1 CMPDI Preparations for 925 Million Tonne Production from CIL in 2019-20

2  www.cmpdi.co.in  No drilling is required for the Blocks/Mines identified for 925 Mt production in 2019-20. 18 Project Reports (PRs) are to be prepared (production 57 Mt in 2019-20). Based on PR approval schedules of CIL, the PR submission schedule will be as follows: 10 PRs will be submitted by March 2015. 7 PRs will be submitted in 2015-16. 1 PR will be submitted in 2016-17. 27 Updated Cost Estimates for PRs will be submitted well before their PR approval schedule. 6 Schemes for Patch OCPs (for ECL) will be submitted well before their approval schedule. Preparations for 925 Mt Production in 2019-20

3  www.cmpdi.co.in  GRs Required for 925 Mt production in 2019-20 Sl No Comp- any BlockProdn in 2019-20 (Mt) RemarksAlternative for Prodn 1NCLPatpahari UG/OC 1.00GR for non-forest part available. Drilling delayed due to forest clearance. 10-15 km rail link with Katni-Chopan main line needed. Power supply network needed. PR approval required by Nov-17. 2.5 Mt production can be obtained from expansion of operating mines like Jayant Expn, Dudhichua Expn, etc. 2NCLMarki- Barka (W) UG 0.50GR for non-forest part available. Drilling delayed due to forest clearance. 30 km rail link with Katni-Chopan main line needed. Power supply network needed. PR approval required by Nov-17. 3NCLMarki- Barka (E) UG/OC 1.00Drilling delayed due to forest clearance. 30 km rail link with Katni-Chopan main line needed. Power supply network needed. GR expected by Mar-17. PR approval required by Nov-17. 4ECLDhangajore UG 0.30Drilling delayed due to forest clearance. Forest cover-75%. Number of villages to be rehabilitated. CBM overlap. GR expected by 18-19. 0.4 Mt production can be obtained from Hura C, Chuperbhita, etc. 5ECLMadhu- kunda UG 0.10Drilling delayed due to forest clearance. GR expected by 18-19.

4  www.cmpdi.co.in  Project Reports (PRs) to be Prepared for 925 MT Projection of CIL in 2019-20 Sl No Comp- any Project ReportOC/ UG Incremental Capacity (Mty) Contribution in 2019-20 (Mt) Schedule of PR Submission PR Approval Schedule 1ECLChaudhar-Gariapani-Kayada (119 blocks) OC3.000.50Sep-15Dec-15 2ECLNorth Searsole RecastOC2.000.80Sep-15Dec-15 3ECLNakrakonda Kumardih-BOC0.70 Mar-15Jun-15 4ECLMadanpur Recast (119 blocks)UG1.590.50Sep-15Dec-16 Sub-total ECL 7.292.50 Note: For CCL, the PR for Chatti-Bariatu-Kerendari is to be prepared before Jan 2016 only after these captive blocks are allotted to CCL.

5  www.cmpdi.co.in  PRs to be Prepared for 925 MT Projection of CIL in 2019-20 Sl NoComp- any Project ReportOC/ UG Incremental Capacity (Mty) Contribution in 2019-20 (Mt) Schedule of PR Submission PR Approval Schedule 1WCLKumbharkhani UG to OC RecastOC1.000.20Mar-16Mar-17 Sub-total WCL 1.000.20 Note: 22 Updated Cost Estimates of PRs made earlier, are to be submitted. 7 in 2014-15, 14 in 2015-16, 1 in 2016-17. 1SECLChira Group OC (119 blocks)OC15.001.50Jul-16Oct-16 2SECLSyang Group OC (119 blocks)OC20.003.00Jan-16Apr-16 3SECLGevra Expn OC (70 Mty)OC35.0024.00Mar-15Apr-15 4SECLMahamaya OCOC1.141.25Mar-15Apr-15 5SECLChirimiri ExpnOC1.00 Mar-15Apr-15 6SECLGayatri UGUG0.66 Mar-15Apr-15 7SECLBatura HighwallOC0.50 Mar-15Jan-16 8SECLBatura West Extn Highwall/OCOC1.000.50Mar-15Sep-16 Sub-total SECL 74.3032.41 Note: 3 Updated Cost Estimates of PRs made earlier, are to be submitted by June 2015.

6  www.cmpdi.co.in  PRs to be Prepared for 925 MT Projection of CIL in 2019-20 Sl No Comp- any Project ReportOC/ UG Incremental Capacity (Mty) Contribution in 2019-20 (Mt) Schedule of PR Submission PR Approval Schedule 1NCLBlock B Expn Recast PR (6 Mty)OC4.003.50Nov-15Jul-16 2NCLJayant Expn OCOC10.006.00Jan-15Sep-15 3NCLDudhichua Expn OCOC10.006.00Dec-15Mar-16 4NCLDongrital UG (119 blocks)UG3.001.50Mar-15Nov-15 Sub-total NCL 27.0017.00 Note: Projected production of 2.5 Mt in 2019-20 from Patpaharia, Marki-Barka E & Marki-Barka W (all 3 in 119 blocks list) is proposed to be obtained from expansion of operating mines e.g. Jayant Expn & Dudhichua Expn, etc. 1MCLBhubaneswari Expn (30 Mty)OC10.005.00Dec-15Mar-16 Sub-total MCL 10.005.00 TOTAL 18 PRs (10 PRs in 14-15; 7 PRs in 15-16; 1 PR in 16-17) 119.5957.11

7  www.cmpdi.co.in  Sustaining the Production Level Status of 119 Blocks assigned to CIL No. of blocks Tentative Reserves (MT) Tentative capacity (Mty) GR Available379451.7873.49 Exploration in progress5924396.29102.70 Exploration to start2310297.0929.25 Total11944145.16205.44 Note: 1. GR preparation for all 23 Unexplored Blocks will be completed by 2026-27. 2. 7 of these 23 blocks are on dip side of operating mines. 1 block is under the NTPC power plant site in North Karanpura.

8  www.cmpdi.co.in  Geological Reports Available – 37 Blocks. Project Reports Submitted – 7 Blocks Project Reports to be submitted in 2015-16 – 19 Blocks Project Reports to be Submitted in 2016-17 – 2 Blocks Blocks allotted for CTL – 2 Blocks Blocks to be Worked from Operating Mines – 3 Blocks Blocks on Dip side of Other Mines/blocks – 4 Blocks Exploration in Progress – 59 Blocks. Exploration to commence – 23 Blocks. Sustaining the Production Level Status of 119 Blocks assigned to CIL

9  www.cmpdi.co.in  Comp- any No. of Blocks Type of MineReserves (in MT) OCUGMixedProvedIndicatedInferredTotal ECL1701161212.736665.1924.877902.79 BCCL3120315.10147.06-462.16 CCL178631020.043265.72621.094906.85 WCL183150208.371519.8175.001803.18 SECL40815171989.8312978.51150.0015118.34 NCL13049524.114790.83-5314.94 MCL118121965.025446.881225.008636.90 CIL1192854377235.2034814.002095.9644145.16 Note: Out of 119 blocks, 4 blocks (Brahmani, Chichropatsimal, East of Damagoria, and Takli-Jena-Bellora North) are deallocated captive blocks (Schedule-I), and 2 blocks (Brajnathpur and Radharamanpur) are allotted for CTL. So, the number of additional CIL blocks would be 113 instead of 119. Sustaining the Production Level Status of 119 Blocks assigned to CIL

10  www.cmpdi.co.in  Large Projects Likely in 119 Blocks Sl No BlockCompanyTentative Capacity (Mty) 1Brahmani-ChichropatsimalECL18 2SalaipaharECL6 3Chirra Group (5 blocks)SECL15 4Syang Group (4 blocks)SECL20 5Mahan NorthSECL5 6Mahan SouthSECL5 7PrajaparaMCL 5 8Prajapara Dip SideMCL 9TribiraMCL8 TOTAL82

11  www.cmpdi.co.in  Operational Planning for large opencast mines Surface Layout and Infrastructure support services Introduction of higher size equipment (e.g. 42 cum rope shovel, 15 cum hydraulic shovels, 240 T dumpers, 381 mm drills, 860 HP dozers, 533 HP motor graders, etc) Mobile In-pit crushing and conveying systems with dust suppression arrangements Satellite Surveillance for R&R and Land Reclamation Monitoring OBR measurement for all mines of CIL (as per recent CVC guidelines) NDT. Laser Scanner for Survey. Environmental Monitoring for PM 2.5 micron. New Area for Space Technology Application: Regional Air Quality Monitoring using space borne scanners Slope Stability monitoring using SAR Interferometry Rapid OB and Coal Stock Measurement using UAVs. Support Services during Project Implementation

12  www.cmpdi.co.in  Planning and design of Coal Handling Plant including tender documents preparation, cost estimates, etc. Blasting services - Controlled blasting, Fragmentation, Site-specific proper drilling/blasting design. Design of roof support systems and strata control services. Management services for ISO Certification - ISO 9001(Quality Management System), ISO 14001 (Environment Management System), OHSAS (Occupational Health & Safety Assessment Series)18001, SA (Social Accountability) 8000, ISO 27001 (Information Security Management System), ISO 50001(Energy Management System). Lab. services for – Coal characterisation, Washability, Air / water quality, Physico-mechanical properties of rocks, CBM, Shale Gas, etc. Support Services during Project Implementation (Contd)

13  www.cmpdi.co.in  Production Enhancement from UG mines – Mass Production Technology UNDERGROUND MINES IN OUTSOURCING MODE Sl NoMineComp- any Capacity (Mty) TechnologyStatus 1Moonidih XV SeamBCCL2.500PS LongwallWork Awarded 2Moonidih XVI SeamBCCL0.700PS LongwallWork Awarded 3KapuriaBCCL2.000PS LongwallWork Awarded 4MuraidihBCCL2.000PS LongwallWork Awarded 5JhanjraECL0.950Continuous MinerWork Awarded 6SarpiECL0.460Continuous MinerWork Awarded 7Jhanjra PSLWECL1.700PS LongwallWork Awarded 8NCPH/KapildharaSECL0.430Continuous MinerWork Awarded 9Sheetaldhara-KurjaSECL0.420Continuous MinerWork Awarded 10PinouraSECL0.400Continuous MinerWork Awarded 11Rani-AtariSECL0.180Continuous MinerWork Awarded 12Churcha ROSECL1.000Continuous MinerWork Awarded 13HaldibariSECL0.420Continuous MinerWork Awarded 14Vijay WestSECL0.420Continuous MinerWork Awarded 15TandsiWCL0.510Continuous MinerWork Awarded Sub-total 14.090

14  www.cmpdi.co.in  UNDERGROUND MINES IN OUTSOURCING MODE Sl NoMineComp- any Capacity (Mty) TechnologyStatus 1Block-IIBCCL0.450Continuous MinerIn Pipeline 2KottadihECL0.510Continuous MinerIn Pipeline 3KhairahaSECL0.465Continuous MinerIn Pipeline 4KetkiSECL0.300Continuous MinerIn Pipeline 5GayatriSECL0.510Continuous MinerIn Pipeline 6Tawa-IIWCL0.360Continuous MinerIn Pipeline 7BordaWCL2.000PS LongwallIn Pipeline 8MurparWCL2.000PS LongwallIn Pipeline Sub-total 6.595 Grand-total 20.685 Production Enhancement from UG mines – Mass Production Technology

15  www.cmpdi.co.in  OTHER MINES IDENTIFIED FOR CM TECHNOLOGY Sl NoMineComp- any Capacity (Mty) TechnologyStatus 1Kumardih BECL1.020Continuous MinerPR approved 2ChuriCCL0.500Continuous MinerPR approved 3Parej EastCCL0.510Continuous MinerPR approved 4Piparwar MangardahaCCL1.020Continuous MinerPR approved 5Amlo-DhoriCCL0.300Continuous MinerPR approved 6JamuniaWCL0.840Continuous MinerPR approved 7GandhigramWCL1.170Continuous MinerPR approved 8Dhau NorthWCL0.360Continuous MinerPR approved 9Talcher WestMCL0.520Continuous MinerPR approved 10NatrajMCL0.520Continuous MinerPR approved Sub-total (PR approved) 6.760 Production Enhancement from UG mines – Mass Production Technology

16  www.cmpdi.co.in  OTHER MINES IDENTIFIED FOR CM TECHNOLOGY Sl NoMineComp- any Capacity (Mty) TechnologyStatus 1TilaboniECL1.860Continuous MinerAwaiting approval 2Jhanjra LHCMECL0.720Continuous MinerAwaiting approval 3ShankarpurECL1.163Continuous MinerAwaiting approval 4Pandaveswar- Dalurband ECL1.170Continuous MinerAwaiting approval 5Rangamati-AECL0.855Continuous MinerAwaiting approval 6Rangamati-B (Tumni and Kanchanpur Sector) ECL1.080Continuous MinerAwaiting approval 7PathakpurSECL0.720Continuous MinerAwaiting approval Sub-total (PR awaiting approval)7.568 Total (Other Identified Mines)14.328 Grand-total (Outsourcing + Other Identified Mines) 35.013 Production Enhancement from UG mines – Mass Production Technology

17  www.cmpdi.co.in  Coal Resources & Reserves under CIL as per UNFC Classification Total No. Of Blocks/Mines/ Projects Total Resources (BT) Proved Resources (BT) Indicated / Inferred Resources (Balance to be proved) (BT) 64588.41766.6121.80

18  www.cmpdi.co.in  Resources in Stand Alone Blocks and Dip Side Blocks as per UNFC Classification Type of BlocksNumberResources (BT) Explored Stand alone Blocks40.28 Total – Explored0.28 Un-Explored Stand alone Blocks20.50 Under Exploration Stand alone Blocks50.98 Total - Unexplored Blocks1.48 TOTAL – Stand alone Blocks1.76 Resources on dip side blocks/lower seams20.32 Grand Total22.08

19  www.cmpdi.co.in  Stand-alone Blocks under CIL Sl No BlockCoalfieldExploration Status Tentative Reserves (Mt) OC/ UG Tentative Capacity (Mty) Remarks 1North LohariDaltonganjExplored3.62UG0.3Small isolated block. Meager reserves. 2Barul BagdihaRanigunjUnexplored468.78UG1Reserves deep seated below barren measure. 3MadhupurIb ValleyIn progress70.73OC230% forest land. Dhutra Sardega Rly Corridor 52 km needed. 4Baitarni EastTalcherIn progress425.00OC5Law & Order Problem. 60 % forest, Jarapada-Talcher Rail Corridor 87 km needed, 2 nalas to be diverted. 5Tulsi Block ABisrampurExplored32.91OC/ UG 1GR submitted in 2013. Block area 4.13 sq.km. 6East of Manikpur (Bundeli-I, II, III) KorbaExplored200.00OC/ UG 340% forest land, R&R of 1 village, 3-4 km rly link needed from proposed East West Rail Corridor. 7NoonbirraKorbaExplored44.58OC/ UG 1Indicated reserve. Detailed exploration not done due to low potential. 8Keshwahi (Gerua Area) SohagpurUnexplored30.00UG120% forest land, R&R of 7 villages, 20 km rly link needed from Burhar siding. 9AmartipurTatapaniIn progress45.86OC1Law and order problem. 95 % forest land, 49 km rly link needed from Bhatgaon siding. 10DubaTatapaniIn progress87.81OC1Law and order problem. 80% forest land. 43 km rly link needed from Bhatgaon siding 11Mitgain BhormiTatapaniIn progress350.00OC3Law and order problem. 7 km rly link from Bhatgaon siding needed. 1759.2919.30

20 THANK YOU

21  www.cmpdi.co.in  PRs prepared and not included in the 925 Mt production program Sl No ProjectComp- any OC/ UGIncremental Capacity (Mty) PR Status 1Pandaveswar-DalurbandECLUG2.27Awaiting approval with ECL. OC (H) Patch Proposed. 2Rangamati AECLUG0.86Awaiting approval with ECL. 3Rangamati B (Gourbazar Sector)ECLUG0.51Awaiting approval with ECL. 4Rangamati B (Tumni Kanchanpur Sector) ECLUG1.08Awaiting approval with ECL. 5Shankarpur UGECLUG1.16Awaiting approval with CIL. Sub-total ECL 5.88 6Block VBCCLOC3.00Awaiting approval with BCCL. OC (H) Patch Proposed. 7Block VIBCCLOC1.50Awaiting approval with BCCL. OC (H) Patch Proposed. 8Kalyaneshwari (119 blocks)BCCLOC4.00Awaiting approval with BCCL. Sub-total BCCL 8.50

22  www.cmpdi.co.in  PRs prepared and not included in the 925 Mt production program Sl No ProjectComp- any OC/ UGIncremental Capacity (Mty) PR Status 9Ara OCCCLOC2.50Awaiting approval with CCL 10Argada OCCCLOC1.70Approved in Principle by CCL 11Asnagarha OCCCLOC3.00Awaiting approval with CCL 12Aswa NSCCLOC1.00Approved in Principle by CCL 13Chano RikbaCCLOC2.00Approved in Principle by CCL 14DRD OCCCLOC4.00Awaiting approval with CCL 15Gose OCCCLOC2.00Approved in Principle by CCL 16HesalongCCLOC1.50Approved in Principle by CCL 17Jeevandhara OCCCLOC1.00Awaiting approval with CCL 18KujuCCLOC1.30Approved in Principle by CCL 19Mahendra (Rajbar) (119 blocks)CCLOC4.00Approved in Principle by CCL 20Pundi ExpnCCLOC2.50Approved in Principle by CCL 21Ramgarh-II WestCCLOC1.50Awaiting approval with CCL 22Religara ExpnCCLOC0.60Awaiting approval with CCL 23Sawang Pipradih OCCCLOC2.00Awaiting approval with CCL 24Sayal DCCLOC1.00Approved in Principle by CCL Sub-total CCL 31.60

23  www.cmpdi.co.in  PRs prepared and not included in the 925 Mt production program Sl NoProjectComp- any OC/ UG Incremental Capacity (Mty) PR Status 25Bakulmuni OCSECLOC1.50Submitted to SECL. Uneconomic. 26Amba UGSECLUG0.24Submitted to SECL. Uneconomic. 27Badauli PSLW UGSECLUG0.78Submitted to SECL. 28Bodri/Bodri North UGSECLUG0.78Submitted to SECL. Uneconomic. 29Pathakpur UGSECLUG0.72Submitted to SECL. Sub-total SECL 4.02 30Chikalgaon / ChinchalaWCLOC3.00Uneconomic 31Ghugus Expansion (Sector C) /Nokoda UG to OC WCLOC0.80Uneconomic 32Magrahi UrdhanWCLOC2.00Uneconomic - shelved by WCL 33BhakraWCLUG0.27Uneconomic 34DhankasaWCLUG1.00Uneconomic 35GandhigramWCLUG1.20Uneconomic Sub-total WCL 8.27 TOTAL 58.27


Download ppt "CMPDI Preparations for 925 Million Tonne Production from CIL in 2019-20."