1 Material Requirements Planning (MRP)
CHAPTER 13 Material Requirements Planning (MRP)

2 Material Requirements Planning
Master Production Schedule Time-phased plan specifying timing and quantity of production for each end item. Material Requirement Planning Process Product Structure Tree Moderately Firm Frozen Flexible Capacity Forecast and available capacity Lead Times Time fences --available capacity become dedicated over time.

3 Dependent vs Independent Demand
“Lumpy” demand Demand Stable demand Demand Time Time Amount on hand Amount on hand Safety stock Time Time

4 Objectives of MRP MRP answers the following production decision of a firm What is needed? How much is needed? When is it needed?

5 Material decision Decision on
Quantity (how much) Time (when) Type (what) The first two are same as in inventory management. The last one is needed because it involves more than one type of parts or components.

6 MRP Overview MRP Inputs MRP Processing MRP Outputs Changes
Order releases Master schedule Planned-order schedules Primary reports Exception reports Planning reports Performance- control reports Bill of materials file MRP computer programs Secondary reports Inventory records file Inventory transaction

7 Output from an MRP system
Generate a feasible schedule of requirements for subassemblies component parts raw materials required to produce the quantity of items required in the given time frame

8 Planning Horizon 1 2 3 4 5 6 7 8 9 10 Assembly Subassembly Fabrication
Procurement

9 Master Schedule Master schedule: One of three primary inputs in MRP; states which end items are to be produced, when these are needed, and in what quantities. Cumulative lead time: The sum of the lead times that sequential phases of a process require, from ordering of parts or raw materials to completion of final assembly. Time fences: Series of time intervals during which order changes are allowed or restricted.

10 Bill-of-Materials Bill of materials: One of the three primary inputs of MRP; a listing of all of the raw materials, parts, subassemblies, and assemblies needed to produce one unit of a product. Product structure tree: Visual depiction of the requirements in a bill of materials, where all components are listed by levels.

11 BOM Accuracy is important since errors may multiply many times

12 Product Structure Tree
Level Chair Seat Legs (2) Cross bar Side Rails (2) Back Supports (3) Leg Assembly 1 2 3

13 Low Level Coding Level Y 1 A B C D E F E G H 2 E E E 3

14 MRP Processing Gross requirements
Scheduled receipts(orders scheduled to arrive from suppliers at the beginning of the period) Projected on hand Net requirements Planned-order receipts Planned-order releases

15 ) ( MRP Processing - = Net Requirement in period t
Gross Requirement in period t Projected on hand inventory in period t ) ( Safety stock Allowance for waste - = + +

16 Assembly Time Chart 1 2 3 4 5 6 7 8 9 10 11 Final assembly
Procurement of raw material D raw material F part C part H raw material I Fabrication of part G of part E Subassembly A Subassembly B Final assembly and inspection

17 MRP Outputs Planned orders - schedule indicating the amount and timing of future orders. Order releases - Authorization for the execution of planned orders. Changes - revisions of due dates or order quantities, or cancellations of orders.

18 Example (p.632) A firm that produces wood shutters and bookcases has received two orders for shutters: One for 100 to be due for delivery at the start of week 4 and the other 150 units to be due for delivery at the start of week 8 of the current schedule. Each shutter consists of four slatted wood sections and two frames. The wood sections are made by the firm, and fabrication takes one week. The frames are ordered, and lead time is two weeks. Assembly of the shutters requires one week. There is a scheduled receipt of 70 wood sections at the beginning of week 1. Determine the size and timing of planned-order releases necessary to meet delivery requirements under each of theses conditions: (1). Lot-for-lot ordering (order size equal to net requirement) (2). Lot-size ordering with a lot size of 320 units for frames and 70 units for wood sections.

19 Solution to example Develop a master schedule and a product structure tree Shutter Frames (2) Wood sections (4)

20 Solution to example(lot-for-lot)

21 Solution to example (lot-for-lot)

22 Solution to example (lot-for-lot)

23 Solution to example (fixed lot-size)

24 Solution to example (fixed lot-size)

25 MRP Secondary Reports Performance-control reports Planning reports
Exception reports

26 Other Considerations Safety Stock Lot sizing Yield rates
Lot-for-lot ordering Economic order quantity Fixed-period ordering Part-period model Yield rates

27 MRP Capacity requirement Planning
Capacity requirements planning: The process of determining short-range capacity requirements. Load reports: Department or work center reports that compare known and expected future capacity requirements with projected capacity availability.

28 MRP Capacity Requirement Planning
Develop a tentative master production schedule Use MRP to simulate material requirements Convert material requirements to resource requirements Revise tentative master production schedule No Is shop capacity adequate? Can capacity be changed to meet requirements No Yes Yes Firm up a portion of the MPS Change capacity

29 Benefits of MRP Low levels of in-process inventories
Ability to track material requirements Ability to evaluate capacity requirements Means of allocating production time

30 Requirements of MRP Computer and necessary software
Accurate and up-to-date Master schedules Bills of materials Inventory records Integrity of data

31 MRP II Expanded MRP with and emphasis placed on integration
Financial planning Marketing Engineering Purchasing Manufacturing

32 Overview of MRP II Market Demand Master production schedule Finance
Manufacturing Marketing Production plan MRP Adjust master schedule Rough-cut capacity planning Capacity planning Adjust production plan Problems? No Problems? Yes No Requirements schedules Yes