2 Slide 2 Linear Programming (LP) Relaxation-Based Approximation Variables can take rational values (relax integrality constraints) Efficiently solvable: gives lower bound on optimal IP solution Common technique: –Use structural information from LP solution to find feasible IP solution –Bound quality using LP bound Integrality gap = (best IP solution)/(best LP solution) This technique cannot prove anything better than integrality gap

3 Slide 3 Integer Program (IP) for capacitated network design A simple IP for capacitated network design: Where d(C) is the maximum demand d i for any pair that crosses cut C x e = 1 if edge e is selected

4 Slide 4 Knapsack Cover (KC) Inequalities A C

5 Slide 5 Finding An Approximate Solution Let Set of edges at least half selected by LP Select all these edges –Increases cost (for A) by factor of 2 Now much meet demand D(A) = D - u(A) with rest of edges

6 Slide 6 Finding an Approximate Solutions Sort edge by u e Consider the three cases

7 Slide 7 Finding an Approximate Solution x e = q/p rational r is least common multiple of denominators so rx e integral for all e Make 2rx e “copies” of x e (convex multipliers will be 1/r)

8 Slide 8 Approximate solution for knapsack (gap 2) 2rx e copies of edge e, sorted by capacity Place in r buckets, round robin Each bucket will be a solution S i No edge in any solution twice e1e1 e1e1 e1e1 e1e1 e1e1 e1e1 e2e2 e2e2 e2e2 e2e2 e3e3 e3e3

9 Slide 9 All buckets are Feasible First Bucket (biggest) Last Bucket (smallest) e k4 e k2 e1 e k3 e k1 < <

10 Slide 10 All Buckets Feasible Suppose We have So for all buckets From total capacity: Contradicts KC inequality

11 Slide 11 Separation Only have to satisfy KC inequality for Add these cuts if violated till we get an LP solution where KC inequality holds for it’s A.

12 Slide 12 Polynomial Time Really only m+1 distinct solutions e1e1 e1e1 e1e1 e1e1 e1e1 e1e1 e2e2 e2e2 e2e2 e2e2 e3e3 e3e3

13 Slide 13 A Scheduling Example Given n jobs J 1, J 2, …, J n Job J i has length p i, weight w i Precedence constraints: mean J i must finish before J j starts No preemption, one machine C j = completion time of job J j Goal: minimize NP-complete. We’ll get a 4-approximation

14 Slide 14 Integer Programming Formulation Subject to

15 Slide 15 Constraint: One Job at a Time Consider all (job, finish time) pairs that would run over (t-1, t] t t+1 t+2 t+p j -1 t-1 T-p j... t-1

16 Slide 16 Precedence Constraints If job J k finishes by time t + p k, then job J j must finish by time t

17 Slide 17 LP relaxation, Fractional Schedule x jt pjpj

18 Slide 18 Fractional Schedule x* Fractional Completion Time: Midpoint: min t* such that

19 Slide 19 Approximation Algorithm Solve LP Compute midpoints for all jobs Order by midpoints

20 Slide 20 Approximate Schedule is feasible No preemption One job at a time Precedence constraints Midpoint of J j < Midpoint of J k

21 Slide 21 Proof of Quality Road Map Relate C j to LP values Renumber jobs by midpoint: We’ll show

22 Slide 22 Upper Bound on Completion Times At time t j * fractional schedule has done p j /2 work. Since t k *  t j * for k<j, schedule has done p k /2 work on J k. One unit of work/time unit  But by construction t-p j t x jt

23 Slide 23 Lower Bound on LP values By definition: So

24 Slide 24 Proof of Quality Therefore

25 Slide 25 Comments Can create alternative schedules using  point t j  LP-based approximation algorithms can give feasible solutions in branch and bound Other LP-based approximation algorithms for scheduling problems are based on matching/assignment