Presentation is loading. Please wait.

Presentation is loading. Please wait.

Run II Status and Prospects - Spalding1 Run II Status and Prospects Jeff Spalding Fermilab June 14, 2004.

Similar presentations


Presentation on theme: "Run II Status and Prospects - Spalding1 Run II Status and Prospects Jeff Spalding Fermilab June 14, 2004."— Presentation transcript:

1 Run II Status and Prospects - Spalding1 Run II Status and Prospects Jeff Spalding Fermilab June 14, 2004

2 Run II Status and Prospects - Spalding2 Contents  Introduction  Major elements of the Run II “campaign”  Present performance  Status of the upgrade projects  Luminosity projection  Summary

3 Run II Status and Prospects - Spalding3 Run II goal: maximize integrated luminosity delivered to CDF & D0 …

4 Run II Status and Prospects - Spalding4 … with a program of upgrades throughout the complex Recycler Ring

5 Run II Status and Prospects - Spalding5 Basis for the Plan: What drives the luminosity  Peak Luminosity  Luminosity lifetime (tunes, beam-beam interactions)  Reliable Operation  p,  pbar, form factor F,  * provide some gains But major improvements from bunch intensities  especially total number of pbars BN pbar, (B=36 bunches for Run II)  proton brightness (N p /  p ) is constrained by beam-beam tune shift

6 Run II Status and Prospects - Spalding6 Major Elements of the Run II Campaign

7 Run II Status and Prospects - Spalding7 Operational improvements and upgrade projects Near Term (and ongoing)  Improved reliability and operating efficiency  Failure modes, abort system improvements…  Tevatron alignment  Improved instrumentation throughout the complex  Optimization of transfers, improved optics and helices in Tevatron Upgrade Projects  Increase pbar production  Slip stacking  Pbar acceptance upgrade  Stacking rate and stack size (stacktail, Recycler, e-cooling)  Upgrade Tevatron for higher bunch intensities  Helix  TEL: active beam-beam compensation

8 Run II Status and Prospects - Spalding8 Reliability  The number of store hours per week is up 27% from FY03 - the TEV is a more reliable machine.  Typical store length 15 hrs last year  >24 hrs now  Due to:  Alignment of the TEV Dipole un-rolls, Low Beta alignment, Smart bolt retrofit  Reliability strategy Aggressively pursue equipment failures –Individual components and Systems (e.g. TEV abort system)  Operations strategy With improved reliability  run long stores –More time to ensure large stack size –Minimize the effects of store turnaround time –Minimize impact of parasitic studies Short focused dedicated studies –Configuration control

9 Run II Status and Prospects - Spalding9 Dynamic plan – adjust the strategy when new information from operations and project R&D Major Elements  Increase number of protons on the pbar production target  Slip stacking (5E12  >8E12 protons on pbar target)  Upgrade the target itself to handle higher intensity  Increase antiproton collection  Increase the gradient of the antiproton collection lens  Increase the aperture of the antiproton collection transfer line (AP2) and the Debuncher ring.  Increase the antiproton stacking and storing capabilities  Increase the flux capability of the Accumulator stacktail stochastic cooling system.  Use the Recycler as a second antiproton storage ring, with both stochastic and electron cooling  Upgrade Tevatron to handle higher intensity bunches.  Improvements to helix separation and smoothness  Active compensation for beam-beam tune shift using the TEL Upgrade Projects

10 Run II Status and Prospects - Spalding10 Status of Operations Run I

11 Run II Status and Prospects - Spalding11 Status: Integrated Luminosity Up 55% with 14% fewer scheduled running weeks Average integrated luminosity per week is up 80% Compare the last 12 months to the year before

12 Run II Status and Prospects - Spalding12 Status: Peak Luminosity Current best = 7.6E31 cm -2 s -1 *

13 Run II Status and Prospects - Spalding13 Summary of Current Operations  Booster running at record intensities  Major improvements in transfer efficiencies and emittances, TEV tunes, optics and helix  Improved reliability and operations allows longer stores  larger stacks  higher luminosity  However, stacking rate is ~75% of current goal – present focus of investigation and improvement for the stacktail and core cooling systems  Near term: introduce mixed-source operation (pbars loaded from both Accumulator and Recycler) – first [pilot] store 6/9/04 successful (6.7E31)  And slip-stacking by end of 04 ( already tested at 75% of design intensity) – awaits completion of RF upgrade

14 Run II Status and Prospects - Spalding14 Status of the Upgrade Projects

15 Run II Status and Prospects - Spalding15 Main Injector  Slip Stacking (goal x1.8ppp on pbar tgt)  Excellent progress  Tested @ 6 x 10 12 and 1.5 nsec bunch length on pbar target  Reliable operation >8 x 10 12 requires RF upgrade (beam-loading compensation)  On track for end of this year.

16 Run II Status and Prospects - Spalding16 Pbar Source Pbar Acceptance (goal: x2)  Lithium Lens (goal x 1.1)  Prototype of new design (higher field gradient) bench test successful  AP2 and Debuncher aperture increase (goal x1.8)  Developed procedures for beam-based identification of limiting apertures, identified components to modify Stacktail cooling upgrade  Cooling system upgrade (extends the bandwith 2-4  2-6 GHz)  Requires the large stack to be in Recycler (with e-cool), and “rapid transfers”  Not [easily] reversible  emphasize a phased approach  Interim upgrade (05) [NEW] Reconfigure existing cooling tanks -quick and reversible Simulated performance ~30E10 per hr  Full upgrade, with new cooling tanks (06) Simulated performance ~40E10 per hr

17 Run II Status and Prospects - Spalding17 Recycler  The Recycler has made excellent progress over the past year  Transverse emittance growth is no longer an issue (vacuum problems solved)  Met the performance specs needed for commissioning electron cooling  Ready to be integrated into operations (with stochastic cooling)  Provides possibility for interim operating phase [NEW]  Extract pbars from both Accumulator and Recycler: “mixed-source”  e.g. 24 bunches from the Accumulator + 12 bunches from the Recycler  A few (2-4) interim transfers from Accumulator to Recycler  Improves average stacking rate in the Accumulator  Reasons  Push Recycler commissioning progress by plunging it into operations  Potential luminosity enhancement – more pbars for smaller emittances Break-even right now, potential for up to 20% gain in the next year  Flexibility in the Run II Upgrade schedule Merge more naturally into commissioning electron cooling

18 Run II Status and Prospects - Spalding18 Electron Cooling  R&D program on e-beam is complete, now moving the setup to the Recycler  R&D scheduled stretched by ~2 months  NOT BAD!  Operational test of the full system successful  All major components, diagnostics and controls developed and tested  Beam properties achieved close to spec (analysis ongoing)  Will add additional Pelletron section at Recycler  reliable operation at 4.3 MeV  Commission e-beam and then pbar cooling in Recycler, parasitic to HEP, then intro e-cooled stacks to HEP (05)  Still R&D (until pbar cooling demonstrated next year), but excellent progress

19 Run II Status and Prospects - Spalding19 Tevatron Major improvements so far  Lifetime at 150 GeV  Larger aperture, alignment and dipole un-rolls  Emittance dilution reduced  De-coupling at TEV injection, optimization of injection optics  Helix improvements  CDF IP  Centered beam in low beta quads (4mm move at CDF), and re- aligned the quadrupoles  New Low Beta Optics  20% increase in luminosity Upgrades  Further alignment improvements in shutdown 04 (and 05)  Add separators and polarity switches in shutdown 04 and 05  improved helices

20 Run II Status and Prospects - Spalding20 Luminosity Projections

21 Run II Status and Prospects - Spalding21 Luminosity Projection  Luminosity model incorporates  Performance parameters from simulation, parametric model and data  Long term operating experience Sustained average store length was 15 hrs (now >24) Sustained average 85 store hrs/week (operating weeks often >>100)  Scheduled shutdowns + turn on & recovery + learning slopes  Expect to do better on some parameters, worse on others  What’s new  The following plots are from Feb04 DOE review Illustrate strategy Updated projection will be similar in scale  We are in the process of updating the projections for: e-cooling and stacktail schedules and strategy Improved reliability (longer stores and stacking) Mixed-source op - assume break even (conservative)

22 Run II Status and Prospects - Spalding22 Design and Base Projections (Feb04 DOE Review) Integrated Luminosity Design Projection - No schedule contingency, maintains eng. design margin per subproject Base Projection - Assumes schedule slip for all subprojects and that all subprojects under perform

23 Run II Status and Prospects - Spalding23 Design and Base Projections (Feb04 DOE Review) We are here Integrated Luminosity per Week

24 Run II Status and Prospects - Spalding24 Risk Analysis / Strategy (Feb04 DOE Review) Our plan is to deliver the Design Projection but develop strategy for fallback scenarios:  Base Projection models schedule slip and under-performance for all upgrades  Can also ask: where would we be  without Recycler & e-cooling?  with e-cooling, but without stacktail upgrade?

25 Run II Status and Prospects - Spalding25 Risk Analysis / Strategy (Feb04 DOE Review)  Design Projection  Electron Cooling  Stacktail Upgrade  Parameters in FY09 Debuncher & AP2 at 32  -mm-mrad Slip Stacking at 8x10 12 ppp Av. Stk Rate = 39x10 10 /hr Stk in Accum = 20x10 10 Stk in Rec’r = 570x10 10  Base Projection  As above with sched & param slip  Parameters in FY09 Debuncher & AP2 at 25  Slip Stacking at 7x10 12 ppp Av. Stk Rate = 24x10 10 /hr Stk in Accum = 24x10 10 Stk in Rec’r = 360x10 10  Black Projection  NO Electron Cooling  NO Stacktail Upgrade  Parameters in FY09 Debuncher & AP2 at 21  Slip Stacking at 7x10 12 Av. Stk Rate = 14x10 10 /hr Stk in Accum = 205x10 10 Stk in Rec’r = 0x10 10  Purple Projection  Electron Cooling  NO Stacktail Upgrade  Parameters in FY09 Debuncher & AP2 at 20  Slip Stacking at 8x10 12 Av. Stk Rate = 23x10 10 /hr Stk in Acum = 58x10 10 Stk in Rec’r = 337x10 10

26 Run II Status and Prospects - Spalding26 Risk Analysis / Strategy (Feb04 DOE Review) with e-cooling, but w/o stacktail upgd without e-cooling & stacktail upgd Branch points from Design Projection Design Black Purple Assumes average store length 15 hrs

27 Run II Status and Prospects - Spalding27 Strategy Changes Design Black Purple mixed-source operation longer stores e-cooling and interim stacktail upgrade will be delayed to fall 2005, full upgrade in 06 interim Stacktail upgrade WARNING: curves not yet updated changes in green to be implemented

28 Run II Status and Prospects - Spalding28 Risk Analysis / Strategy (Feb04 DOE Review) Design Base Black Purple

29 Run II Status and Prospects - Spalding29 Summary  Current performance is above the design projection  80% higher weekly luminosity than a year ago  Major achievements in the last year (Tevatron perf, Recycler…)  There is a complex-wide plan for the Run II campaign  Plan is dynamic: schedule/scope adjustments, mixed-source, capitalize on improved reliability  The upgrade projects are making good technical progress  The plan and progress are formally reviewed by DOE  With the updated plan, expect the design projection to be close to the previous 8.5 fb -1 2009, with fall-back scenarios >4.5 fb -1


Download ppt "Run II Status and Prospects - Spalding1 Run II Status and Prospects Jeff Spalding Fermilab June 14, 2004."

Similar presentations


Ads by Google