Presentation is loading. Please wait.

Presentation is loading. Please wait.

Welcome.

Similar presentations


Presentation on theme: "Welcome."— Presentation transcript:

1 Welcome

2 Title of the Thesis Productivity Improvement of a Sewing Line in a Selected Company of Ready Made Garment Industry by Using Assembly Line Balancing Technique Presented By Md. Anwar Hossen Reg. No Md. Shakil Khan Reg. No

3 Introduction Now the business world is very dynamic and competitive.
This competitive situation can only be managed by applying operations management tools. As example, for repetitive production system Assembly Line Balancing is very effective tool. Line balancing can ensure the improvement of: efficiency production rate productivity and Reduction of: idle time resource utilization production cost etc.

4 Objectives To evaluate the existing assembly line for finding the current status To reduce idle time, if any To improve productivity, if possible

5 Research Methodology The steps involved in case study are:
[page 13] The steps involved in case study are: Step 1: Determining the research questions Step 2: Selecting the cases and analysis techniques Step 3: Prepare to collect the data Step 4: Collect data in the field Step 5: Evaluate and analyze the data Step 6: Prepare the report

6 Case Company On the assembly process of Short Pant
In a manufacturing industry named “Mondol Fabrics Ltd.”, Nayapara, Kashimpur, Gazipur

7 Tools & Techniques Evaluation parameters of existing assembly process:
efficiency idle time production time production rate production cost & productivity Scientific technique “Six-Step Assembly Line Balancing” Improvement analysis “Sequential Improvement Technique”

8 Evaluation

9 Six-Step Assembly Line Balancing
[page 7] It has the following six steps: Step 1. Select task, estimate time & draw precedence diagram Step 2. Specify the daily output level & calculate cycle time Step 3. Calculate the minimum number of work centers Step 4. Develop an initial layout Step 5. Evaluate the current layout Step 6. If possible, improve the layout

10 Time Study [page 3] Time study is the combination of a series of activities as follows: Step 1: Define the Task Step 2: Breaking the Job into Elements Step 3: Estimate the Required Number of Observation Step 4: Record the Times and Ratings of Performance Step 5: Average Observed Time Step 6: Normal Time Step 7: Allowance Step 8: Standard Time

11 Collected Data [page 19] :

12 Precedence Diagram [page 21]

13 Initial Process Control Chart

14 Evaluation Results Items Designed Results Actual Results Cycle Time
[page 24] Items Designed Results Actual Results Cycle Time 1.08 Min. 0.588 Min. Idle Time 71.74 % 48.09 % Efficiency 28.26 % 51.91 % Production Rate 55 Piece/Hr. 102 Piece/Hr. No. of Work Station 61 Total Process Time Min. Production Cost 90.70 TK/Piece Selling Price 99.96 TK/Piece Productivity 1.102

15 Improvement

16 Reasons for Improvement
Efficiency % bellow the standard Productivity close to minimum level Existing line is unbalanced

17 Sequential Improvement Technique
[page 9] It has three sequential steps: Step 1: Withdrawal of Idle Resources Step 2: Redistribution of Tasks Step 3: Bottleneck Reduction a. By Existing Resources & b. By Additional Resources

18 Summary after Withdrawal of Idle Resources
[page 28] Items Before Improvement After Improvement Cycle Time 1.08 Min. Idle Time 71.74 % 70.86 % Efficiency 28.26 % 29.14 % Production Rate 55 Piece/Hr. No. of Work Station 61 Total Process Time Min. Min. No. of M/C & Operator 46 41 No. of Helper 34 33

19 Summary after Redistribution of Tasks
[page 34] Items Before Improvement After Improvement Cycle Time 1.08 Min. Idle Time 71.74 % 64.22 % Efficiency 28.26 % 35.78 % Production Rate 55 Piece/Hr. No. of Work Station 61 50 Total Process Time Min. Min. No. of M/C & Operator 46 41 No. of Helper 34 22

20 Manufacturing Cost after Improvement
[page 41] With existing Resources:

21 Comparative Summary after Improvement
[page 41] With Existing Resources:

22 Manufacturing Cost after Improvement
[page 42] With Additional Resources:

23 Comparative Summary after Improvement
[page 42] With Additional Resources:

24 Improvement in Terms of Money
[page 43] By using Sequential Improvement Technique: Profit gain = TK Time saving = ( ) days = 5.1 days By this time the industry can also gain, = (4576 piece/day)*(15.05 TK/piece)*(5.1 days) = TK So, Total additional profit gain by improvement, = ( ) TK = TK

25 Achievement of Objectives

26 Idle Time Reduction at Different Stages of Improvement

27 Productivity Gain at Different Stages of Improvement

28 Analytical Results Considering Different Allowance

29 Productivity Gain for Different Allowance

30 Efficiency Gain for Different Allowance

31 Errors/Mistakes in Our Report

32 Major Mistakes In page 1: A world dominating business sector can fall down suddenly. (organization) In page 4: Average observed valve. (value) In page 15: After Introduction we have used STEP: ONE. (before STEP: ONE will be 4.2 Six-Step Assembly Line Balancing & after STEP: ONE will be Time Study) In page 25 & 28: The given control charts are wrong. In page 34: We have used 39.3 % allowance. (20 %). In page 37: Typing mistake for value of SSV & SMV.

33 Limitations of this Thesis

34 Limitations Assumption about the current method.
Omission of performance rating. Omission of cross study for different product. Lack of our experience.

35 Thank You

36 Questions ???


Download ppt "Welcome."

Similar presentations


Ads by Google