Presentation is loading. Please wait.

Presentation is loading. Please wait.

Construction Management

Similar presentations


Presentation on theme: "Construction Management"— Presentation transcript:

1 Construction Management
M I N I T A B H E A D Q U A R T E R S Erin E. Hess Construction Management Senior Thesis Presentation April 15, 2003 Alexander Constructors, Inc. Building Construction

2 Presentation Outline Project Description Cladding System
Mechanical System Green Building Summary & Conclusions Erin E. Hess Construction Management Senior Thesis Project Minitab Headquarters Presentation Outline

3 Project Description Headquarters for Minitab, Inc.
Developer of data analysis software Location: State College, PA Construction: June 2001 – December 2002 Size: Site acres Facility 88,000 SF Cost: $ 14 Million Erin E. Hess Construction Management Senior Thesis Project Minitab Headquarters Project Description

4 Architecture Four Story Exposed Basement
Full four-story atrium with glass elevators, pond, and waterfall 209 offices, 18 conference rooms, theater, exercise area with locker rooms, game room Erin E. Hess Construction Management Senior Thesis Project Minitab Headquarters Project Description

5 Contractor Selection CM Proposal Alexander chosen based on
Qualified Team Local Company Project Team Erin E. Hess Construction Management Senior Thesis Project Minitab Headquarters Project Description

6 Thesis Project Goals Project Description Maintain clean
architectural appearance Maintain superior energy efficiency Complete construction by November 2002 Erin E. Hess Construction Management Senior Thesis Project Minitab Headquarters Project Description

7 Presentation Outline Project Description Cladding System
Mechanical System Green Building Summary & Conclusions Erin E. Hess Construction Management Senior Thesis Project Minitab Headquarters Presentation Outline

8 Existing Cladding System
Exterior Insulation Finish System (EIFS) Prefabricated, panelized system Four foot, seamless mullion ribbon windows Glass fiber reinforced panels Prefabricated EIFS panels Ribbon windows GFRC panels Rear entrance constructed & finished on-site Erin E. Hess Construction Management Senior Thesis Project Minitab Headquarters Project Description

9 Cladding System Desired Appearance Economic Performance
Clean lines Economic Performance Energy efficient, maintain R-20 Life Cycle Cost Installation Maintenance & Repair Energy Savings Inflation Erin E. Hess Construction Management Senior Thesis Project Minitab Headquarters Cladding System

10 Precast Concrete Panel
Maintain Architectural Appearance Variety of finishes and colors Thermal Efficiency Add rigid insulation to precast assembly Maintenance Durable Cost efficient Resistant to moisture. Photo courtesy Tindall Corporation: Houston Co. Spec., Perry, GA Erin E. Hess Construction Management Senior Thesis Project Minitab Headquarters Cladding System

11 Life Cycle Cost Analysis
Thirty year study period Exterior façade area 23,000 SF Maintain insulation value of R-20 ASTM Standard Practice for Measuring Life Cycle Costs of Buildings and Building Systems Erin E. Hess Construction Management Senior Thesis Project Minitab Headquarters Cladding System

12 EIFS Installation Cost
Exterior Insulation and Finish System (EIFS, Class PB) Cost per square foot Fiberglass batt insulation, 6 in. thick, 15 in. wide $0.60 EIFS Framing, 6 in. metal 16” o.c. Cement board sheathing, ¾ in. 4” Expanded polystyrene insulation board (EPS) EIFS base coat Reinforcing mesh Finish coat $15.75 Total unadjusted present value cost = $16.35 Total Installation Cost = $376,050 Location Adjustment (State College, PA) = 95.4 percent = $358,752 Time Adjustment (July 2001) = 96.1 percent = $344,761 TOTAL INSTALLATION COST = Erin E. Hess Construction Management Senior Thesis Project Minitab Headquarters Cladding System

13 Precast Installation Cost
Precast Concrete Cost per square foot Metal studs, non-loadbearing 16” o.c. $0.85 Fiberglass batt insulation, 6 in. thick, 15 in. wide $0.60 Flat precast concrete panel Thickness – 6 in. thick Panel size (ft) – 6 x 18 Finish – smooth gray Rigid insulation – 2 in. Type – low rise $10.45 Add’l 2 in. rigid insulation* $0.73 Total unadjusted present value cost = $12.63 Total Installation Cost = $300,370 Location Adjustment (State College, PA) = 95.4 percent = $286,553 Time Adjustment (July 2001) = 96.1 percent = $275,377 TOTAL INSTALLATION COST = Erin E. Hess Construction Management Senior Thesis Project Minitab Headquarters Cladding System

14 Projected Life Cycle Cost (Present Value Dollars)
Projected Maintenance Costs Projected Life Cycle Cost (Present Value Dollars) Cladding and Structural Framing Assembly Estimated Installation & Maintenance Costs (Year) Total Life Cycle Cost 15 20 25 30 EIFS (Class PB) cash outflow (initial costs and maintenance) 344,761 7,318 11,119 $ 363,198 Precast Concrete 275,377 22,079 6,183 $ 303,639 Erin E. Hess Construction Management Senior Thesis Project Minitab Headquarters Cladding System

15 Life Cycle Cost Installation Maintenance Total Life Cycle Cost
EIFS - $344,761 Precast - $275,377 Maintenance EIFS - $18,437 Precast - $28,262 Total Life Cycle Cost EIFS - $363,198 Precast - $303,639 Erin E. Hess Construction Management Senior Thesis Project Minitab Headquarters Cladding System

16 Structural Impact Typical Structural Frame Panel Size
Bays 24’-0” x 19’-9”/19’-5” Panel Size 24’-0” x 7’-3” Cladding Assembly Panel Size Weight (per Panel) EIFS Panel 4 in. EPS insulation Heavyweight reinforcing mesh 20 ga., 6 in. metal 16” o.c. 24’-0” x 7’-3” 581 lbs. Precast Panel 6 in. lightweight concrete (50 pcf) 4,408 lbs. Erin E. Hess Construction Management Senior Thesis Project Minitab Headquarters Cladding System

17 Structural Impact Calculation of Additional Loading
Tributary area = 242 SF Erin E. Hess Construction Management Senior Thesis Project Minitab Headquarters Cladding System

18 Structural Impact Cladding System EIFS (lbs) PRECAST ROOF Dead Load
588.8 Live Load 26,620.0 THIRD/SECOND/ FIRST FLOORS 38,007.0 49,448.0 50,820.0 TOTAL LOADS 38,596.0 50,077.0 77,440.0 DESIGN LOAD: 1.2 DL LL 170,219 183,996 Erin E. Hess Construction Management Senior Thesis Project Minitab Headquarters Cladding System

19 Structural Impact Design Load Increase Original Perimeter Columns
13,777 pounds per bay; 8% increase Original Perimeter Columns W12X45 Design Load Capacity = 350 kips Resized Perimeter Columns W12X50 Design Load Capacity = 393 kips; 12.3% increase Increased Steel 30 Perimeter columns, each 38 ft. in length Increase of 5 plf = 2.85 tons => $4,047. Erin E. Hess Construction Management Senior Thesis Project Minitab Headquarters Cladding System

20 Schedule Analysis EIFS – Fork lift Cladding System
Panelized EIFS Installation Detail ACTIVITY DURATION 1. Attached panel to fork lift rigging. 10 min. 2. Maneuver forklift to panel installation location. 5 min. 3. Align panel with pre-installed steel angle attachments. 15 min. 4. Level and attach panel to structural steel frame. 30 min. TOTAL EIFS PANEL INSTALLATION DURATION (per panel): 1 hour TOTAL ACTIVITY DURATION: 9 DAYS Erin E. Hess Construction Management Senior Thesis Project Minitab Headquarters Cladding System

21 Schedule Analysis Precast – Crane Cladding System
Precast Panel Installation Detail ACTIVITY DURATION 1. Attached panel to crane rigging. 15 min. 2. Maneuver panel to installation location. 30 min. 3. Align panel with pre-installed steel angle attachments. 4. Level and attach panel to structural steel frame. 60 min. TOTAL EIFS PANEL INSTALLATION DURATION (per panel): 2.25 hours TOTAL ACTIVITY DURATION: 19 DAYS Erin E. Hess Construction Management Senior Thesis Project Minitab Headquarters Cladding System

22 Cladding System Summary
Use of Precast Concrete Panel System First Cost Savings = $69,384 30-year Life Cycle Cost Savings = $59,559 Increased Structural Steel = $4,047 Overall Cost Savings $55,512 16% savings on exterior cladding budget 0.5% savings on project estimated cost Increased project schedule 10 days Erin E. Hess Construction Management Senior Thesis Project Minitab Headquarters Cladding System

23 Presentation Outline Project Description Cladding System
Mechanical System Green Building Summary & Conclusions Erin E. Hess Construction Management Senior Thesis Project Minitab Headquarters Presentation Outline

24 Original Mechanical System
Dedicated outdoor air system with parallel radiant panel system Ventilation system – temperature control, air quality, and latent (moisture) load Radiant panels address remainder of sensible load (temperature) Erin E. Hess Construction Management Senior Thesis Project Minitab Headquarters Project Description

25 Mechanical System Redesign
Original Design Estimated Cost = $1,500,000 Did not consider structural effects of locating boiler and chiller on roof – additional $200,000. Revised Estimated Cost = $1,700,000 Redesign 100% Outdoor air – geothermal system Erin E. Hess Construction Management Senior Thesis Project Minitab Headquarters Mechanical System

26 Mechanical System 100% Outdoor Air – Geothermal System
Energy-efficient Environmentally clean Cost effective Minitab Geothermal System 40,000 lf of pipe – ft. each 278 high-efficiency heat pumps Air to air heat recovery system Erin E. Hess Construction Management Senior Thesis Project Minitab Headquarters Mechanical System

27 Geothermal System Individual heat pumps for each space above the ceiling in the corridor. Geothermal Well Field Erin E. Hess Construction Management Senior Thesis Project Minitab Headquarters Mechanical System

28 Geothermal System Maintain energy efficiency
Maintain indoor air quality Maintain service load requirements Eliminate structural and architectural redesign Cost Savings = $200,000 Erin E. Hess Construction Management Senior Thesis Project Minitab Headquarters Mechanical System

29 Presentation Outline Project Description Cladding System
Mechanical System Green Building Summary & Conclusions Erin E. Hess Construction Management Senior Thesis Project Minitab Headquarters Presentation Outline

30 Green Building Atmosphere conducive to:
“We hire the best people and then provide them with an environment that enables them to do their best work.” Atmosphere conducive to: Employee health Quality of life Productivity Erin E. Hess Construction Management Senior Thesis Project Minitab Headquarters Green Building

31 Benefits of a Green Building
Energy Efficient Advanced Technology Indoor Air Quality Minimize Waste Thermal Comfort Resource Efficiency Minimize waste: excavated material is crushed for use as backfill and parking lot base Erin E. Hess Construction Management Senior Thesis Project Minitab Headquarters Green Building

32 LEED™ Certification Two leading categories of LEED™ rated buildings
Owner Type – Profit Organization Building Type – Commercial Office Minitab is environmentally conscious Public respect Employee morale Erin E. Hess Construction Management Senior Thesis Project Minitab Headquarters Green Building

33 LEED™ Certification Points required for LEED™ Certification 26 – 32
Category Total Possible Points Minitab 1. Sustainable Sites 14 3 2. Water Efficiency 5 4 3. Energy and Atmosphere 17 2-11 4. Materials and Resources 13 2 5. Indoor Environmental Quality 15 9 6. LEED Innovation Credits 1-4 TOTAL: 69 22-33 Points required for LEED™ Certification 26 – 32 Erin E. Hess Construction Management Senior Thesis Project Minitab Headquarters Green Building

34 Green Building Associated Benefits
Significant gains in worker health Improved satisfaction Increased productivity Higher profits Decreased employee turnover Added value to corporation and building. Erin E. Hess Construction Management Senior Thesis Project Minitab Headquarters Green Building

35 Presentation Outline Project Description Cladding System
Mechanical System Green Building Summary & Conclusions Erin E. Hess Construction Management Senior Thesis Project Minitab Headquarters Presentation Outline

36 Summary & Conclusions Precast Panel Cladding Alternative
Maintain Clean Appearance Maintain Energy Efficiency Increase Schedule by 10 days Overall Savings $55,512 15 % Geothermal Heat Pump Alternative Eliminate Design Conflicts No Effect First Cost Savings $200,000 12 % LEED™ Certification Improved Building Function Added value to corporation and building Erin E. Hess Construction Management Senior Thesis Project Minitab Headquarters Summary & Conclusions

37 Acknowledgements AE Faculty AE Classmates Family & Friends
Alexander Constructors, Inc. Minitab, Inc. Erin E. Hess Construction Management Senior Thesis Project Minitab Headquarters Acknowledgements

38 Questions Questions Erin E. Hess Construction Management
Senior Thesis Project Minitab Headquarters Questions

39


Download ppt "Construction Management"

Similar presentations


Ads by Google