MEP201 Mechanical Engineering Drawing 1 st semester 2005-2006 S R Kale Lecture Piping Drawings
2
Piping (2005)2 Piping drawings Pre-requisites Schematic, P&I drawings Equipment G.A. drawings Layout drawings Restrictions Space (X, Y, Z), movement Piping outputs B.O.M. for piping fabricator Hangers, anchors/foundations, trenches
3
Piping (2005)3 Francis Turbine – Lube Oil Piping (1) L.O. TANK BRG L.O. TANK BEARING Z X Y SCHEMATIC
4
Piping (2005)4 Information Requirements Position of each equipment (L.O. tank, Bearing block, pump : floor plans, elevations) G.A. drawing of each equipment (type, size & position of piping connections) Civil requirements (beams & columns, walkway, maintenance) Electrical requirements (panels, cable trenches) Other pipes in the area
5
Piping (2005)5 Piping Joints Threaded Accuracy (?), Metal/plastic. Plumbing Flanged Industrial pipes, low/medium pressure and temperature. Metal/Plastic. Steam, oil, water, Welded Permanent; High pressure and temperature. Industrial, Water, steam, oil, chemicals, Water supply, sewage, large hydro - Concrete
6
Piping (2005)6 Piping Joints Threaded / Flanged / Welded
7
Piping (2005)7 Piping Joints Threaded / Flanged / Welded
8
Piping (2005)8 Pipe - Flanged connection PIPE-FLANGE WELDED or SCREWED PIPE 2 PIPE 1 FLANGE 1FLANGE 2 GASKET BOLT-NUT
9
Piping (2005)9 Pipe - Flanged connection
10
Piping (2005)10 Piping Joints Threaded / Flanged / Welded
11
Piping (2005)11 Piping Joints
12
Piping (2005)12 Piping Bends Tee (T)Short Radius (SR) Elbow Long Radius (SR) Elbow Radius/Pipe dia. ratio Hydrodynamics. Space.
13
Piping (2005)13 Piping : Vents, Drains & Supports Vents : Location, accessibility, outlet Drains : Location, accessibility, collection, funnel, Supports : Anchor/foundation, hanger Thermal expansion Pipe weight Surges, water hammer Equipment vibrations Seismic
14
Piping (2005)14 Francis Turbine – Lube Oil Piping (2) L.O. TANK BEARING
15
Piping (2005)15 Piping – Plan & Elevation (1) ISOMETRIC PLAN ELEVATION
16
Piping (2005)16 Piping – Plan & Elevation (2) ISOMETRIC PLAN ELEVATION
17
Piping (2005)17 Piping – Plan & Elevation (3) ISOMETRIC PLAN ELEVATION
18
Piping (2005)18 Pipe supports Foundation Hanger Rack Clamp Underground – foundation “Rigid” - anchor vs. “flexible” allows pipe to move All along pipe length (at regular intervals?)
19
Piping (2005)19 Pipe support - Hanger
20
Piping (2005)20 Piping Examples Oil pumping station, Central A.C. system,
21
Piping (2005)21 Piping – How things go wrong Power plant steam turbine – steam pipe under lube oil pipe. Hostel – drinking water pipe and sewage pipe too close. Automobile – brake oil leak on alternator. Pipes running into beams, columns, walls, … Pipe centerline O.K. (?) but insulation fouls with walls/ceiling.
22
Piping (2005)22 Lecture summary Using schematics/P&I diagrams make piping drawings (routing), to scale, with material and other specifications (e.g. standards) NEXT STEP : Piece-wise design and manufacture of pipes, joining details, and their supports,