Crandall Canyon Shaft Project PLATEAU MINING CORPORATION.

Similar presentations


Presentation on theme: "Crandall Canyon Shaft Project PLATEAU MINING CORPORATION."— Presentation transcript:

1 Crandall Canyon Shaft Project PLATEAU MINING CORPORATION

2 Crandall Shaft Depths About 3 ¼ LDS Church Office Buildings

3 Crandall Shaft Volumes  Both Shaft approx. 46,000 yds  158 - Cat 797 haul Trucks (290 yd Capacity)

4 Liability for Caps Source: USDA, Natural Resource Conservation Service, Mine Shaft and Adit Closing, July 2000  Enclosures, gates, and caps shall be used only where periodic inspection and maintenance is ensured through a maintenance agreement with a responsible government entity, landowner, or organization.”  “Shafts shall be closed with plugs only if another practical solution is not available.”

5 Permanent Closure of Mines Source: Openings Hazards and Remediation Handbook - Nova Scotia Department of Natural Resources P. 11 & P.22  Long Term Closure- Concrete caps & Bulkheads Effective 30 to 50 years The installation should be monitored, however, as over time, the concrete will deteriorate, steel reinforcing will corrode and/ or the mine openings may cave or subside.  Permanent Closure Backfilling Closure through blasting

6 Innovative use of existing Technology for Western Coal ISSUE:  Very little experience with filling large, deep shafts

7 Innovative use of existing Technology for Western Coal  Many issues to deal with Size of Shaft Depth of Shaft Methane Water in the shaft Underground issues unknown  Pipes  Landings  Elevator guide rails  Seals

8 Size of Shaft  Large Track Hoes Used  Multiple Machines Required  Spotters

9 Depth of Shaft  Material Handling Move Material with scrapers Use Hoes, and dozers for filling  Ventilation Dump material versus convey Provides ventilation

10 Methane Issue  1.8% in Exhaust Shaft  Up to 7.5% in Intake Shaft  Mechanical Ventilation of Shaft  Would Ventilation circuit remain in-tact

11 Methane Resolution  Monitor prior to removal of caps  <3% remove exhaust (20’) cap  Allow to ventilate  <3 % remove intake winze next to (26’) cap  Dump material to provide mechanical Ventilation  Monitor at top of shaft

12 Water in Shaft  Determine depth of water FOUND  Could cause closure of ventilation circuit  Could cause more material to be used  Provided for safety in lower part of shaft

13 Structural Issues Summary  The bottom 50’ of shaft stabilized w/ broken concrete  Broken Concrete through mined Seams  Clay plug to seal water and methane

14 Other Issues  Could not cut guide rails at top of shaft.  Landings/ pipes may provide for bridging.  Steel in shaft could cause for ignition of >5% Methane concentrations

15 Intake Headframe from Exhaust Shaft Prior to Reclamation

16 Intake Shaft Headframe & Hoist

17 Removing Exhaust Cap

18 Moving Fill Material

19 Filling Exhaust Shaft

20 Exhaust Shaft filled/Collar Exposed

21 Intake Shaft Filled & Collar Demo

22 Rough Grade at Intake Shaft

23 Checking Streambed Grade near exhaust shaft

24 Stream Grade Complete Top Soil Placement

25 Intake Shaft, Final Reclamation

26 Crandall Canyon Shaft Project Permanent Reclamation PLATEAU MINING CORPORATION