Presentation is loading. Please wait.

Presentation is loading. Please wait.

TMP Development Module 7. What is a TMP? Set of coordinated transportation management strategies applied to manage work zone impacts of the project Scaleable.

Similar presentations


Presentation on theme: "TMP Development Module 7. What is a TMP? Set of coordinated transportation management strategies applied to manage work zone impacts of the project Scaleable."— Presentation transcript:

1 TMP Development Module 7

2 What is a TMP? Set of coordinated transportation management strategies applied to manage work zone impacts of the project Scaleable – projects with larger anticipated impacts may require more strategies Required in all FA projects – TMP=TCP in some projects TMP=TCP+TO+PI components in others

3 TMP Development Process

4 TMP Development, Implementation, and Assessment 11 Step Process 1. Compile Project Material 2. Determine TMP Needs 3. Identify Stakeholders 4. Develop TMP 5. Update/Revise TMP 6. Finalize Construction Phasing/Staging and TMP

5 TMP Development, Implementation, and Assessment 11 Step Process (continued) 7. Re-evaluate/Revise TMP 8. Implement TMP 9. TMP Monitoring 10. Update/Revise TMP Based on Monitoring 11. Post-Project TMP Evaluation

6 TMP Team Approach Better coordination throughout the process from development to implementation Involve all involved offices internally  TMP Coordinator  Planning  Design  Traffic engineering  Construction  Operations (maintenance)?

7 Step 1 - Compile Project Material Staff responsible for each stage of the project (planning, preliminary engineering, design, construction) begins by compiling available project materials such as: Project definition Construction phasing/staging alternates Preliminary work zone management strategies. Preliminary cost estimates for strategy implementation Information from other projects in the corridor to evaluate the combined or cumulative impact of the projects.

8 Step 2 - Determine TMP Needs Necessary Components of TMP  Impact assessment  Duration of project  Possible Strategies Determine if it is a significant project: Based upon the agency's policy and procedures, project's anticipated work zone impacts.

9 Step 2a - Basic TMP Basic TMPs –  Applied on construction or maintenance projects with minimal anticipated impacts  Projects typically only involve the development of a TCP – layout of devices, phases, etc.

10 Step 2b - Intermediate TMP Intermediate TMPs – Used for construction or maintenance projects that are anticipated to have more than minimal disruption, but have not been identified as significant projects. Include more detailed work zone impacts analysis and management strategy information than Basic TMPs, including some element of PI and/or TO strategies as well as TCP.

11 Step 2c - Major TMP - Significant Projects Major TMPs are intended for significant projects. Major impacts to road users, residents and businesses TMPs for significant projects shall consist of a TCP, and also address PI and TO components. In addition to the TMP components required by the Rule, TMPs may also contain cost estimates, coordination strategies between stakeholders, secondary mitigation strategy(s), analysis of potential impacts on detour routes, and analysis of the potential effects of the management strategies.

12 Step 3 – Identify Stakeholders Internal and external that can provide valuable input to the agency on what strategies to include in the TMP to help manage the work zone impacts of a project. TMP DOT Road Users Local Government Property Owners Emergency Responders Federal Agencies Contractor

13 Step 4 – Develop TMP The level of detail of the TMP during early planning is largely dependent upon the type of planning activity, the expected impacts of the project, and the availability of data. At a minimum, early planning should entail a qualitative exercise to list the potential impacts of a project, along with a list of potential management strategies, and the expected costs of those management strategies.

14 Step 5 – Update/Revise TMP The TMP is updated or revised as the project progresses through its various developmental stages as more project-specific information becomes available.

15 Step 6 – Finalize Construction Phasing/Staging and TMP PS&Es shall include either all the applicable elements of a TMP, or the provisions for a contractor to develop a TMP. TMP development should begin prior to project letting, even for design-build projects. Some elements could be accomplished early in process – alternate route work or beginning of PI plan Some may not be in PS&E – agency in house

16 Step 7 – Re-evaluate/Revise TMP If alternative construction phasing/staging plans or other management strategies have been suggested, technical specialists from the contractor or agency need to review the TMP to see if changes are needed.

17 Step 8 – Implement TMP The TMP is implemented. In some cases, components of the TMP may need to be implemented prior to construction (e.g., public relations campaign, improvements to detour routes, etc.).

18 Step 9 – TMP Monitoring Monitor operational performance of work zone during the construction phase  Are predicted impacts realistic?  Are the strategies in the TMP effective in managing the impacts?  Do any adjustments to TMP need to be initiated?

19 Step 10 – Update/Revise TMP Based on Monitoring If performance requirements are not met, the agency and/or contractor should revisit the TMP and consider alternate management strategies and/or phasing/staging approach(es) that meet the approval of the agency.

20 Step 11 – Post-Project TMP Evaluation TMP performance assessment can aid in addressing the following concerns: Which management strategies have proven to be either more or less effective in improving the safety and mobility of work zones? Are there combinations of strategies that seem to work well? Should TMP policies, processes, procedures, standards, and/or costs be adjusted based on what has been observed or measured? Are the best decisions in planning, designing, implementing, monitoring, and assessing work zones being made? Performance assessment may involve two tracks: 1) the overall TMP process 2) actual field performance of the work zone and TMP.

21 TMP PROCESS –CA Example Conceptual Planning and Design Request TMP Data Sheet What Kind of TMP is required? Establish TMP Team (Ops, Design, Traffic, Const, CHP) START MAJOR Prepare Data Sheet Arrange for Funding of TMP Strategies Detailed Plans & Specs (inc.TMP) Modify Strategies as Needed Start early TMP elements Begin Construction Implement TMP Minor Maintenance and Permits activities Blanket ** Modify TMP Strategies as Needed / Monitor traffic initially / Provide Lessons Learned

22 Ohio DOT’s TMP Development Process Start Project MOTAA MOT Policy Exception Requests Stage 1 Design Construct Project

23 Developing the TMP (Putting the components together) Traffic Control Plan  Layout of traffic control devices to guide road users through or around work zone.  Determined after analysis of strategies  Contain any restrictions on work hours  Include Work Zone Speed Limits – State policy ?

24 TYPICAL TRAFFIC CONTROL PLANS CONTENTS : LANES WIDTHS WORK AREA & DIMENSIONS CONSTRUCTION SEQUENCE SCHEDULE, STAGES & ACTIVITIES /STAGE ADJACENT HAZARDS TEMPORARY DRAINAGE TYPE OF AREA (CBD, RURAL, URBAN) GEOMETRICS LOCAL ORDINANCES SPECIAL PROVISIONS PAY ITEMS

25 TYPICAL TRAFFIC CONTROL PLANS CONTENTS : LOCATION/TYPES OF TC DEVICES SIGNS, BARRIERS, PAVEMENT MARKINGS, ARROW BOARDS, CMS, ETC… EMERGENCY ACCESS PEDS./BYCLIST ACCESS EQUIPMENT, WORKERS ACCESS CROSSOVERS/EMERGENCY OPENINGS EXISTING REGULATORY SPEED LIMIT/OTHER SIGNS TRAFFIC CONTROL NOTES LIGHTING/GLARE SCREEN GEOMETRICS LOCAL BUSINESS/RESIDENT ACCESS DETOURS, IF APPLICALIBE

26 PEDESTRIAN/BICYCLISTS Situations That Warrant Special Considerations: Sidewalks Traverse Work Zone Designated School Route Significant Pedestrian/Bicyclist Activity ADA compliance Existing Generators (Parks, Schools, Shops)

27 Additional TMP Components for Significant Project Transportation Operations Plan  Improvements to alternate route Traffic Signal retiming Intersection geometric improvements  Utilize existing infrastructure – detectors, cameras, TMC

28 Traffic Operations Plan  Incident management plan for work zone Pre-stationed tow operators during peak hours  Motorist Assist Patrols Utilize existing with added units Contract during project  Demand reduction strategies Carpools Increase transit ridership  ITS real time traffic information systems

29 Other Considerations Existing state policies  Work zone speed limits Reduced at all times? Reduced when workers present and exposed? Use of Law Enforcement?  Use of Positive Protection – PCB or other 23 CFR 630 Subpart K

30 MUTCD Sec 6C.01 “Reduced speed limits should be used only in the specific portion of the TTC zone where conditions or restrictive features are present…A TTC plan should be designed so that vehicles can reasonably safely travel through the TTC zone with a speed limit reduction of no more than 10 mph.”

31 Increase in Fatal Plus Injury Accident Rates From Before to During Construction Speed Limit Reduction (mph) Percentage Increase (%) Rural - traveled way & detours

32 Increase in Speed Variance from Upstream to Work Zone Speed Limit Reduction (mph) Percentage Increase (%)

33 Minimizing Variance Safest traffic operations result when speed variance is minimized Only police enforcement is effective in reducing speeds without increasing speed variance

34 Stationary Police Vehicle on Approach

35 Enforcement Enforcement Impact on Vehicle Speeds Enforcement Policies Problems Work Zone Training for Police Policies on Work Zone Speed Limits

36 Observed Problems  Difficult to ticket speeders in work zones  Officers have little guidance on when or where to deploy  Lack of ticketing  Officers are stationed in unsafe positions

37 Observed Problems (cont.)  State laws affect enforcement options  TTC plans are not designed for enforcement  Officers are in short supply

38 Do not allow this…

39 Reduction in Mean Speeds Between Upstream and Work Locations Speed Limit Reduction (mph) Reduction in Mean Speed (mph)

40 Comparison of Speed Variance Between Upstream and Work Locations Speed Limit Reduction (mph) Increase in Speed Variance (mph)

41 Incident Management Plan Ensure access to all areas for emergency vehicles  Hospitals nearby?  Trauma centers? Plan to provide access within work site  Identify alternate routes  Pre-sign for use during incidents? Pre-station tow operators during peak hours

42 Business Access Temporary entrances  Signing  Pavement Advance notification of phase changes  Keep owners informed Work Schedules  Christmas shopping season  Weekends

43 Residential Access Keep residents informed as project begins and progresses  Maintain access if possible  Neighborhood association meetings, newletters, mailings, etc.

44 Additional TMP Components Public Information  Strategies to inform public of work zone conditions Website Real time traffic information system Community outreach – residents and businesses Twitter TV – Radio – commuters  Occasionally contracted out to PR firm for major campaign

45 Billboards on Project Project logo Progress

46 NHI 380072A 16-46 THE STEVENSON RECONSTRUCTION Brochures for Media Kits and Public Distribute early – may influence alternate route choice

47 Example Checklist FHWA Guide

48

49 Example Checklist DDOT

50 Example Checklist DDOT Guide

51

52

53 TMP Overview53 Summary Estimate and budget for TMP development and implementation early in project development (update as appropriate throughout project) Consider and address WZ impacts from a broad transportation management perspective (rather than solely a traffic control perspective) Coordinate with key parties to jointly identify WZ impacts issues to account for and management strategies to address them Strive to use strategies that keep lanes open, especially during peak traffic times

54 TMP Overview54 Summary (cont.) Consider using extended closures or full closures versus numerous night closures Consider strategies that facilitate decision-making by the public to avoid the WZ (e.g., public awareness, advance signage in locations prior to key motorist decision points) Training is important for all personnel involved in TMPs Management support is needed for effective TMP efforts

55 Questions ?


Download ppt "TMP Development Module 7. What is a TMP? Set of coordinated transportation management strategies applied to manage work zone impacts of the project Scaleable."

Similar presentations


Ads by Google