1 Solar Update July 11, 2013 Michael E. Finn, CFO.

Similar presentations


Presentation on theme: "1 Solar Update July 11, 2013 Michael E. Finn, CFO."— Presentation transcript:

1 1 Solar Update July 11, 2013 Michael E. Finn, CFO

2 Coyote Hills, Zuni Hills and Peoria High School to begin construction April 1 – Elementary schools completed August 2 – High School completed August 30 Cheyenne, Desert Harbor, and Santa Fe to begin construction May 27 – All completed September 27 2 Construction Schedule- Original Schedule

3 Zuni Hills – Plans submitted to city March 15th – Permits issued May 23 rd – Broke ground May 31 st – New projected completion date of September 20 th Coyote Hills – Plans submitted to city March 17th – Permits issued May 23 rd – Broke ground June 3 rd – New projected completion date of September 20th 3 Updated Schedules and Progress

4 Peoria High School – Plans submitted to city March 18th – Permits issued June 13 th – Broke ground June 17 th – New projected completion date of September 20 th Cheyenne Elementary School – Plans submitted to city April 29th – Permits issued July 1 st – New projected completion date of November 15th 4 Updated Schedules and Progress

5 Santa Fe Elementary School – Plans submitted to city April 29th – Permits still under review – Projected permits on July 17th – New projected completion date of November 15 th Desert Harbor Elementary School – Plans submitted to city April 29 th – Projected permits on July 17th – Permits still under review – New projected completion date of November 15th 5 Updated Schedules and Progress

6 AERIAL VIEWS OF WORK IN PROGRESS 6

7 7

8 8

9 9

10 QUESTIONS 10