1 Contracts and Procurement
Project Management Contracts and Procurement

2 Outline Introduction Procurement Requirement Cycle Requisition Cycle
Solicitation Cycle Award Cycle

3 Outline Types of Contracts Incentive Contracts
Contract Type versus Risk Contract Administration Cycle Using a Checklist Proposal-Contractual Interaction

4 Procurement Strategies
Corporate procurement strategy: the relationship of specific procurement actions to the corporate strategy Project procurement strategy: the relationship of specific procurement actions to the operating environment of the project

5 Procurement Objectives
Procure all goods/services from a single source. Procure all goods/services from multiple sources. Procure only a small portion of the goods/ services. Procure none of the goods/services.

6 Procurement Management
Requirement cycle: definition of the boundaries of the project Requisition cycle: analysis of sources Solicitation cycle: the bidding process Award cycle: contractor selection and contract award Contract administration cycle: managing the subcontractor until completion of the contract

7 Requirement Cycle Defining the need for the project
Development of the statement of work, specifications, and work breakdown structure Performing a make or buy analysis Laying out the major milestones and the timing/schedule Cost estimating, including life-cycle costing Obtaining authorization and approval to proceed

8 Specifications Specifications are written, pictorial, or graphic information that describe, define, or specify the services or items to be procured. There are three types of specifications:

9 Types of Specifications
Design specifications: These detail what is to be done in terms of physical characteristics. The risk of performance is on the buyer. Performance specifications: These specify measurable capabilities the end product must achieve in terms of operational characteristics. The risk of performance is on the contractor.

10 Types of Specifications (Continued)
Functional specifications: This is when the seller describes the end use of the item to stimulate competition among commercial items, at a lower overall cost. This is a subset of the performance specification, and the risk of performance is on the contractor.

11 The Make Decision Less costly (but not always!!)
Easy integration of operations Utilize existing capacity that is idle Maintain direct control Maintain design/production secrecy Avoid unreliable supplier base Stabilize existing workforce

12 The Buy Decision Less costly (but not always!!)
Utilize skills of suppliers Small volume requirement (not cost effective to produce) Having limited capacity or capability Augment existing labor force Maintain multiple sources (qualified vendor list) Indirect control

13 Requisition Cycle Evaluating/confirming specifications (are they current?) Confirming sources Reviewing past performance of sources Producing solicitation package

14 Solicitation Package Bid documents (usually standardized)
Listing of qualified vendors (expected to bid) Proposal evaluation criteria Bidder conferences How change requests will be managed Supplier payment plan

15 Solicitation Cycle Advertising Negotiation
Small purchases (i.e., office supplies)

16 Negotiation Processes
Request for information (RFI) Request for quotation (RFQ) Request for proposal (RFP)

17 Negotiation Factors Compromise ability Adaptability Good faith

18 Negotiation Planning Develop objectives (i.e., min-max positions)
Evaluate your opponent Define your strategy and tactics Gather the facts Perform a complete price/cost analysis Arrange “hygiene” factors

19 Negotiation Objective-Setting
Buyer Min Objective Max Seller Min Objective Max Price

20 Award Cycle Conclusion: The objective of the award cycle is to negotiate a contract type and price that will result in reasonable contractor risk and provide the contractor with the greatest incentive for efficient and economic performance.

21 Contracting Elements Mutual agreement Consideration
Contract capability Legal purpose Form provided by law

22 Contract Forms Completion contract Term contract

23 Contract Selection Criteria
Overall degree of cost and schedule risk Type and complexity of requirement (technical risk) Extent of price competition Cost/price analysis Urgency of the requirements Performance period Contractor’s responsibility (and risk)

24 Contract Selection Criteria (Continued)
Contractor’s accounting system (is it capable of earned value reporting?) Concurrent contracts (will my contract take a back seat to existing work?) Extent of subcontracting (how much work will the contractor outsource?)

25 Contractor’s Risks FFP CPFF HIGH LOW Risk On Contractor LEGEND
FFP FIRM FIXED PRICE CPFF COST PLUS FIXED FEE

26 Firm-Fixed-Price Contract (FFP)
Maximum risk with contractor Higher negotiated profit margins High likelihood of scope changes 100 % RISK SHARING METER 0 % RISK CONTRACTOR’S CUSTOMER’S RISK RISK LOCATION 0 % 100 %

27 Firm-Fixed-Price With Economic Price Adjustments (FPE)
Adjustments for escalation factors Adjustments for inflation Negotiated adjustment cycle 100 % RISK SHARING METER 0 % RISK CONTRACTOR’S CUSTOMER’S RISK RISK LOCATION 0 % 100 %

28 Incentive Contracts Additional profits are possible by lowering cost
Customer and contractor share cost savings

29 Principles of Incentive Contracts
CUSTOMER PAYS 80 % OF OVERRUN CONTRACTOR PAY 20 % OF OVERRUN PROFIT IS $1500 LESS EXAMPLE CONTRACTOR’S 20 % TARGET COST: $20,000 TARGET FEE: $1500 CUSTOMER KEEPS 80 % OF OVERRUN CONTRACTOR KEEPS 20 % OF OVERRUN PROFIT IS $1500 PLUS SHARING RATIO: 80/20 % CONTRACTOR’S 20 % NOTE: LIMITATIONS MAY BE IMPOSED ON PRICE OR PROFIT

30 Fixed-Price-Incentive-Fee Contract (FPIF)
Contractor can earn additional profits Contract has a ceiling on price (or cost) paid Price (or cost) ceiling at point of total assumption 100 % RISK SHARING METER 0 % RISK CONTRACTOR’S CUSTOMER’S RISK RISK LOCATION 0 % 100 %

31 Cost-Plus-Incentive-Fee Contract (CPIF)
Contractor can earn additional profits All costs are reimbursed (cost run-ups) A “floor” and “ceiling” exists on profits 100 % RISK SHARING METER 0 % RISK CONTRACTOR’S CUSTOMER’S RISK RISK LOCATION 0 % 100 %

32 Cost-Plus-Award-Fee Contract (CPAF)
All costs are reimbursed (cost run-ups) Negotiated range of possible profits Customer determines profit paid at completion 100 % RISK SHARING METER 0 % RISK CONTRACTOR’S CUSTOMER’S RISK RISK LOCATION 0 % 100 %

33 Cost-Plus-Fixed-Fee Contract (CPFF)
All costs are reimbursed (cost run-ups) Fee is fixed (in $$$ not %) irrespective of costs Contractor is motivated for early completion 100 % RISK SHARING METER 0 % RISK CONTRACTOR’S CUSTOMER’S RISK RISK LOCATION 0 % 100 %

34 Cost-Sharing Contract (CS)
No profits allowed Customer and contractor share costs Contractor may retain control of 100 % RISK SHARING METER 0 % RISK CONTRACTOR’S CUSTOMER’S RISK RISK LOCATION 0 % 100 %

35 Cost Contract (C) 100 % 0 % 0 % 100 % No profits allowed
Contractor is usually a non-profit organization Limitations on costs allowed may be imposed 100 % RISK SHARING METER 0 % RISK CONTRACTOR’S CUSTOMER’S RISK RISK LOCATION 0 % 100 %

36 Cost-Plus-Percentage-Of-Cost Contract (CPPC)
Costs incurred may be unlimited Contractors can maximize profits Scope changes may be frequent and unlimited 100 % RISK SHARING METER 0 % RISK CONTRACTOR’S CUSTOMER’S RISK RISK LOCATION 0 % 100 %

37 Relative Contract Risk
RISK SHARING METER 0 % 100 % FFP FFE RISK RISK FPIF CUSTOMER’S CONTRACTOR’S CPIF CPAF CPPC CPFF RISK LOCATION CS C 0 % 100 %

38 There are several other types of contracts available
There are several other types of contracts available. They may be derivatives of these contracts, combinations, or simply special contracts for special circumstances.

39 Contract Administration Cycle
Change management Specification interpretation Adherence to quality Warranties Subcontractor management Production surveillance Waivers Contract breach

40 Contract Administration Cycle (Continued)
Resolution of disputes Project termination Payment schedules Project closeout

41 Order of Precedence Specifications (first priority)
Other instructions (second priority) Other documents, such as exhibits, attachments, appendices, SOW, contract date requirements list [CDRL], etc. (third priority) Contract clauses (fourth priority) The schedule (fifth priority)

42 Type of Changes Administrative change Change order
Contract modification Undefinitized contractual action Supplemental agreement Constructive change

43 Causes of Constructive Changes
Defective specification with impossibility of performance Erroneous interpretation of contract Over-inspection of work Failure to disclose superior knowledge Acceleration of performance Late or unsuitable owner or customer furnished property

44 Causes of Constructive Changes
Failure to cooperate Improperly exercised options Misusing proprietary data

45 Reasons for Termination for Convenience of the Customer
Elimination of the requirement Technological advances in the state-of-the-art Budgetary changes Related requirements and/or procurements Anticipating profits not allowed

46 Reasons for Termination for Default Due to Contractor’s Actions
Contractor fails to make delivery on scheduled date. Contractor fails to make progress so as to endanger performance of the contract and its terms. Contractor fails to perform any other provisions of the contract.

47 Contract Administration Rights
Reject the entire shipment Accept the entire shipment (barring latent defects) Accept part of the shipment