Presentation is loading. Please wait.

Presentation is loading. Please wait.

PROJECT MANAGEMENT PART SIX Chapter Eighteen Project Management.

Similar presentations


Presentation on theme: "PROJECT MANAGEMENT PART SIX Chapter Eighteen Project Management."— Presentation transcript:

1 PROJECT MANAGEMENT PART SIX Chapter Eighteen Project Management

2 Unique, one-time operations designed to accomplish a specific set of objectives in a limited time frame. Build A A Done Build B B Done Build C C Done Build D Ship JANFEBMARAPRMAYJUN On time! Projects

3 Deciding which projects to implement Selecting a project manager Selecting a project team Planning and designing the project Managing and controlling project resources Deciding if and when a project should be terminated Key Decisions

4 Project Manager Responsible for: WorkQuality Human ResourcesTime CommunicationsCosts

5 Temptation to understate costs Withhold information Misleading status reports Falsifying records Comprising workers’ safety Approving substandard work Ethical Issues

6 Project Life Cycle Concept Feasibility Planning Execution Termination Management

7 Risk: occurrence of events that have undesirable consequences –Delays –Increased costs –Inability to meet specifications –Project termination Project Risk

8 Identify potential risks Analyze and assess risks Work to minimize occurrence of risk Establish contingency plans Risk Management

9 Work Breakdown Structure Project X Level 1 Level 2 Level 3 Level 4 Figure 18-3

10 MARAPRMAYJUNJULAUGSEPOCTNOVDEC Locate new facilities Interview staff Hire and train staff Select and order furniture Remodel and install phones Move in/startup Planning and Scheduling Gantt Chart

11 PERT and CPM PERT: Program Evaluation and Review Technique CPM: Critical Path Method Graphically displays project activities Estimates how long the project will take Indicates most critical activities Show where delays will not affect project

12 Project Network – Activity on Arrow 1 2 3 4 56 Locate facilities Order furniture Furniture setup Interview Hire and train Remodel Move in

13 Project Network – Activity on Node 1 2 3 5 6 Locate facilities Order furniture Furniture setup Interview Remodel Move in 4 Hire and train 7S

14 Network Conventions a b ca b c a b c d a b c Dummy activity

15 Example 1 1 2 3 4 56 8 weeks 6 weeks 3 weeks 4 weeks 9 weeks 11 weeks 1 week Locate facilities Order furniture Furniture setup Interview Hire and train Remodel Move in

16 Example 1 Solution Critical Path

17 Network activities –ES: early start –EF: early finish –LS: late start –LF: late finish Used to determine –Expected project duration –Slack time –Critical path Computing Algorithm

18 Probabilistic Estimates Activity start Optimistic time Most likely time (mode) Pessimistic time opmtete Figure 18-8

19 Example 5 1-3-4 a 3-4-5 d 3-5-7 e 5-7-9 f 2-4-6 b 4-6-8 h 2-3-6 g 3-4-6 i 2-3-5 c Optimistic time Most likely time Pessimistic time

20 17 Weeks 10.0 16.0 13.5 1.00 a-b-c d-e-f g-h-i Example 6

21 Computer aided design (CAD) Groupware (Lotus Notes) Project management software –CA Super Project –Harvard Total Manager –MS Project –Sure Track Project Manager –Time Line Technology

22 Imposes a methodology Provides logical planning structure Enhances team communication Flag constraint violations Automatic report formats Multiple levels of reports Enables what-if scenarios Generates various chart types Advantages of PM Software

23 A project consists of 10 activities, lettered A through J, as shown in the accompanying precedence diagram, with the activities on the arrows. For each activity, the deterministic time estimate in weeks is shown in the following table. Advantages of PM Software

24 A project consists of 10 activities, lettered A through J, as shown in the accompanying precedence diagram, with the activities on the arrows. For each activity, the deterministic time estimate in weeks is shown in the following table. Activity Time Activity Time ABCDE 24356 FGHIJ 34431 List all of the paths through the network. What is the duration of each of the paths? What is the critical path? What is the second-most critical path? What is the slack time for each activity? Calculate the ES, Ef, LS and LF times for each activity. Advantages of PM Software

25 Time-Cost Trade-Offs: Crashing Total cost Shorten Cumulative cost of crashing Expected indirect costs Optimum CRASH Figure 18-11

26 6a6a 4d4d 5c5c 10 b 9e9e 2f2f Example 7

27 Advantages of PERT Forces managers to organize Provides graphic display of activities Identifies –Critical activities –Slack activities 1 2 3 4 56

28 Limitations of PERT Important activities may be omitted Precedence relationships may not be correct Estimates may include a fudge factor 1 2 3 4 56 142 weeks


Download ppt "PROJECT MANAGEMENT PART SIX Chapter Eighteen Project Management."

Similar presentations


Ads by Google