s Training Spares Philosophy and Provisioning HES Quality Assurance Communications Systems Engineering Purchasing Hazard Analysis Value Improving Practices Others?

14 WBS - Support

15 WBS - Work Packages Lowest agreed level for management purposes
Enables delegation of responsibility and authority Results in ownership and accountability Building block of the Project Baseline Plan Provides a common basis for Estimation of Scope, Time, Resources, and Risk Comparison between plan and actual

16 How to build a WBS Begin with the Charter, focusing on Objectives and Deliverables Break the main product(s) down into sub-products Set the structure to match how you’ll manage the project Lowest level not too detailed, not too large Is there a need for Integration? Identify support activities Check for completeness - is all the effort included? Develop a coding structure if needed Assign work package managers

17 Group Exercise Using the Project Charter provided, let’s build a work breakdown structure together We will then develop A project organization A linear responsibility chart

18 Individual Exercise Using the charter you brought, develop a WBS
Hypothetically assign work package managers We will be sharing each one of them with the group and critiquing it

19 Suggested WBS Template Process


Download ppt "Work Breakdown Structure Workshop"

Similar presentations


Ads by Google