MEDACTHU PROGRAM 28 September 2007 EPA Thessalia Emergency and Readiness Procedures.

Similar presentations


Presentation on theme: "MEDACTHU PROGRAM 28 September 2007 EPA Thessalia Emergency and Readiness Procedures."— Presentation transcript:

1 MEDACTHU PROGRAM 28 September 2007 EPA Thessalia Emergency and Readiness Procedures

2 EPA THESSALIA GAS DISTRIBUTION SYSTEM

3 GAS DISTRIBUTION SYSTEM DATA  EPA MANAGES THE MEDIUM AND LOW PRESSURE GAS DISTRIBUTION NETWORK (MPDS, LPDS) IN THE URBAN AREA OF LARISSA AND GHIANULI MUNICIPALITIES AND IN THE AREA OF VOLOS  EPA MANAGES THE MEDIUM AND LOW PRESSURE GAS DISTRIBUTION NETWORK IN THE INDUSTRIAL AREAS (VIPE) OF LARISSA AND VOLOS

4  DESIGN PRESSURE: 19 BAR  SERVICE PRESSURE: 16 BAR  TYPE OF DISTRIBUTION: PIPELINES  PIPELINE MATERIAL: STEEL  PIPE INSTALLATION: BURIED PIPES  LENGTH: ~86 KM  DIAMETER: VARIES FROM 14’’ TO 2’’ MEDIUM PRESSURE DATA

5  GAS SUPPLIER: DESFA  GAS DELIVERY STATIONS (CITYGATES): 2 NORTH LARISSA CITYGATE LOCATION: NEW NATIONAL ROAD, SYKOYRIO JOINT SOUTH LARISSA CITYGATE LOCATION: BY NEW NATIONAL ROAD, NEAR PLATYKAMPOS JOINT  OPERATIONS AT CITYGATES PROVIDED BY DESFA PRESSURE REDUCTION AND REGULATION SERVICES OVERALL QUANTITY AND ENERGY METERING ODORIZATION MEDIUM PRESSURE DATA in LARISSA

6  GAS SUPPLIER: DESFA  GAS DELIVERY STATIONS (CITYGATES): 2 VOLOS A’ INDUSTRIAL ESTATE (A VIPE) CITYGATE LOCATION: A VIPE VOLOS, 3 RD ROAD KOKKINA VILLAGE DESFA LINE VALVE CITYGATE FROM WHICH STARTS A 28 KM 8“ BRANCH TO SOVEL  OPERATIONS AT CITYGATES PROVIDED BY DESFA SERVICE PRESSURE REDUCTION AND REGULATION OVERALL QUANTITY AND ENERGY METERING ODORIZATION MEDIUM PRESSURE DATA VOLOS & SOVEL (ALMYROS)

7  PRESSURE REDUCTION: 19/4 BAR  NOMINAL CAPACITY: 5000 Nm3/h  TYPE: 2 LINES  INSTALLATION: ABOVE GROUND FENCED IN PUBLIC AREAS  NUMBER OF IRI: 4 (SERVING LARISSA- GHIANULI), 2 (SERVING INDUSTRIAL AREA) IRI STATIONS LARISSA AREA

8  PRESSURE REDUCTION: 19/4 BAR  NOMINAL CAPACITY: 5000 Nm3/h  TYPE: 2 LINES  INSTALLATION: ABOVE GROUND FENCED IN PUBLIC AREAS  NUMBER OF IRI: 4 (SERVING VOLOS-NEA IONIA COUNCILS), 1 (SERVING A’ INDUSTRIAL ESTATE – A’ VIPE), 1 (SERVING B’ INDUSTRIAL ESTATE – VIPE VELESTINO), 1 (SERVING AGRIA COUNCIL) IRI STATIONS VOLOS AREA

9  DESIGN PRESSURE: 4 BAR  SERVICE PRESSURE: 3 BAR  PIPELINE MATERIAL: HIGH DENSITY POLYETHYLENE  PIPE INSTALLATION: BURIED PIPES  LENGTH: ~490 KM  DIAMETER: VARIES FROM Φ160 TO Φ63  NETWORK TOPOLOGY: LOOPED (Φ125) WITH OPEN BRANCH EXTENSIONS (Φ125/Φ63) DERIVED FROM LOOP FOR SATURATION  LPDS DEVELOPMENT URBAN AREA OF LARISSA DIVIDED INTO THREE OPERATING SECTOR (OS) EACH ONE COVERED BY A MAJOR LOOP AND SATURATED BY OPEN BRANCHES EACH OS SUPPLIED BY ONE OR MORE IRI LP DISTRIBUTION SYSTEM

10  THE LOW PRESSURE DISTRIBUTION NETWORK SERVES: ~ 20300 CLIENTS IN GAS IN LARISSA AND VOLOS AREAS 20 INDUSTRIAL CLIENTS  CLIENTS ARE SERVED VIA 5.500 SERVICE LINES DERIVED FROM THE LOW PRESSURE DISTRIBUTION NETWORK  26 EPA INDUSTRIAL CLIENTS ARE SERVED FROM THE MEDIUM PRESSURE DISTRIBUTION NETWORK (4 IN LARISSA AREA) CLIENTS IN GAS

11 MEDIUM PRESSURE P&ID LARISSA

12 MEDIUM PRESSURE P&ID VOLOS/NEA IONIA

13 EPA THESSALIA OPERATING PROCEDURES

14 PROCEDURES EPA Procedures N° 011 and 012 According to the Natural Gas Distribution Licence EPA Thessalia has to guarantee:  Operation and Maintenance of the whole network  Readiness Management  Crisis Management

15  Safety of the population  Safety of the involved employees  Secure operation of the gas distribution system  Continuity of gas distribution service  Compliance to regulations: - Gas Distribution License - National Technical Regulation: Operation and Maintenance Manual PROCEDURES REQUIREMENTS TO BE FULFILLED

16 READINESS PROCEDURE PRO 011 and operational instruction 013 Applied in case of anomaly or accident in the gas network or in the internal installation of the Client CALL CENTER SCADA THIRDS  Head of Readiness  Operating Technical Head (2 º )  Squad Head (1 º)  Technician(1 º)  External Contractor Intervention by 2 h for 90% of calls and 4h for 10%

17  EPA RUNS A READINESS SERVICE DURING WORKING AND NON WORKING HOURS (24 H A DAY, 365 D A YEAR) ACCORDING TO INTERNAL PROCEDURES 011 AND 013  DURING WORKING HOURS THE OPERATING READINESS IS GUARANTEED BY THE HEAD OF READINESS, THE OPERATING TECHNICAL HEAD, THE SQUAD HEAD AND TECHNICIAN. ALL PEOPLE ARE ON OPERATING READINESS WHILE CARRYING OUT NORMAL MAINTENANCE DUTIES ACCORDING TO THE SCHEDULE  AFTER THE WORKING HOURS THERE ARE TWO LEVELS OF AVAILABILITY: - 1° LEVEL: Squad Head and Technician - 2° LEVEL: Operating technical head READINESS PROCEDURE CONT’D

18 READINESS MANAGEMENT THE READINESS SQUAD HEAD IS CONTACTED BY THE CALL CENTER ABOUT GAS INCIDENTS OCCURING AT THE EPA RESPONSIBILITY ZONE THE SQUAD HEAD MANAGES THE READINESS SQUAD DECIDING THE RESOURCES TO UTILISE FOR RESOLVING THE SITUATION AN EXTERNAL CONTRACTOR WITH ADEQUATE PERSONNEL AND EQUIPMENT IS ALSO ON READINESS WITH DUTIES REGULATED BY A CONTRACT WITH EPA CONTRACTOR IS ORDERED BY THE SQUAD HEAD, AFTER JUDGEMENT OF THE INCIDENT, TO INTERVENE IN MAXIMUM TWO HOURS TIME FROM THE ANNOUNCEMENT THE OPERATING TECHNICAL HEAD IS CALLED BY THE SQUAD HEAD IN CASE OF DIFFICULT INTERVENTION OR PRESENCE OF PUBLIC AUTHORITIES THE OPERATING TECHNICAL HEAD INFORMS THE COMPANY’S UPPER LEVEL MANAGEMENT IF THE INCIDENT IS JUDGED TO HAVE CHARACTERISTICS OF AN EMERGENCY OR CRISIS

19 EPA THESSALIA EMERGENCY PROCEDURE

20 The results on gas distribution system may be: Unscheduled out of operation of City Gates or IRS Unscheduled out of operation of Medium Pressure and Low Pressure network with gas supply interruption for one or more final clients Gas supply interruption to one or more final clients following a gas leakage Pressure excess or shortage in the network Gas supply interruption to at least 250 final Clients and for which the gas is not supplied for more than 24 hours. Pro. 012: CRISIS MANAGEMENT FOR THE GAS DISTRIBUTION SYSTEM EMERGENCY: EVENT ABLE TO PRODUCE SERIOUS AND/OR LARGE SCALE EFFECTS ON GAS DISTRIBUTION SYSTEM

21 ATTACHED: I.TERRITORIAL EMERGENCY PLAN for  EPA THESSALONIKIS  EPA THESSALIAS II.GENERAL EMERGENCY PLAN III.JOURNAL OF EMERGENCY MANAGEMENT ACTIVITIES Pro. 012: CRISIS MANAGEMENT FOR THE GAS DISTRIBUTION SYSTEM

22 EMERGENCY MANAGEMENT NOTIFICATION OF ANOMALIES IN THE DISTRIBUTION NETWORK EVALUATION OF THE ANOMALIES or INNEFICIENCIES EMERGENCY MANAGEMENT FINAL ANALYSIS CONTROL AND MONITORING REPORTING

23 NOTICE OF ANOMALIES CALL CENTER MAY BE INFORMED ABOUT AN ANOMALY BY:  THIRDS  SAFETY BOARDS SUCH AS FIRE FIGHTING BRIGADE, POLICE ETC.  ALARMS FROM REMOTE CONTROL SYSTEM  EPA PERSONNEL THE CALL CENTER OPERATES ACCORDING TO THE PROCEDURE 011 READINESS MANAGEMENT

24 EVALUATION OF ANOMALIES  THE READINESS HEAD OR THE OPERATING TECHNICAL HEAD INFORM THE HEAD OF TECHNICAL DEPARTMENT ABOUT A LARGE SCALE OR OUTSTANDING ANOMALY  THE HEAD OF TECHNICAL DEPARTMENT EVALUATES THE EVENTS AND ANNOUNCES THE EMERGENCY TAKING CHARGE OF THE OPERATIONS  IN CASE OF GENERAL EMERGENCY (PUBLIC AUTHORITIES AND BOARD INVOLVED, MEDIA ETC.) EPA GENERAL MANAGER ANNOUNCES AND TAKE CHARGE OF GENERAL EMERGENCY

25 EMERGENCY MANAGEMENT  COORDINATES THE EMERGENCY STRUCTURE (INCLUDING MAINLY ALL TECHNICAL PERSONNEL)  IN CASE OF GENERAL EMERGENCY IS ACTIVATED ALSO THE EMERGENCY STEERING COMMITTEE (INCLUDING ALL UPPER LEVEL MANAGEMENT OF EPA)  INFORMS AND GET INVOLVED AUTHORITIES AND SAFETY BOARDS IF REQUIRED. IN THIS CASE IS SUPPORTED BY “COIME” AND “LEGAL” DEPARTMENT  INFORMS COMMERCIAL DEPARTMENT IF IT’S NECESSARY TO INTERRUPT THE GAS SUPPLY TO SOME CUSTOMERS ACTIONS PROVIDED BY THE HEAD OF EMERGENCY

26 EMERGENCY MANAGEMENT CONT’D  KEEP THE CALL CENTER UPDATED ABOUT THE EMERGENCY PROGRESS IN ORDER TO GUARANTEE A CONSTANT AND CORRECT INFORMATION TO PEOPLE CALLING  ONCE RESTATED THE SAFETY CONDITIONS AND THE GAS SUPPLY TO ALL FINAL CLIENTS, THE HEAD ANNOUNCES THE END OF THE EMERGENCY  INFORMS ALL PERSONNEL, DEPARTMENTS AND AUTHORITIES INVOLVED DURING THE EMERGENCY  AN EMERGENCY JOURNAL IS FILLED IN TO RECORD ALL ACTIONS ADOPTED. ACTIONS PROVIDED BY THE HEAD OF EMERGENCY

27 FINAL ANALYSIS BY TWO MONTHS FROM THE END “INAU” DEPARTMENT PROVIDES AN ANALYSIS OF THE EMRGENCY CASE  HOW THE INTERNAL STRUCTURE HAS WORKED  HOW THE EXTERNAL CONTRACTORS HAVE WORKED  AVAILABILITY OF DATA AND INFORMATION  AVAILABILITY OF TOOLS AND MATERIALS  COMMUNICATION  RELATIONSHIP WITH AUTHORITIES, MEDIA ETC  EVENTUAL NEEDS FOR IMPROVING THE EMERGENCY PLAN

28 MONITORING AND REPORTING  THE HEAD OF EMERGENCY SENDS TO THE GREEK ENERGY AUTHORITY (RAE) A REPORT FOR EACH EMERGENCY AS REQUIRED BY THE GAS LICENCE  “INAU” MONITORS ALL EMERGENCY ACTIVITIES AND ISSUES EVERY SIX MONTHS A REPORT  AFTER EACH EMERGENCY “INAU” ISSUES A REPORT TO BE PRESENTED TO THE GENERAL MANAGER  ALL TERRITORIAL AND GENERAL EMERGENCY PLANS ARE FILED AND UPDATED BY TECHNICAL DEPARTMENT


Download ppt "MEDACTHU PROGRAM 28 September 2007 EPA Thessalia Emergency and Readiness Procedures."