Presentation is loading. Please wait.

Presentation is loading. Please wait.

PQSynergy TM 2011 Chiangmai

Similar presentations


Presentation on theme: "PQSynergy TM 2011 Chiangmai"— Presentation transcript:

1 PQSynergy TM 2011 Chiangmai
The Impact of Voltage Sag for PEA Area 1(North) Customers in North Industrial Estate Suwipha Kittitanapisarn. B.Eng(EE) Assist. Chief of Power Quality Section PEA Area1 (North) Chiang Mai, THAILAND Provincial Electricity Authority, Thailand September 2011, Chiang Mai, Thailand

2 PEA Area1 (North) In Overview
The Service Area of PEA Area1(North) is approx. 69,557 km2 , accounting for % of the country. 6 Provinces 80 amphors 592 districts 6,611 villages 4,734, populations 1,534, customers Provincial Electricity Authority, Thailand 2

3 41 Substations in Responsibility of PEA Area1 (North) (278 Feeders)
PEA Substation 115/22 kV MEA PEA Substation 22 kV CSA PEA Switching Substation115 kV MCA CKN Transmission Line 115 kV PEA S THG MCN S S EGAT Substation FAA TNG CR CRA Customer115 kV S CUN CDO MLA PAU WPA MHA S MTG MRM PYA PEA Substation 22kV MTA PAN DKA CHM CMB Total 14 Substations CMD CMF CMA SKP Cement Thai Lampang Public Co.,Ltd. CME LPC CMC LNB S LP-2 PEA Substation 115/22 kV LPB HCA LNA S LP-1 CEA Total 27 Substations NIU NIA LPA CTG S PAS PEA Switching Substation 115kV LNC BGA HOA Total 2 Substations LIA TEA

4 The Comparison of Peak Load Year 2011 and 2010
MW 1,039.12 991.33 995.73 Higher than = 4.86% Lower than = 4.85% Lower than = 3.92% Lower than = 4.38% Higher than = 7.83% Higher than 4.55% Higher than= 12.5% Jan Feb Mar Apr May June Jul Aug Sep Oct Nov Dec Year 2010 Year 2011

5 Lamphun Province In Brief
8 Amphors 8 Substations Power Transformer Capacity 490MVA Total Load MW UF %

6 Transmission Loop Line Project in Chiangmai Area
MRM MRM Now Open Looped Peak Load 300 MW 1,630 A DKA CMD CMD CMF CMF CME CME SKP SKP LNC,NIA,NIU, LNC,NIA,NIU, CMC CMC

7 Introduction North Industrial Estate
NIU Substation North Industrial Estate Lot2 North Industrial Estate Lot1 NIA Substation 3 Substations Power Transformer Capacity 240 MVA Total Load MW UF % 8 Amphors 8 Substations Power Transformer Capacity 490MVA Total Load MW UF % LNC Substation Sahapat Industrial Estate 115kV CMC- LNC

8 Report of Average SAIFI Indices (Accumulated from Jan-June 2011) Compare with Target (Level3) in Year 2011 Lower than 21.47% Times per customer per year Industrial Estate City Municiple District Municiple SubDistrictt Municiple Residental Area Total SAIFI Year 2011 Target Year 2011

9 Report of Average SAIDI Indices (Accumulated from Jan-June 2011) Compare with Target (Level3) in Year 2011 Lower than27.35% Minutes per customer per year Industrial Estate City Municiple District Municiple Subdistrict Municiple Residental Area Total SAIDI Year 2011 Target Year 2011

10 Voltage Sag (IEEE Std.1159-1995)
To Industrial Customers, a Voltage Sag and Momentary Interruption are equivalent if both shut their process down

11 Fault in Transmission and Distribution Line
While the Fault is in the Transmission System, the Entire Power System, including the Distribution System will experience Voltage Sag and Fault are cleared 3-6 cycles for Fault Detection and Breaker Operation 22 kV 115kV 22 kV/400 V 2500 KVA DYn11 Severity of Voltage Sag depend on Fault Location Fault Sizing Fault Type and Clearing Time of Protection Equipment Provincial Electricity Authority, Thailand 11

12 Study of Voltage Sag Analysis in North Industrial Estate
Process of Voltage Sag Prediction 1.To Correctly Prepare Single Line Diagram of North Industrial Estate Area from PEA-GIS Phase2 Web Database 2.Performing Short-Circuit Simulations with Sliding Faults which include Line to Line, Line to Ground and Three Phase Faults in Digsilent 14.0 Simulation Program. 3.Calcutaion Magnitude of Voltage Sag at Interesting Load 4.Predict Voltage Sag Duration Time by Characteristic of Clearing Fault of Protection Equipment 5.Compare Characteristic of Voltage Sag for Determine the Need for Power Conditioning Equipment at Sensitive Loads in Customer Area Provincial Electricity Authority, Thailand 12

13 Theory of Voltage Sag Analysis
V sag = Z 2 + Z f Impedance Divider Z 1 + Z 2 + Z f Provincial Electricity Authority, Thailand 13

14 Transmission Line from CMC to LNC
Provincial Electricity Authority, Thailand 14 14

15 Process to Voltage Sag Analysis
1.Prepare Single Line Diagram from PEA-GIS Phase 2 Web Database Provincial Electricity Authority, Thailand 15

16 GIS Phase 2 Provincial Electricity Authority, Thailand 16

17 Export Single Line Diagram from GIS Phase 2 as *dz files
Provincial Electricity Authority, Thailand 17 17

18 3. Merge. dz Files in Digsilent Power Factory Version 14
3.Merge *.dz Files in Digsilent Power Factory Version 14.0 and start to run Sliding Fault Calculation Provincial Electricity Authority, Thailand 18 18

19 Voltage Sag from Transmission Fault
*OPTREX is a Customer in North Industrial Estate Lot1 Provincial Electricity Authority, Thailand 19

20 (Continued) Voltage Sag from Transmission Fault
Provincial Electricity Authority, Thailand 20

21 Description Voltage Sag from Distribution Fault
Provincial Electricity Authority, Thailand 21 21

22 For Parallel Feeder (NIU01,03,05 = 0.49 pu.)
4. The Result For Fault at NIU02 ,5 km. From NIU Substation 3P-Fault=3.63 kA, distance =5km. V=0 pu. 0.14 pu. For Parallel Feeder (NIU01,03,05 = 0.49 pu.) S Drissen 0.43 pu. 0.46 pu. Provincial Electricity Authority, Thailand 22 22

23 Voltage Sag Summary from Distribution Fault
Provincial Electricity Authority, Thailand 23 23

24 (Continued)Voltage Sag Summary from Distribution Fault
Provincial Electricity Authority, Thailand 24

25 Voltage Sag Occurrence Calculation Summary from Transmission and Distribution Fault
Provincial Electricity Authority, Thailand 25

26 Voltage Sag Occurrence Calculation Summary from Transmission and Distribution Fault
Provincial Electricity Authority, Thailand 26 26

27 How Often for Customers to Meet Voltage Sag?
How Often for Sag 40% at Drissen Co.,Ltd.(NIU02) In 8 Months? Drissen Co.,Ltd. Meet Sag 40% = Uniform Fault Rate x Distance from NIU-Drissen = 0.17 (Faults/km-year) x 1 km = 0.17 sags / 8 Months Provincial Electricity Authority, Thailand 27 27

28 Installation Dranetz-BMI PX5-400 POWER Analyzer
1.At Chiangmai 3 Substation(CMC) 2.At OPTREX Co.,Ltd.(NIA10) 3.At Drissen Co.,Ltd.(NIU 02) Provincial Electricity Authority, Thailand 28

29 Power Quality Measurement at OPTREX Co.,Ltd.
3 times for Transient 25 Jul – 26 Jul 2011 Provincial Electricity Authority, Thailand 29

30 Power Quality Measurement at Drissen Co.,Ltd.
Abnormal Harmonic 5th order at Main Capacitor 12 Sep – 15 Sep 2011 Provincial Electricity Authority, Thailand 30

31 Power Quality Measurement at Central Pattana Chiangmai
Two events of Voltage Sag at MDB11 from Jun 2011 Instantaneous( S) Sag 46% Provincial Electricity Authority, Thailand 31

32 Conclusion The Impact of Voltage Sag for PEA Area 1(North) Customers in North Industrial Estate 1. The Result of 1P-Fault in 115 kV Transmission Line (From CMC to LNC Substation) Effects Voltage Sag not less than 0.8 pu. 2. The Result of 1P-Fault in 22 kV Distribution Line (NIU,NIA,LNCSubstation) Effects Voltage Sag not less than 0.6 pu Uniform Fault Rate of LNC Substation (From TR.1) has the Most Value and Implies that at the Same Distance from Substation if Comparing with Other Substation in Industrial Park ,LNC Substation (From TR.1) must have the Most Effect from Voltage Sag Provincial Electricity Authority, Thailand 32

33 Suwipha Kittitanapisarn.
PEA Area1 (North) Chiang Mai, THAILAND Provincial Electricity Authority, Thailand


Download ppt "PQSynergy TM 2011 Chiangmai"

Similar presentations


Ads by Google