OPTIMIZE OR−SCHEDULE TO REDUCE NUMBER OF REQUIRED BEDS Theresia van Essen, Joël Bosch.

Similar presentations


Presentation on theme: "OPTIMIZE OR−SCHEDULE TO REDUCE NUMBER OF REQUIRED BEDS Theresia van Essen, Joël Bosch."— Presentation transcript:

1 OPTIMIZE OR−SCHEDULE TO REDUCE NUMBER OF REQUIRED BEDS Theresia van Essen, Joël Bosch

2 Reduce number of required beds:  Less admissions  Reduce length of stay  Level bed utilization 9-11-2011Optimize OR-Schedule to Reduce Number of Required Beds 2/26 CONTEXT

3 9-11-2011Optimize OR-Schedule to Reduce Number of Required Beds 3/26 BED UTILIZATION PatientLOSOption 1Option 2 13MondayTuesday 23 Wednesday 32ThursdayWednesday

4 9-11-2011Optimize OR-Schedule to Reduce Number of Required Beds 4/26 BED UTILIZATION PatientLOSOption 1Option 2 13MondayTuesday 23 Wednesday 32ThursdayWednesday

5 9-11-2011Optimize OR-Schedule to Reduce Number of Required Beds 5/26 BED UTILIZATION PatientLOSOption 1Option 2 13MondayTuesday 23 Wednesday 32ThursdayWednesday

6 9-11-2011Optimize OR-Schedule to Reduce Number of Required Beds 6/26 BED UTILIZATION PatientLOSOption 1Option 2 13MondayTuesday 23 Wednesday 32ThursdayWednesday

7 9-11-2011Optimize OR-Schedule to Reduce Number of Required Beds 7/26 BED UTILIZATION PatientLOSOption 1Option 2 13MondayTuesday 23 Wednesday 32ThursdayWednesday

8  Beliën and Demeulemeester (2007)  Stochastic length of stay  Optimization  Minimize sum required beds  Van Oostrum et al. (2008)  Mean length of stay  Optimization  Vanberkel et al. (2011)  Stochastic length of stay  Evaluation 9-11-2011Optimize OR-Schedule to Reduce Number of Required Beds 8/26 RELEVANT LITERATURE

9  Generate OR blocks  Maximize OR utilization  Satisfy overtime probability  Assign OR blocks to OR-day  Minimize number beds  Satisfy OR availability  Satisfy surgeon availability  Satisfy capacity instrument sets 9-11-2011Optimize OR-Schedule to Reduce Number of Required Beds 9/26 MODEL

10  Blocks are assigned to one specialist  Maximize sum of expected duration  Sum expected duration plus slack is less than capacity  Solve with Column Generation 9-11-2011Optimize OR-Schedule to Reduce Number of Required Beds 10/26 GENERATE OR BLOCKS 08:00 16:00

11  Planning horizon  Days with OR and surgeon availability  OR blocks  Number of patients of each type  Required instruments  Probability distribution LOS 9-11-2011Optimize OR-Schedule to Reduce Number of Required Beds 11/26 ASSIGN OR BLOCKS TO OR-DAY INPUT LOS12345 Probability0.100.300.400.150.05

12 9-11-2011Optimize OR-Schedule to Reduce Number of Required Beds 12/26 ASSIGN OR BLOCKS TO OR-DAY DISTRIBUTION BEDS 1 0.8 0.6 0.4 0.2

13 Simulated Annealing  Swap two OR blocks from two different days  If swap is feasible, determine number required beds  Better solution: accept  Worse solution: accept with probability 9-11-2011Optimize OR-Schedule to Reduce Number of Required Beds 13/26 ASSIGN OR BLOCKS TO OR-DAY MODEL

14 9-11-2011Optimize OR-Schedule to Reduce Number of Required Beds 14/26 ASSIGN OR BLOCKS TO OR-DAY MODEL OR 1OR 2 Day 112 Day 234

15 9-11-2011Optimize OR-Schedule to Reduce Number of Required Beds 15/26 ASSIGN OR BLOCKS TO OR-DAY MODEL OR 1OR 2 Day 142 Day 231

16  Assignment of OR blocks to OR-days  Number required beds per day 9-11-2011Optimize OR-Schedule to Reduce Number of Required Beds 16/26 ASSIGN OR BLOCKS TO OR-DAY OUTPUT

17 9-11-2011Optimize OR-Schedule to Reduce Number of Required Beds 17/26 RESULT HAGAZIEKENHUIS ORTHOPEDICS

18 9-11-2011Optimize OR-Schedule to Reduce Number of Required Beds 18/26 RESULT HAGAZIEKENHUIS ORTHOPEDICS

19 9-11-2011Optimize OR-Schedule to Reduce Number of Required Beds 19/26 RESULT HAGAZIEKENHUIS ORTHOPEDICS

20  Applicable to surgical wards  Applicable to nonsurgical wards  No OR blocks, but individual patients  Emergency patients can be incorporated  Add distribution of emergency patients per day 9-11-2011Optimize OR-Schedule to Reduce Number of Required Beds 20/26 APPLICATIONS

21  Number beds can be reduced  Even when OR utilization increases  Costs can be reduced  Information for nurse rostering provided  Develop iterative approach  Close wards during weekend 9-11-2011Optimize OR-Schedule to Reduce Number of Required Beds 21/26 CONCLUSIONS & FUTURE RESEARCH

22 Questions? j.t.vanessen@utwente.nl


Download ppt "OPTIMIZE OR−SCHEDULE TO REDUCE NUMBER OF REQUIRED BEDS Theresia van Essen, Joël Bosch."