Presentation is loading. Please wait.

Presentation is loading. Please wait.

Indira Paryavaran Bhawan

Similar presentations


Presentation on theme: "Indira Paryavaran Bhawan"— Presentation transcript:

1 Indira Paryavaran Bhawan
PRESENTATION To CPWD Senior Officers on Indira Paryavaran Bhawan

2 INDIRA PARYAVARAN BHAWAN
New delhi G+7 Storeyed+3Basements Plinth area:32,000 sq.m Solar PV System KWp Capacity

3 PROJECT TEAM User organisation MoEF Execution Agency CPWD
Architectural and Structural Planning CPWD Consultants Green Building M/s DPAP MEP Services M/s Spectral Services Interior Design M/s Kothari Construction agencies 1.Main Composite Contract M/s Swadeshi Civil Infra structure 2. Solar Power M/s Swadeshi Civil Infra structure 3.Automated Parking M/s Simplex Projects

4 Indira Paryavaran Bhawan
Area details Plot area sqm Plinth Area sqm Project Completion Cost Rs 195 Cr (Tentative)

5 BUILDING UTILITY DETAILS
Basements 1. Fully automated Robotic parking for 330 cars 2. All bulk MEP Services i/c a)AC plant room 500 TR b) Electrical Substation and Transformers c)Fire fighting pump house d) Sewage treatment plant (30KL/day) e) DG set 500KVA and UPS

6 BUILDING UTILITY DETAILS
Superstructure 1. Office space for 600 employees i/c 3 Ministers 2. Auditorium 125 seating capacity 3. Committee rooms and conference rooms(7 Nos) 4. Roof garden ,Gymnasium and Yoga room for recreation 5. Cafeteria, Kitchen and executive dining hall

7 Additional Scope beyond conventional
Roof Top Solar Power plant KW Capacity 6000 sqm Fully Automated Robotic Car Parking cars

8 UNIQUE FEATURES FIRST “NET – ZERO ENERGY” Multistoreyed Building
in GOVERNMENT SECTOR targeted for both ratings of Green building “NET – ZERO ENERGY” Multistoreyed Building with 100% ON-SITE Power Generation 5STAR GRIHA LEED India PLATINUM LARGEST Roof top Solar Power system in any multistoreyed Building (930KWp)

9 Overall Environmental Protection
ACHIEVEMENTS a)40% Savings in ENERGY b)ZERO Electricity Billing a)55% Savings in Water b)Zero Net Disharge Overall Environmental Protection

10 GREEN BUILDING 5STAR GRIHA Certification

11 Services Included (All inclusive)
COMPOSITE CONTRACT Services Included (All inclusive) 1.Main structure and finishing works 2.Central Air Conditioning 3.Sub station 4.Lifts 5.Fire Fighting & Fire Alarm 6.IBMS 7.DG Sets 8.UPS 9.CCTV system 10.Internal EI

12 CHRONOLOGY OF EVENTS Foundation stone laying 19.11.2009
 Sanction of PE(A/A& ES)    Conceptual Approval by DUAC Total Planning time < 1 Y 2M  Start of the Project Completion of the Project  Completion Certificate by NDMC Total Construction time Y 11M

13 STATUTORY APPROVALS Sl No Approval Concept stage Completion Stage 1
Forest (Tree cutting ) 2 Environmental Impact Assessment 3 Delhi Fire Services 4 AAI 5 Land Use Change 6 DUAC 7 ASI 8 NDMC (expected) Completion of Project : Ready for Occupation:

14 STATUTORY APPROVALS Sl No Approval Concept stage Completion Stage 9
Electric Load Sanction Oct 2013 10 Energisation of HT panels Nov2013 11 Substation by CEA 12 Labour safety (Delhi Govt) Nov 2013 13 Electric Power Supply 14 Water Supply & Sewerage Connection Completion of Project : Ready for Occupation:

15 ASPECTS OF SUSTAINABILITY
1.SITE PLANNING 2.ENERGY MANAGEMENT 3.MATERIAL MANAGEMENT 4.WATER &WASTE MANAGEMENT 5.HEALTH & WELL BEING

16 SITE PLANNING

17 ARCHITECTURAL PLANNING AND LANDSCAPING
Effective Ventilation by orientating the building E-W and by optimum integration with nature by separating out different blocks with connecting corridors and a huge central court yard. E W N

18 ARCHITECTURAL PLANNING AND LANDSCAPING
The Building Envelope has been designed i) to receive 75% of natural daylight to reduce energy consumption. ii) Access Friendly to differently-abled persons. Out of total 79 trees existing on the site , only 19 were cut, and 11 transplanted

19 ARCHITECTURAL PLANNING AND LANDSCAPING
More than 50% area outside the building is soft with plantation and grassing. circulation roads and pathways soft with grass paver blocks to enable ground water recharge

20 ENERGY MANAGEMENT

21 E&M Services REGULAR 1.Central Air Conditioning(HVAC) 2.Lifts
3.Fire Fighting & Fire Alarm 4.IBMS 5.DG Sets 6.UPS 7.CCTV system 8.Audio Visual System 9.Internal EI SPECIAL 1.Fully Automated robotic Parking for 330 cars

22 ENERGY SCENARIO 22.0 lakh KWh 13.6 lakh KWh 40% (approx) 14.3 lakh KWh
(Average Annual) Power Requirement (Base Case) lakh KWh Power Requirement(Design Case) lakh KWh Percentage savings 40% (approx) Targeted Solar Power Generation lakh KWh Net Power generation lakh KWh (Surplus)

23 Energy Efficiency ECBC 2007 ACTUAL Lighting Power Density (LPD)
11.8 W/sqm 5 W/sqm HVAC load 20 sqm/Tr 40 sqm/Tr Total 100W/sqm 40 W/sqm

24 CENTRAL PUBLIC WORKS DEPARTMENT
Operational energy savings 1)Proper orientation Optimized building envelope 2)Insulated walls and roof 3)Glass tranmitting light but not heat Optimized day lighting 1)Energy efficient LED Lights 2)SENSORS CENTRAL PUBLIC WORKS DEPARTMENT

25 CENTRAL PUBLIC WORKS DEPARTMENT
Operational energy savings Optimized ENERGY systems i/c HVAC 1)Chilled beam system of air conditioning with <50% conventional energy consumption 2)GEOTHERMAL HEAT EXCHANGE SYSTEM 3)Regenrative lifts 4)Energy efficient equipment CENTRAL PUBLIC WORKS DEPARTMENT

26 chilled beam work at site
In the IPB project Chilled Beams are being installed in second floor to sixth floor. Chilled Beam Water in Temperature is 16° C and water out temperature is 20° C. Room temperature maintained is 26 ±1 ° C. Chilled Beams with Drain pan are used to drain out water droplets due to condensation during monsoon. 160 TR of air conditioning load of the Building is met through Chilled Beam system.

27 Chilled beams induction units overview
Primary air ventilation from Dedicated Outdoor Air Source Chilled Water Hot Water Total room mixing is achieved through Convection currents within the space

28 A chilled beam installed at site
Chilled Water Return Pipe (½” dia.) Chilled Beam Chilled Water Supply Pipe (½” dia.) Drain Pipe (¾” dia.) Flexible Duct (6 Inch dia.) Supply Air Induced Air

29 A geothermal heat exchange work at site
There are 180 vertical bores at the Depth of 80 meter all along the Building Premises. Minimum 3 meter distance is maintained between any two bores. Each bore is lowered with HDPE pipe U-loop (32mm outer Dia.) and grouted with Bentonite Slurry. Each U-Loop is connected to MS Header Pipe(100mm Dia.)which finally joins the Condenser Water Line in Plant Room. Condenser hot water is sent at 100°F (37.8° C) & back at 900 F (32.2° C). One U-Loop has 0.9 TR Heat Rejection capacity, so all together 160 TR of Heat rejection is obtained without using a cooling tower.

30 GEO THERMAL HEAT EXCHANGE Vertical closed loops

31 NET ZERO ENERGY With SOLAR POWER

32 NET ZERO ENErgy A major chAllenge
Renewable Energy to be Generated : 14 lakh KWh Per Year Area required for locating Solar panels : Area available over terraces : Creation of this additional space(6000 minus 2200 m2) in a multistoreyed building with restricted plot & roof areas where no structure including surface parking is provided around the building, was a big Constraint 6000 m2 2200 m2

33 ACTUAL SOLAR POWER GENERATION
(as on ) Power Evacuation to grid started on Power generation achieved KWh(per day) Total generation so far lakh KWh

34 Highest efficiency (20%) Solar PV panels
Grid Interactive System SOLAR PV SYSTEM KWp CAPACITY TOTAL AREA M2 TOTAL AREA OF PANELS M2 ANNUAL ENERGY Generation lakh units

35

36

37

38 MATERIAL MANAGEMENT

39 UTILISATION OF FLY ASH Flyash (Reuse) : Cement used is PPC (Portland Pozzolona Cement)(29% Fly Ash) In all RCC, PCC, Plaster, Masonry Work. FALG Bricks and AAC blocks used instead of clay bricks.

40 AAC BLOCKS INDIRA PARYAVARAN BHAWAN,NEW DELHI

41 FLYASH LIME GYPSUM BRICKS
FALG BRICKS FLYASH LIME GYPSUM BRICKS FLYASH 40%

42 LOW ENERGY MATERIALS Granite (Lakha Red) Dholpur Stone
REGIONALLY AVAILABLE Use of material available within a radius of 800 km . Dholpur stone, Kota stone, North Indian Granites, AAC Blocks, FaLG bricks etc. Granite (Lakha Red) Dholpur Stone

43 Calcium Silicate Tiles
LOW ENERGY MATERIALS RECYCLED / RECYCLABLE Use of material available having Recycled content FaLG Bricks, Terrazo Tiles, Vitrified Tiles, Calcium Silicate Tiles, crazy marble etc. Calcium Silicate Tiles Terrazo Tiles Crazy Marble

44 LOW ENERGY MATERIALS RAPIDLY RENEWABLE BAMBOO – JUTE COMPOSITE DOORS
Polymer Thermosetting Resin (Phenol Formal Dehyde) BAMBOO MAT Woven sheet using Bam0.boo slivers 0.6 to 0.8mm thick & 5mm wide JUTE / COIR MAT Jute / Coir Thread woven into coarse cloth Satisfies all the quality parameters that a normal flush door does

45 Use of Eco friendly Materials
Fly Ash Brick Aerated Autoclaved Cement (AAC) Block Portland Puzzolona Cement Terrazzo tile flooring with salvaged stone pieces Grass Paver Blocks Pavements Local Stone with Marble Strips Calcium Silicate Tiles Bamboo Jute Composite for Frames & Doors Low Volatile Organic Compound Paints

46 WATER MANAGEMENT

47 55% Reduction in overall use of water
CONSERVATION OF WATER 55% Reduction in overall use of water Low discharge water fixtures Low demand plants in landscaping Use of Geothermal Cooling Recycling of waste water for ZERO Discharge Rain water harvesting Recharge wells, supply to NDMC Tankers

48 Water Supply to TANKERS

49 Automatic car parking system
Introduction All the three(3) basements will be used for Automatic Car Parking system. Total Capacity : 330 nos. of cars. The following type of system is adopted in this project:- 1. Shuttle Dolly System( 2nd & 3rd Basement). 2. Puzzle Parking System(1st Basement).

50 Salient feature The followings are the stringent targets of the project:- 1. Maximum waiting time : 180 sec(i.e. 3minutes) 2. Total evacuation time : 40 minutes. (Emergency)

51 LIFT ENTRY LOBBY

52 LIFT WELL

53 SHUTTLE BAY

54 SHUTTLE BAY

55 Thank You


Download ppt "Indira Paryavaran Bhawan"

Similar presentations


Ads by Google